Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 70409: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT - CUSTER
Project Number:
Title:
Pahsimeroi River Habitat
BPA PM:
Stage:
Complete
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
70409
Contract Title:
2008-603-00 EXP PAHSIMEROI RIVER HABITAT - CUSTER
Contract Continuation:
Previous: Next:
66757: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT - CUSTER
  • 74491: 2008-603-00 EXP PAHSIMEROI RIVER HABITAT - CUSTER
Contract Status:
Closed
Contract Description:
Work proposed in this statement of work will allow completion of three projects that are ongoing from contract #66527. The Environmental Assessment development was much slower than anticipated for the P-16 project. The work window for terrestrial species near P-16/Furey Lane did not allow work to start until after July 15, 2015 which shortens the window of construction for both the on-farm work and the diversion. IDFG is also in the process of installing a fish screen. If the screen is not installed early in September we will not be able to complete installation of the on-farm work due to the loss of water to the two properties that depend on the water through the end of irrigation season.  All diversion work will be complete from last year's contract with exception of the fence and 90% of the on-farm work will be complete. The riparian fence on the Pahsimeroi river at Furey Lane will be delayed to this contract to allow all the diversion and screening work to be completed prior to constructing the fence.

This SOW also includes two culvert removals that are serving as passage barriers. Bridges were ordered from last FY contract but could not be completed due to cultural survey requests being delayed via the BOR. Reports from a BOR hired contractor should be provided before the close of the #66527 contract. EC has been completed but will be re-vised for this year's contract and a new HIP III completed for the new contract. A feed-lot area near one of the bridges will also be treated to remove the cattle from the stream bank, fence installed and off stream stock water installed. The stock-water system was planned for the last FY contract but was not completed due to cultural. The delay will provide for a better project by providing a separation between the livestock and the stream with fence and a berm to prevent sediment from the livestock operation.

P-17 diversion is immediately upstream from the P-16/Furey Lane project. This statement of work addresses planning and consultation for this project with implementation scheduled in 2017. The BLM and Custer SWCD have a good working template from the P-16 EA that will make consultation more streamlined but will still take at least a full year to complete. This project was one of the top priorities for the Upper Pahsimeroi work group. In addition the Custer SWCD would request support from OSC and BPA to complete the consultation through the Programmatic process in the same manner as the P-16 project was completed. This project would likely not require a new diversion and instream work but would address a water conservation pipeline to provide water savings and a fish screen installed by IDFG screen shop. This would be a combined partnership effort to complete this project much in the same way the P-16 project was implemented. NRCS would provide design and assist in implementation for the Irrigation infrastructure and IDFG would design and implement the fish screen. BLM would assist in a cultural survey with the remaining cultural on the private property completed through a contract for cultural.

There are also multiple opportunities for riparian fencing in the Pahsimeroi and Patterson/Big Springs Creek as the Custer SWCD continue to work with landowners. Custer SWCD will continue to work with the Pahsimeroi group to identify and prioritize these projects. Additional focus needs to be paid to those projects reaching their project life of 15 years and should be addressed for either future maintenance or re-construction. With a staff assistance the Custer SWCD will be able to better identify the projects that are in need of improvement.
Account Type(s):
Expense
Contract Start Date:
09/26/2015
Contract End Date:
09/25/2016
Current Contract Value:
$489,620
Expenditures:
$489,620

