Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 70707: 2010-057-00 EXP B-RUN STEELHEAD SUPPLEMENTATION
Project Number:
Title:
Snake Basin Steelhead Assessments
Stage:
Implementation
Area:
Province Subbasin %
Basinwide - 100.00%
Contract Number:
70707
Contract Title:
2010-057-00 EXP B-RUN STEELHEAD SUPPLEMENTATION
Contract Continuation:
Previous: Next:
67492: 2010-057-00 EXP B-RUN STEELHEAD SUPPLEMENTATION
  • 74546: 2010-057-00 EXP CLEARWATER B-RUN STEELHEAD MONITORING/EVALUATION
Contract Status:
Closed
Contract Description:
This project provides: 1) hatchery (supplementation and conventional) monitoring on B-run steelhead (Oncorhynchus mykiss) released in the Clearwater River subbasin, 2) incorporation and validation of PIT tag array-based status and trend estimates of adult abundance, 3) descriptive biological data on natural-origin returns, and 4) facilitation of a run-reconstruction of Snake Basin steelhead to known and unknown areas (formally proposal 2010-04-800). Carried out by co-managers, the Nez Perce Tribe (NPT) and the Idaho Department of Fish and Game (IDFG), this project will play a critical role in increasing the existing understanding of two significant populations of B-run steelhead in the Clearwater River major population group (MPG), the Lolo Creek and the South Fork Clearwater River (SFCR) populations. Data generated through the implementation of this project is required under the FCRPS BiOp (RPAs 63.1, 71 and 72) and is consistent with the Coordinated Anadromous Workshop Snake Basin strategy for high precision abundance data, hatchery effectiveness monitoring, and data management.

The 2008-2017 U.S. vs Oregon Management Agreement designated 200,000 unclipped (supplementation) steelhead reared at Dworshak National Fish Hatchery (DNFH) released into Lolo Creek and 330,000 unclipped steelhead reared at the Clearwater Anadromous Fish Hatchery (CAFH) released into tributaries of the South Fork Clearwater River (SFCR). These releases are in addition to the 840,000 conventionally reared, AD-clipped, steelhead smolts released into the SFCR each year. The motivation behind the unclipped fish releases is escapement from down-river fisheries and increased contribution to natural production to bolster natural steelhead population abundances. The brood stock composition of the supplementation releases (e.g., integration of natural adults into the brood stock) and the increase of these releases from the current level of 60,000 into Lolo Creek to full production (200,000) will be decided by tribal, state, and federal co-managers. Therefore, this project is structured as an observational study of management actions, as per the recommendation of ISRP/ISAB.

This project aims to evaluate the efficacy of these actions by 1) monitoring the population abundances of Lolo Creek and SFCR steelhead, 2) assessing the relative productivity, survival and behavior of natural and hatchery fish in Lolo Creek, and 3) comparing the relative performance of supplementation and conventional hatchery steelhead in the SFCR. Furthermore, the spatial distribution of returning natural, supplementation, and conventional adults in the SFCR will be followed to determine spatial overlap in the spawning distribution of these fish and to verify or refute the believed presence of a velocity barrier (near Golden) to returning steelhead in the SFCR. Finally, working in coordination with all co-managers in the Snake River Basin, including the U.S. Fish and Wildlife Service, The Shoshone-Bannock Tribe, Oregon Department of Fish and Wildlife, Washington Department of Fish and Wildlife, Washington Department Fish & Wildlife, and The Confederated Tribes of the Umatilla Indian Reservation, the data collected through the activities of this project will be intergrated with that of other monitoring projects to account for the final disposition of adults upstream of Lower Granite Dam for the purposes of run-reconstruction.

