Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 74017 REL 28: 1999-017-00 EXP NPT LAPWAI CREEK WATERSHED RESTORATION
Project Number:
Title:
Protect and Restore Lapwai Creek Watershed
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
74017 REL 28
Contract Title:
1999-017-00 EXP NPT LAPWAI CREEK WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
75888: 1999-017-00 EXP LAPWAI CREEK WATERSHED RESTORATION
  • 74017 REL 52: 1999-017-00 EXP LAPWAI CREEK WATERSHED RESTORATION
Contract Status:
Closed
Contract Description:
PROJECT/CONTRACT HISTORY:

Our mission is to work proactively within the region’s diverse landscapes to restore and protect the ecological processes of the Lapwai Creek watershed to the greatest extent possible.  We will work to rehabilitate habitat that will support healthy, self-sustaining fish populations and provide clean water for the benefit of all.  We will work within present challenges and opportunities toward achieving a balance whereby all communities can thrive for generations to come.

Hé-yey, Nez Perce for steelhead or rainbow trout (Oncorhynchus mykiss), are a culturally and ecologically significant resource of the Lapwai Creek watershed and compose a portion of the federally listed Snake River Basin Steelhead distinct population segment (DPS).  The majority of the Lapwai Creek drainage is federally identified as critical habitat for this DPS while also providing habitat for the federally listed Snake River Nacó’x, or fall chinook (Oncorhynchus tshawytscha), evolutionarily significant unit (ESU).  The Nez Perce Soil and Water Conservation District (District) and the Nez Perce Tribe Department of Fisheries Resources Management- Watershed (Tribe), in an effort to support the continued existence of these and other aquatic species, have developed the "Strategy for the Ecological Restoration of Lapwai Creek Watershed" document to direct efforts and resources toward the highest priority restoration projects and areas of the Lapwai Creek watershed.  The prioritization framework considered four aspects to determine the relative importance of performing restoration in a certain area: density of critical fish species, physical condition of the AU, water quantity, and water quality.  It was established, through vigorous data analysis within these four areas, that the top three areas to pursue restoration within the Lapwai Creek watershed are Lapwai Creek from stream km 17-34, Sweetwater Creek from the mouth to km 13 and from the mouth of Lapwai Creek to km 17.

SUMMARY OF CY 18 CONTRACT:

The "Strategy for the Ecological Restoration of Lapwai Creek Watershed," which was completed under the FY 07 contract, was the main reference for prioritizing implementation and developing the CY 18 SOW.  

Implementation projects planned for the 2018 SOW include the following:

A total of 7 sites, treating 23.85 acres.

o  Tribal Trust Unit 3123 Spring Creek Raceway- implementation of noxious weed control and maintenance of riparian planting on 1.0 acres.
o  Tribal Trust Unit 3123 Spring Creek Wetlands- implementation of noxious weed control on1.0 acres.
o  Tribal Trust Unit 3125 Fisheries Building -  implementation of noxious weed control and maintenance of riparian planting on 0.4 acres.
o  Tribal Allotment 365 - implementation of noxious weed control and maintenance of riparian plantings on 6.45 acres.
o  Tribal Allotment 419A - implementation of noxious weed control on 9.0 acres.
o  Lutes Wetland adjacent to Tribal Allotment 350 - implementation of noxious weed control and maintenance of plantings on 0.5 acres.
    
Instream Complexity - Implement Post Assisted Log Structure (PALS) project on Sweetwater Creek - Tribal Allotment 419A.

Floodplain Restoration - Lapwai Creek Reach 14A - implementation of channel reconstruction, riparian/floodplain reconnection, and riparian planting in Culdesac Canyon on 5.5 acres.

Outreach and Education-- Education and outreach will continue to the general public, fellow professionals, high school and college students, and especially elementary school students, e.g. the  "Steelhead in the Classroom" program for 6th graders. Partners include the Lapwai School District, Lewiston School District, and Idaho Department of Fish and Game.
Account Type(s):
Expense
Contract Start Date:
05/01/2018
Contract End Date:
04/30/2019
Current Contract Value:
$389,038
Expenditures:
$389,038