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
All administrative tasks fulfilled with timely quality products B: 119. Manage and administer projects within this contract for FY 15/16 09/25/2016 09/25/2016
Upload prioritized project list to Pisces C: 114. Identify and Select projects based on partnership coordination with Pahsimeroi Group 07/01/2016 07/05/2016
Obtain or complete Environmental consultation documents and provide to BPA D: 165. Produce EC documents on identified projects 09/25/2016 09/25/2016
Produce Design and/or Specifications E: 175. Produce Design and/or Specifications for P-17 09/23/2016 09/23/2016
Progress Report has been published F: 132. Submit Progress Report for the period September 26, 2014 thru September 25, 2015 02/19/2016 02/05/2016
Remove partial barrier on Spring Creek/Pahsimeroi near McCoy Lane G: 85. Remove Fish Barrier at Lone Pine near McCoy Lane 03/31/2016 10/27/2015
Install Bridge to replace undersized existing culvert. H: 184. Install bridge at Lone Pine near McCoy Lane 03/31/2016 10/30/2015
Remove fish barrier culvert on McCoy Lane on the County Road I: 85. Remove Fish Barrier near McCoy Lane #2 03/31/2016 10/30/2015
Install Bridge McCoy Lane on the County Road J: 184. Install bridge near McCoy Lane #2 03/31/2016 11/30/2015
Install stock-water pipeline & stock tanks to replace in-stream water from Hamilton Ditch K: 34. Install Off Stream Stockwater at P16 to replace Hamilton/P16/Pahsimeroi Stockwater 09/25/2016 09/25/2016
Install remaining sprinkler irrigation for Furey Lane Project L: 203. Install remaining sprinkler irrigation for Furey Lane Project 09/01/2016 09/23/2016
Install Riparian Post and Wire Fence to meet wild life specifications. M: 40. Install riparian fence near Furey Lane diversion and fish screen 03/31/2016 11/30/2015
Install stock-water, pipeline & stock tanks to replace in-stream watering from Pahsimeroi/Goldberg N: 34. Install off Stream Stockwater at McCoy Lane 08/31/2016 09/25/2016
Install berm/erosion control barrier on Lone Pine to address confined cattle area O: 55. Install erosion control barrier on Lone Pine to address confined cattle area. 09/23/2016
Install Post and Pole Fence along sediment barrier on Lone Pine to exclude livestock P: 40. Install riparian fence along sediment barrier on Lone Pine 09/23/2016 09/23/2016
Remove Culvert at Flying Joe Q: 85. Remove Flying Joe Culvert 09/23/2016
Install Flying Joe Bridge R: 184. Install Bridge to Replace Flying Joe Culvert 09/23/2016
Remove Culvert on Muddy Springs (Phase I) S: 85. Remove Culvert on Muddy Springs (Phase I) 09/23/2016
Breach P-15 irrigation diversion from the Pahsimeroi T: 85. Remove and Rehab Closed P-15 Diversion 09/23/2016 09/16/2016
Install Bridge at the DR Ranch in the Upper Pahsimeroi U: 184. Install Bridge at DR Ranch in Upper Pahsimeroi 09/23/2016 09/19/2016
Purchase Pipe for the P-17 pipeline project V: 203. Purchase Pipe for P-17 Water Conservation Project 09/23/2016
Provide designs and specifications for 2 bridges in the Upper Pahsimeroi W: 175. Contract with Private Engineer to Produce Designs and Specs for two Bridges 08/12/2016 05/27/2016
Install Fence on the DR Ranch to protect the Pahsimeroi X: 40. Install Fence on DR Ranch to protect the Pahsimeroi 09/23/2016
Complete maintenance on approximately 6000 feet of existing Jack Post and Pole Riparian Fence Y: 186. Monitor, maintain and extend fencing contracts on existing BPA investments 09/23/2016 09/23/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 2 instances of WE 203 Install Water Conservation Measure
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 34 Develop Alternative Water Source
  • 3 instances of WE 40 Install Fence
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 5 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 4 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 175 Produce Design
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 2 instances of WE 203 Install Water Conservation Measure
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 34 Develop Alternative Water Source
  • 2 instances of WE 40 Install Fence
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 5 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 4 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 09/26/2015
B 119 Manage and administer projects within this contract for FY 15/16 09/26/2015
C 114 Identify and Select projects based on partnership coordination with Pahsimeroi Group 09/26/2015
D 165 Produce EC documents on identified projects 09/26/2015
E 175 Produce Design and/or Specifications for P-17 09/26/2015
F 132 Submit Progress Report for the period September 26, 2014 thru September 25, 2015 09/26/2015
G 85 Remove Fish Barrier at Lone Pine near McCoy Lane 09/26/2015
H 184 Install bridge at Lone Pine near McCoy Lane 09/26/2015
I 85 Remove Fish Barrier near McCoy Lane #2 09/26/2015
J 184 Install bridge near McCoy Lane #2 09/26/2015
K 34 Install Off Stream Stockwater at P16 to replace Hamilton/P16/Pahsimeroi Stockwater 09/26/2015
L 203 Install remaining sprinkler irrigation for Furey Lane Project 09/26/2015
M 40 Install riparian fence near Furey Lane diversion and fish screen 09/26/2015
N 34 Install off Stream Stockwater at McCoy Lane 09/07/2016
O 55 Install erosion control barrier on Lone Pine to address confined cattle area.
P 40 Install riparian fence along sediment barrier on Lone Pine 09/07/2016
Q 85 Remove Flying Joe Culvert
R 184 Install Bridge to Replace Flying Joe Culvert
S 85 Remove Culvert on Muddy Springs (Phase I)
T 85 Remove and Rehab Closed P-15 Diversion 08/10/2016
U 184 Install Bridge at DR Ranch in Upper Pahsimeroi 08/10/2016
V 203 Purchase Pipe for P-17 Water Conservation Project 03/31/2016
W 175 Contract with Private Engineer to Produce Designs and Specs for two Bridges 03/31/2016
X 40 Install Fence on DR Ranch to protect the Pahsimeroi 08/10/2016
Y 186 Monitor, maintain and extend fencing contracts on existing BPA investments 03/31/2016