| Receipt of environmental compliance clearance from BPA. |
A: 165. Complete/initiate Environmental Permitting for Project Activities |
|
04/30/2021 |
04/30/2021 |
| Complete cultural resource investigations on Rock Creek. |
B: 165. Complete/initiate Section 106 Process for Rock Creek Water Developments, Fences, and Planting |
|
04/30/2021 |
|
| Develop Project Design Drawings and Specifications |
C: 174. Develop project designs and produce plans (Middle Upper Grande Ronde Phases 2 and 3) |
|
04/30/2021 |
04/30/2021 |
| Effective implementation management and timely contract administration |
D: 119. Middle Upper Grande Ronde River Fish Habitat Enhancement Project Administration |
|
04/30/2021 |
|
| Develop Project Design Drawings and Specifications |
E: 174. Develop project designs and produce plans (Longley Meadows) |
|
04/30/2021 |
08/03/2020 |
| Effective implementation management and timely contract administration |
F: 119. Longley Meadows Fish Habitat Enhancement Project Administration |
|
04/30/2021 |
04/30/2021 |
| Conduct Fish Salvage Operations |
G: 28. Conduct Fish Salvage Operations (Longley Meadows) |
|
10/15/2020 |
10/30/2020 |
| Maintain vegetation and control weeds on conservation projects |
H: 198. Maintain Vegetation and Control Weeds on conservation projects |
|
04/30/2021 |
04/30/2021 |
| Completed Corral System |
I: 40. Construct Livestock Corral (Relocated from Floodplain) |
|
11/20/2020 |
11/20/2020 |
| Conduct maintenance on McCoy, Dark Canyon, Meadow, Willow, Rock, Catherine Creek, and Grande Ronde River Projects |
J: 186. Maintain instream structures, fences, and off-channel water developments |
|
04/30/2021 |
04/30/2021 |
| Conduct ongoing project development and coordination activities |
K: 114. CTUIR Grande Ronde Subbasin Restoration Projects Coordination |
|
04/30/2021 |
04/30/2021 |
| BiOp Fish Habitat Project Opportunity Development and Review |
L: 114. Solicit, review &select BiOp expense & capital projects - Implementation Team & Technical Input |
|
04/30/2021 |
04/30/2021 |
| Administer Project |
M: 119. Manage and Administer CTUIR GR Subbasin Restoration Project |
|
04/30/2021 |
04/30/2021 |
| Complete outreach & education activities |
N: 99. Public Outreach and Education |
|
04/30/2021 |
04/30/2021 |
| Pre-project and post evaluations |
O: 186. Pre & post project evaluations |
|
04/30/2021 |
04/30/2021 |
| Upload Completion Report |
P: 141. Habitat Completion Reports |
|
04/30/2021 |
05/29/2020 |
| Upload 2020 Annual Report |
Q: 132. 2020 Annual Report - May 2020 - April 2021 |
|
04/30/2021 |
04/30/2021 |