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Daniel Affonso Bonneville Power Administration No Interested Party dxaffonso@bpa.gov (503) 230-3893
Elisabeth Bowers Bonneville Power Administration Yes Interested Party ekbowers@bpa.gov (503) 230-5184
Marcie Carter Nez Perce Tribe Yes Supervisor marciec@nezperce.org (208) 621-3534
Heidi Haak Bonneville Power Administration No Interested Party hlhaak@bpa.gov (541) 922-6856
Arleen Henry Nez Perce Tribe No Administrative Contact arleenh@nezperce.org (208) 621-3833
Bobby Hills Nez Perce Tribe Yes Interested Party bobbyh@nezperce.org (208) 621-3537
Travis House Nez Perce Tribe Yes Contract Manager thouse@nezperce.org (208) 621-4739
Shawn Kaschmitter Nez Perce Tribe Yes Technical Contact shawnk@nezperce.org (208) 621-4728
Jennifer Lord Bonneville Power Administration Yes COR jklord@bpa.gov (503) 230-5192
Christopher Roper Bonneville Power Administration No CO Assistant cproper@bpa.gov (503) 230-3514
Carolyn Sharp Bonneville Power Administration Yes Env. Compliance Lead casharp@bpa.gov (503) 230-5206
Tybee Sheidler Bonneville Power Administration No CO Assistant tasheidler@bpa.gov (503) 230-3820
Emmit Taylor, Jr. Nez Perce Tribe Yes Interested Party emmitt@nezperce.org (208) 621-3544
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448
Elham Zolmajd-Haghighi Bonneville Power Administration No CO Assistant ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
ESA/NEPA/NHPA Compliance complete B: 165. ESA/NEPA/NHPA Compliance for Implementation Projects 04/30/2019 04/30/2019
1.0 Acres Maintenance of Native Vegetation on TU 3123 Spring Creek Raceway C: 198. Maintain Native Vegetation and Treat Exotic Invasive Plant Species on TU 3123 Spring Creek Raceway 04/30/2019 04/30/2019
1.0 Acres of Invasive Plant Species Controlled on TU 3123 Spring Creek Wetland D: 198. Treat Exotic Invasive Plant Species on TU 3123 Spring Creek Wetland 04/30/2019 04/30/2019
0.40 Acres Maintenance of Native Vegetation on TU 3125 Fisheries Building E: 198. Maintain Native Vegetation and Treat Exotic Invasive Plant Species TU 3125 Fisheries Building 04/30/2019 04/30/2019
5.45 Acres of Plant maintenance and weed control at TA 365 F: 198. Maintain Native Vegetation and Treat Exotic Invasive Plant Species on TA 365 04/30/2019 04/30/2019
0.5 acres of plant maintenance and weed control at Lutes wetland, adjacent to TA 350 G: 198. Maintain Native Vegetation and Treat Exotic Invasive Plant Species at Lutes Wetland 04/30/2019 04/30/2019
9.0 Acres of Invasive Plant Management on TA 419A H: 198. Treat Exotic Invasive Plant Species and seed native grasses on TA 419A 04/30/2019 04/30/2019
Lapwai Creek Education and Outreach I: 99. Lapwai Creek Project Area Education and Outreach 04/30/2019 04/30/2019
FY 18 SOW Package J: 119. Management, Coordination and Communication 04/30/2019 04/30/2019
Completed Annual Report K: 132. Submit Progress Report for the period May 2018 to April 2019 04/30/2019
Completed Annual Report L: 132. Confirm previous year's (May 2017- April 2018) progress report is uploaded 05/30/2018 06/29/2018
Environmental and Cultural Compliance for Sweetwater Creek - SW-03 M: 175. Environmental Compliance and Cultural Assessment for Restoration of Sweetwater Creek - SW-03 04/30/2019 04/30/2019
Sweetwater Creek - SW-03 PALS Installation N: 29. Sweetwater Creek (TA 419A) Post Assisted Log Structure (PALS) Installation 10/31/2018 10/31/2018
Lapwai Creek Reach 14A Floodplain Restoration O: 30. Lapwai Creek Reach 14A Floodplain Restoration 04/30/2019 04/30/2019

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 6 instances of WE 198 Maintain Vegetation
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 05/01/2018
B 165 ESA/NEPA/NHPA Compliance for Implementation Projects 05/01/2018
C 198 Maintain Native Vegetation and Treat Exotic Invasive Plant Species on TU 3123 Spring Creek Raceway 08/20/2018
D 198 Treat Exotic Invasive Plant Species on TU 3123 Spring Creek Wetland 08/20/2018
E 198 Maintain Native Vegetation and Treat Exotic Invasive Plant Species TU 3125 Fisheries Building 08/20/2018
F 198 Maintain Native Vegetation and Treat Exotic Invasive Plant Species on TA 365 08/20/2018
G 198 Maintain Native Vegetation and Treat Exotic Invasive Plant Species at Lutes Wetland 08/20/2018
H 198 Treat Exotic Invasive Plant Species and seed native grasses on TA 419A 08/20/2018
I 99 Lapwai Creek Project Area Education and Outreach 05/01/2018
J 119 Management, Coordination and Communication 05/01/2018
K 132 Submit Progress Report for the period May 2018 to April 2019 05/01/2018
L 132 Confirm previous year's (May 2017- April 2018) progress report is uploaded 05/01/2018
M 175 Environmental Compliance and Cultural Assessment for Restoration of Sweetwater Creek - SW-03 07/26/2018
N 29 Sweetwater Creek (TA 419A) Post Assisted Log Structure (PALS) Installation 08/20/2018
O 30 Lapwai Creek Reach 14A Floodplain Restoration 08/20/2018