Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 72029: 2016-001-00 EXP PROJECT ACTION EFFECTIVENESS MONITORING (AEM)
Project Number:
Title:
BPA Project Action Effectiveness Monitoring (AEM) Programmatic
BPA PM:
Stage:
Complete
Area:
Province Subbasin %
Basinwide - 100.00%
Contract Number:
72029
Contract Title:
2016-001-00 EXP PROJECT ACTION EFFECTIVENESS MONITORING (AEM)
Contract Continuation:
Previous: Next:
n/a
  • 74745: 2016-001-00 EXP PROJECT ACTION EFFECTIVENESS MONITORING (AEM)
Contract Status:
Closed
Contract Description:
This contract provides technical support and implementation assistance for BPA's Programmatic Approach for Action Effectiveness Monitoring (AEM).  The contractor will collect, analyze, and interpret data under the Multiple Before After Control Impact (MBACI) protocol, work collaboratively with other BPA Fish and Wildlife Program sponsors to select control and treatment sites, and produce annual reports to disseminate the results for BPA funded projects that participate in the AEM Program.  This professional analysis and collaboration will guide and provide continuous adaptive management for habitat restoration actions that address habitat impairments with the objective of improving the productivity, abundance, and distribution of ESA listed anadromous fish species throughout the Columbia River Basin (ESU/DPSs).

Under this contract Natural Systems Design will:

1. Identify and conduct site visits to confirm control and treatment sites for floodplain, partial passage barriers, bank stabilization, fencing, and land acquisition projects to be monitored in the 2016 field season
2. Monitor and collect habitat, fish, and macroinvertebrate data for both planned and implemented projects funded by BPA
3. Summarize, analyze, and report on the effectiveness of habitat restoration projects evaluated in the 2016 field season
4. Begin site reconnaissance for projects to be evaluated in 2017
5. Participate in meetings to coordinate AEM activities and assure consistency of monitoring protocols
Account Type(s):
Expense
Contract Start Date:
01/22/2016
Contract End Date:
12/31/2016
Current Contract Value:
$746,955
Expenditures:
$746,955

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Firm Fixed Price
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Jan Douglas Bonneville Power Administration Yes Contracting Officer jmdouglas@bpa.gov (503) 230-4164
Leif Emberston Natural Systems Design No Supervisor leif@naturaldes.com (206) 834-0175
David Kaplowe Bonneville Power Administration Yes COR djkaplowe@bpa.gov (503) 230-5365
Jennifer O'Neal Natural Systems Design Yes Contract Manager jen@naturaldes.com (425) 785-0510
Jennifer Snyder Bonneville Power Administration Yes Env. Compliance Lead jasnyder@bpa.gov (503) 230-4187
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
EC Documentation Approved by BPA EC Lead A: 165. Environmental Compliance 06/30/2016 03/31/2016
Coordination for BPA AEM Program B: 189. Coordination with BPA and Project Sponsors 12/31/2016 12/27/2016
Technical Assistance for BPA's Atlas Framework C: 122. Participate in BPA's Atlas Habitat Restoration Prioritization Initiative 12/31/2016 12/27/2016
Protocol Development and Training D: 156. Protocol and Training Development 07/31/2016 07/31/2016
Physical Habitat and Fish Data E: 157. Habitat and Fish Data Collection for AEM Program 11/30/2016 11/30/2016
Data Analysis and Interpretation F: 162. Summarize and Analyze AEM Fish and Habitat Data 11/30/2016 11/30/2016
FY 2017 Contract Package and FY 2016 Accrual Estimate G: 119. Contract Management and Administration 10/21/2016 10/21/2016
2015 Annual Report for MBACI AEM H: 132. Submit Progress Report for 1/1/15 - 12/31/15 02/29/2016 03/31/2016
Comments and Suggested Revisions J: 122. RM&E Synthesis Review 08/15/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 162 Analyze/Interpret Data
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (Oncorhynchus mykiss) - All Populations
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance 01/01/2016
B 189 Coordination with BPA and Project Sponsors 01/01/2016
C 122 Participate in BPA's Atlas Habitat Restoration Prioritization Initiative 01/01/2016
D 156 Protocol and Training Development 03/23/2016
E 157 Habitat and Fish Data Collection for AEM Program 03/23/2016
F 162 Summarize and Analyze AEM Fish and Habitat Data 01/01/2016
G 119 Contract Management and Administration 01/01/2016
H 132 Submit Progress Report for 1/1/15 - 12/31/15 01/01/2016
I 185 Periodic Status Reports for BPA 01/01/2016
J 122 RM&E Synthesis Review 01/22/2016