To perform these tasks the project will utilize existing resources and facilities as well as implement new monitoring activities. Within Lolo Creek, the permanent weir construction approved through the Fast Track proposal process (2010-038-00) will be used to monitor returning adults and to collect biological data such as age at return, size at return, and sex ratio. Genetic sampling conducted at the weir will be used to conduct relative reproductive success analyses. The weir will also serve to validate the passage data collected through the use of PIT tag arrays (installed and operated under Project 2003-017-00) located above and below the weir. Screw trap operation in Lolo Creek currently implemented under the Nez Perce Tribal Hatchery Monitoring and Evaluation Project (1983-350-03) will serve to collect data used to calculate juvenile abundance, assess size and condition at emigration, and sample individuals for age and genetic analysis. Under this project, a screw trap would be installed in the SFCR to monitor juveniles leaving that system and, similar to Lolo Creek, PIT tag arrays located near the mouth of the SFCR and downstream of release tributaries (installed and operated under Project 2003-017-00) would be used to collect data on returning adults.

In addition to these activities, this project will incorporate a suite of tagging technologies to improve the information currently available on the status of steelhead populations in the Clearwater River subbasin. Supplementation juveniles will be coded wire tagged to distinguish these individuals from natural fish as adults. Juveniles will be PIT tagged at the Lolo Creek and SFCR screw traps to determine juvenile abundance and survival through the hydrosystem using mark-recapture analyses. Finally, a subset of the adults returning to SFCR will be captured, utilizing Separation by Code at Lower Granite Dam of know SFCR destined fish, and with the assistance of volunteer anglers and radio tagged to evaluate the spatial distribution of these fish in the SFCR.

An important goal of this project is the timely reporting of science-based data. The Nez Perce Tribe Department of Fisheries Resource Management (DFRM) now has the equipment infrastructure necessary to ensure that this will be achieved. With additional funding for a data steward, DFRM annual reports, metadata, and performance measure data will be available on the new DFRM website http://www.nptfisheries.org. Appropriate components of program data and results will also be provided to the following websites: Snake Basin Data Group; Pacific States Marine Fisheries Commission (PSMFC), including: PIT Tag Information System (PTAGIS), the Regional Mark Information System (RMIS); Integrated Status and Effectiveness Monitoring Program (STEM); Fish Passage Center (FPC); StreamNet; and NOAA Northwest Science Center. This proposal seeks to enable DFRM participation in regional data management and sharing forums and processes (e.g. PNAMP) as required by RPAs 71 and 72.
Account Type(s):
Expense
Contract Start Date:
01/01/2016
Contract End Date:
12/31/2016
Current Contract Value:
$505,779
Expenditures:
$505,779

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brett Bowersox Idaho Department of Fish and Game (IDFG) No Technical Contact brett.bowersox@idfg.idaho.gov (208) 465-8404
Peter Cleary Nez Perce Tribe Yes Contract Manager peterc@nezperce.org (208) 621-3572
Daniel Gambetta Bonneville Power Administration Yes Env. Compliance Lead dagambetta@bpa.gov (503) 230-3493
Jay Hesse Nez Perce Tribe Yes Supervisor jayh@nezperce.org (208) 621-3552
Amber MacLachlan Bonneville Power Administration Yes Contracting Officer almcmahon@bpa.gov (503) 230-3983
Russell Scranton Bonneville Power Administration Yes COR rwscranton@bpa.gov (503) 230-4412
Jason Vogel Nez Perce Tribe Yes Technical Contact jasonv@nezperce.org (208) 621-3602
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479
William Young Nez Perce Tribe Yes Supervisor billy@nezperce.org (208) 634-5290


