| Environmental Compliance |
A: 165. Obtain NEPA Compliance |
|
03/31/2017 |
03/31/2017 |
| Final Design for Phase 5 |
B: 175. Coordinate with Reclamation on Completion of Design and Plans for Phase 5 |
|
12/30/2016 |
06/30/2016 |
| Information Sign Updating, Access Regulation, Hunting Program |
C: 188. Provide Access, Signs, and Adequate Roads |
|
03/31/2017 |
03/31/2017 |
| Project Outreach and Opportunities, Information Distribution |
D: 99. Public Access and Volunteer Coordination |
|
03/31/2017 |
03/31/2017 |
| Facility Maintenance |
E: 186. Maintain Facilities and Structures throughout the Property |
|
03/31/2017 |
03/31/2017 |
| Property Patrol |
F: 26. Property Patrol |
|
03/31/2017 |
03/31/2017 |
| Establish Vegetation |
G: 47. Plant Seed and Locally Collected Cuttings |
|
12/16/2016 |
12/16/2016 |
| Completed Grazing Season |
H: 92. Grazing Program Oversight and Management |
|
03/31/2017 |
03/31/2017 |
| Fish, Habitat, Temperature, Weather and Flow Data |
I: 157. Steelhead Redd Counts |
|
03/31/2017 |
03/01/2017 |
| Fish Data |
J: 157. Juvenile Fish Count Surveys |
|
03/31/2017 |
03/01/2017 |
| Weather Data |
K: 157. Weather Data Management |
|
03/31/2017 |
03/01/2017 |
| Stream Temperature Data |
L: 157. Stream Temperature Monitoring |
|
03/31/2017 |
03/01/2017 |
| Irrigation Data |
M: 157. Irrigation Monitoring |
|
03/31/2017 |
03/31/2017 |
| Oxbow Tailings Monitoring and Maintenance Plan Data |
N: 157. Tailings Project Monitoring and Maintenance Plan Work |
|
03/31/2017 |
03/01/2017 |
| Data Synthesis for Report and Storage of Data with Appropriate Metadata |
O: 162. Oxbow Conservation Area fish and Environmental Conditions Data Analysis |
|
11/01/2016 |
|
| Photo for 2016 |
P: 115. Photopoint Inventory |
|
03/31/2017 |
03/01/2017 |
| Conduct Steelhead and Chinook Redd Surveys with ODFW |
Q: 191. Conduct Steelhead and Chinook Redd Surveys with ODFW |
|
09/30/2016 |
09/30/2016 |
| Property Noxious Weed Control Activities |
R: 199. Property Noxious Weed Control Activities |
|
10/28/2016 |
10/28/2016 |
| Complete Phase 4 and 5 Tailings Remediation |
S: 30. Complete a Portion of Phase 4 and all of Phase 5 Tailings Remediation |
|
10/28/2016 |
10/28/2016 |
| Coordination and Monitoring Efforts for the Middle Fork John Day IMW Group |
T: 191. Coordination and Monitoring Efforts for the Middle Fork John Day IMW Group |
|
03/31/2017 |
03/01/2017 |
| Protect and Maintain Riparian Vegetation |
U: 198. Protect Riparian Vegetation |
|
12/30/2016 |
11/30/2016 |
| Completed Annual Report |
V: 132. Submit Progress Report for the Period (April 2015) to (March 2016) |
|
03/31/2017 |
03/31/2017 |
| Project Management |
X: 119. Manage and Administer Tribal Projects and BPA Activities |
|
03/31/2017 |
03/31/2017 |