Contract 72876: 2007-155-00 EXP CRITFC STURG HATCHERY STEP 2
Project Number:
Title:
Develop a Master Plan for a Rearing Facility to Enhance Selected Populations of White Sturgeon in the Columbia River Basin
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Columbia Lower Middle 100.00%
Contract Number:
72876
Contract Title:
2007-155-00 EXP CRITFC STURG HATCHERY STEP 2
Contract Continuation:
Previous: Next:
69433: 2007-155-00 EXP DEVELOP A MASTER PLAN FOR A RE
  • 76837: 2007-155-00 EXP DEVELOP A MASTER PLAN FOR A REARING FACILITY
Contract Status:
Closed
Contract Description:
In this contract year we will  
1)  complete Step I of the Hatchery Master Planning Process through the ISRP review and NPCC acceptance, and  
2) initiate  Step 2 of the process including the NEPA review.
Account Type(s):
Expense
Contract Start Date:
07/01/2016
Contract End Date:
06/30/2017
Current Contract Value:
$73,340
Expenditures:
$73,340

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
All administrative tasks fulfilled with timely quality products B: 119. Contract Development and Direction 06/30/2017 06/30/2017
Step 2: Preliminary design, 30% cost estimate & EC completed & submitted to NPCC C: 196. STEP 2: Initiate Master Plan Step 2 Tasks 06/30/2017
Step 2 Environmental Compliance Documents D: 165. STEP 2: Assist with NEPA process contracted by BPA 06/30/2017
STEP 2: Facility Preliminary design & 30% cost estimate E: 175. STEP 2: Facility Preliminary design & 30% cost estimate 06/30/2017

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Sturgeon, White (Acipenser transmontanus) - All Populations except Kootenai R. DPS
  • 1 instance of WE 196 Council Step Process
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 07/01/2016
B 119 Contract Development and Direction 07/01/2016
C 196 STEP 2: Initiate Master Plan Step 2 Tasks
D 165 STEP 2: Assist with NEPA process contracted by BPA 07/01/2016
E 175 STEP 2: Facility Preliminary design & 30% cost estimate 07/01/2016
F 132 Master Plan will suffice for annual report 07/01/2016