| Province | Subbasin | % |
|---|---|---|
| Columbia Cascade | Okanogan | 100.00% |
| Previous: | Next: |
|---|---|
| 69697: 1996-042-00 EXP RESTORE SALMON CREEK ANADROMOUS FISH |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Environmental Compliance Requirements Complete | B: 165. Environmental Compliance Requirements | 07/31/2017 | 06/23/2017 | |
| All administrative tasks fulfilled with timely quality products | C: 119. Fulfill all administrative tasks with quality products in a timely manner | 07/31/2017 | 06/23/2017 | |
| Coordinate annual activities with landowners, local govts., irrigation district, WDFW and UCR | D: 191. Coordinate annual activities with landowners, local govts., OID, WDFW, and UCRSRB | 06/30/2017 | 06/30/2017 | |
| Evaluation of fish passage conditions during controlled releases. | E: 186. Evaluate fish passage conditions during controlled releases | 07/14/2017 | 06/30/2017 | |
| Develop a design to reduce sediment delivery and reestablish riparian corridor | F: 175. Develop design to abate sediment and reduce risk of stream channel avulsion at private crossin | 03/31/2017 | ||
| Complete design for construction of a diversion dam on the North Fork of Salmon Creek | G: 175. Design and oversee construction of the irrigation diversion on the N.F. Salmon Creek | 12/01/2016 | ||
| Construct a diversion dam on North Fork of Salmon Creek | H: 84. Install diversion on N. F. Salmon Creek | 11/15/2016 | ||
| Completed 2014 Annual Report | I: 132. Placeholder:Submit Progress Report for the period 8/1/2014 to 7/31/2015 | 09/30/2016 | 09/30/2016 | |
| Completed Annual Report | J: 132. Submit Progress(Annual) Report for the period 8/1/2015 to 7/31/2016 | 05/31/2017 | 05/31/2017 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 185 | Periodic Status Reports for BPA | 08/01/2016 | ||||||
| B | 165 | Environmental Compliance Requirements | 08/01/2016 | ||||||
| C | 119 | Fulfill all administrative tasks with quality products in a timely manner | 08/01/2016 | ||||||
| D | 191 | Coordinate annual activities with landowners, local govts., OID, WDFW, and UCRSRB | 08/01/2016 | ||||||
| E | 186 | Evaluate fish passage conditions during controlled releases | 08/01/2016 | ||||||
| F | 175 | Develop design to abate sediment and reduce risk of stream channel avulsion at private crossin | 08/01/2016 | ||||||
| G | 175 | Design and oversee construction of the irrigation diversion on the N.F. Salmon Creek | 08/01/2016 | ||||||
| H | 84 | Install diversion on N. F. Salmon Creek | |||||||
| I | 132 | Placeholder:Submit Progress Report for the period 8/1/2014 to 7/31/2015 | 08/01/2016 | ||||||
| J | 132 | Submit Progress(Annual) Report for the period 8/1/2015 to 7/31/2016 | 08/01/2016 |