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Maintain Environmental Compliance A: 165. Maintain Environmental Compliance 12/31/2016 12/27/2016
Analyze and interpret comprehensive NPT generated data. B: 162. Analyze and Interpret NPT Generated RPA Data Sets 12/31/2016
Submit BiOp RPA Report C: 202. BiOp RPA Report for CY 2015 03/15/2016 03/31/2016
Coordinate a Monitoring and Evaluation Plan for B-Run Hatchery Origin Steelhead D: 189. Coordinate the B-Run Steelhead Supplementation Monitoring Project 12/31/2016 12/27/2016
Install a Rotary Screw Trap on South Fork Clearwater River E: 70. Plan and Initiate Operation of Rotary Screw Trap on South Fork Clearwater River 09/01/2016 08/11/2016
Submit Spring Data Records to PTAGIS F: 157. Operate a Rotary Screw Trap for Juvenile Steelhead During the Spring Migration 12/31/2016
Submit Fall Data Records to PTAGIS G: 157. Operate a Rotary Screw Trap for Juvenile Steelhead During the Fall Migration 12/31/2016
PIT Tag South Fork Clearwater River and Lolo Creek Steelhead H: 158. Insert PIT Tags into Juvenile Steelhead on South Fork Clearwater River 11/23/2016 12/07/2016
Insert Radio Transmitters into Adult Steelhead at Lower Granite Dam and South Fork Clearwater I: 158. Coordinate Adult Steelhead Tagging at Lower Granite Dam and South Fork Clearwater 10/31/2016 10/31/2016
Install Fixed Radio Telemetry Receivers J: 70. Install Fixed Radio Telemetry Receivers 02/29/2016 03/24/2016
Spawner Distribution of South Fork Clearwater River Steelhead K: 157. Track Movement of Adult Steelhead in the South Fork Clearwater River 12/31/2016
Evaluation of Supplementation in Lolo Creek and South Fork Clearwater River L: 162. Evaluation of Supplementation in Lolo Creek and South Fork Clearwater River for 2016 12/31/2016
Operate and Maintain Nez Perce Tribe File Share Server M: 160. Operate and Maintain Nez Perce Tribe File Share Server 12/31/2016 12/27/2016
Communication of Results N: 161. Communication of Results 12/31/2016 12/27/2016
Populate and validate NPT project specific data in standardized/centralized databases O: 160. Populate and Validate NPT Project Specific Data in Standardized/Centralized Databases 12/31/2016 12/27/2016
Completed Annual Report P: 132. Submit Progress Report for the period (Jan 2015 - Dec 2015) 12/27/2016
All administrative tasks fulfilled with timely quality products Q: 119. Manage and Administer B-run Steelhead Supplementation Monitoring Project 12/31/2016 12/27/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 2 instances of WE 70 Install Fish Monitoring Equipment
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 158 Mark/Tag Animals
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
  • 2 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Maintain Environmental Compliance 01/01/2016
B 162 Analyze and Interpret NPT Generated RPA Data Sets 01/01/2016
C 202 BiOp RPA Report for CY 2015
D 189 Coordinate the B-Run Steelhead Supplementation Monitoring Project 01/01/2016
E 70 Plan and Initiate Operation of Rotary Screw Trap on South Fork Clearwater River
F 157 Operate a Rotary Screw Trap for Juvenile Steelhead During the Spring Migration 01/01/2016
G 157 Operate a Rotary Screw Trap for Juvenile Steelhead During the Fall Migration 01/01/2016
H 158 Insert PIT Tags into Juvenile Steelhead on South Fork Clearwater River 01/01/2016
I 158 Coordinate Adult Steelhead Tagging at Lower Granite Dam and South Fork Clearwater 01/01/2016
J 70 Install Fixed Radio Telemetry Receivers 01/01/2016
K 157 Track Movement of Adult Steelhead in the South Fork Clearwater River 01/01/2016
L 162 Evaluation of Supplementation in Lolo Creek and South Fork Clearwater River for 2016 01/01/2016
M 160 Operate and Maintain Nez Perce Tribe File Share Server 01/01/2016
N 161 Communication of Results 01/01/2016
O 160 Populate and Validate NPT Project Specific Data in Standardized/Centralized Databases 01/01/2016
P 132 Submit Progress Report for the period (Jan 2015 - Dec 2015) 01/01/2016
Q 119 Manage and Administer B-run Steelhead Supplementation Monitoring Project 01/01/2016
R 185 Periodic Status Reports for BPA 01/01/2016