| Province | Subbasin | % |
|---|---|---|
| Mountain Columbia | Flathead | 100.00% |
* Expenditures data includes accruals and are based on data through 31-Oct-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Completed NEPA documentation | A: 165. Work with BPA staff to complete NEPA and public involvement requirements | 09/30/2017 | 09/30/2017 | |
| Final realty package submitted to BPA | B: 172. Conduct all pre-acquisition activities for lands purchased under the CSKT/BPA MOA | 09/30/2017 | 09/30/2017 | |
| Funding Package - Submit draft to COTR | C: 119. Complete necessary BPA contracting requirements | 06/01/2017 | 06/07/2017 | |
| Annual report | D: 132. Submit Progress Report for the period 10/1/2015 to 9/30/2016 | 12/30/2016 | 05/15/2017 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Cutthroat Trout, Westslope (O. c. lewisi) |
|
| Trout, Bull (S. confluentus) (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | Work with BPA staff to complete NEPA and public involvement requirements | 10/01/2016 | ||||||
| B | 172 | Conduct all pre-acquisition activities for lands purchased under the CSKT/BPA MOA | 10/01/2016 | ||||||
| C | 119 | Complete necessary BPA contracting requirements | 10/01/2016 | ||||||
| D | 132 | Submit Progress Report for the period 10/1/2015 to 9/30/2016 | 10/01/2016 | ||||||
| E | 185 | Periodic Status Reports for BPA | 10/01/2016 |