Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 74537: 2008-604-00 EXP LOWER CLEARWATER/POTLATCH WATERSHED ACCORD-LATAH
Project Number:
Title:
Lower Clearwater and Potlatch Watersheds Habitat Improvements
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
74537
Contract Title:
2008-604-00 EXP LOWER CLEARWATER/POTLATCH WATERSHED ACCORD-LATAH
Contract Continuation:
Previous: Next:
70419: 2008-604-00 EXP LOWER CLEARWATER/POTLATCH WATERSHED ACCORD LATAH
  • 76953: 2008-604-00 EXP LOWER CLEARWATER/POTLATCH WATERSHED
Contract Status:
Closed
Contract Description:
This contract continues restoration planning and implementation efforts initiated under previous contract associated with Project #2008-604-00.

This contract supplements work undertaken by BPA and Latah Soil and Water Conservation District (Latah SWCD) through Project #2002-061-00 and associated contracts.  Consistent with Project #2002-061-00, this contract will undertake practices designed to effectively implement the Latah SWCD's Potlatch River Watershed Management Plan.  The 377,776-acre Potlatch River watershed is located in north-central Idaho and is the largest tributary in the lower Clearwater River.  The Potlatch River is critical to wild Snake River steelhead.

Supported by the Accord between BPA and the State of Idaho, this contract seeks to complement the work currently on-going by the Latah SWCD to restore wild Snake River Steelhead to a robust, self-sustaining population within the Potlatch River through coordinated implementation of best management practices on private/public agricultural, forest and range lands, coordination of interagency watershed planning efforts, continuation of watershed monitoring and development of outreach programs to landowners and agricultural producers.  Latah SWCD habitat restoration efforts are outlined in the Potlatch River Watershed Management Plan.      

This proposal is consistent with the NWPCC Fish and Wildlife Program’s goal to develop habitat-based programs designed to rebuild healthy, naturally producing fish and wildlife populations by protecting, mitigating, and restoring habitats. This project is consistent with the objectives and strategies of the Clearwater Subbasin Management Plan.

In an effort to lower stream temperatures, increase summer flows, decrease surface and channel erosion (and associated nutrient loading), and increase riparian habitat complexities, this contract will focus on erosion control and riparian restoration on private/public agricultural, forest, and range lands through the implementation of meadow restoration, livestock exclusion fencing, native plantings of riparian areas, passage barrier removal, protection of functional riparian areas, forest stand improvements, and soil health initiatives on agricultural lands.  Priority tributaries for restoration work within this contract include:  Big Bear Creek, Little Bear Creek, Corral Creek, and East Fork Potlatch River.

Latah SWCD staff will continue implementing riparian restoration and related projects throughout the Potlatch River watershed.  In addition, project staff will continue developing conservation plans with private/pulbic landowners and managers seeking additional BPA and non-BPA funds to implement best management practices designed for the improvement of steelhead spawning and rearing habitat.  Project staff will also continue coordination efforts with other watershed planning efforts throughout the region to improve fish habitat.
Account Type(s):
Expense
Contract Start Date:
09/01/2016
Contract End Date:
08/31/2017
Current Contract Value:
$631,236
Expenditures:
$631,236

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
All administrative tasks fulfilled with timely quality products B: 119. Manage and Administer BPA Contracts 08/31/2017 08/31/2017
Environmental Compliance & Consultation Review C: 165. Verify all NEPA Environmental Compliance has been completed 08/31/2017 08/31/2017
Provide general outreach to 50 landowners and direct contact with 10 landowners. D: 99. Outreach and Education/Solicit Landowner Participation 08/31/2017 08/31/2017
Develop 3 landowner initial conservation plans for project implementation. E: 174. Develop Initial Conservation Plans 08/31/2017 08/31/2017
Undertaken initial site reviews on 10 potential restoration sites. F: 114. Identify and Review Potential Restoration Sites 08/31/2017 08/31/2017
Big Bear Creek Riparian Restoration/Mason G: 30. Riparian/Meadow Restoration - Big Bear Creek/Mason - Continuation of Implementation 08/31/2017 08/31/2017
Riparian/Meadow Restoration Undertaken - Upper Corral Creek H: 30. Riparian/Meadow Restoration - Upper Corral Creek/USFS - Continuation of Implementation 08/31/2017 08/31/2017
Riparian/Meadow Restoration Design and Cost Estimate to BPA I: 175. Riparian/Meadow Restoration - East Fork Potlatch River/USFS - Continuation of Planning and Design 08/31/2017 08/31/2017
Riparian/Meadow Restoration Design and Cost Estimate to BPA J: 175. Riparian/Meadow Restoration - Little Bear Creek/Nora Creek - Continuation of Planning and Design 07/15/2017 08/31/2017
Riparian/Meadow Restoration Undertaken - Nora Creek K: 30. Riparian/Meadow Restoration - Little Bear Creek/Nora Creek - Initiate Implementation 08/31/2017 08/31/2017
Evaluate plantings, replant, and perform light maintenance L: 198. Replant and Maintain Riparian Plantings 08/31/2017 08/31/2017
Operate and maintain all contractual habitat improvement structures M: 186. Maintain Restoration Structures within Project Areas Previously Constructed 08/31/2017 08/31/2017
Develop and Implement Beaver Relocation Program N: 190. Beaver Relocation Program 08/31/2017 08/31/2017
Nutrient Management Analysis - Phosphorus Emphasis O: 99. Nutrient Management - Agriculture Input Modification 08/31/2017 08/31/2017
Completed Annual Report P: 132. Submit Progress Report for the period September 2015 to August 2016 07/31/2017 07/27/2017

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 190 Remove, Exclude and/or Relocate Animals
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 3 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 174 Produce Plan
  • 2 instances of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 09/01/2016
B 119 Manage and Administer BPA Contracts 09/01/2016
C 165 Verify all NEPA Environmental Compliance has been completed 09/01/2016
D 99 Outreach and Education/Solicit Landowner Participation 09/01/2016
E 174 Develop Initial Conservation Plans 07/25/2016
F 114 Identify and Review Potential Restoration Sites 09/01/2016
G 30 Riparian/Meadow Restoration - Big Bear Creek/Mason - Continuation of Implementation 10/17/2016
H 30 Riparian/Meadow Restoration - Upper Corral Creek/USFS - Continuation of Implementation 07/25/2016
I 175 Riparian/Meadow Restoration - East Fork Potlatch River/USFS - Continuation of Planning and Design 09/19/2017
J 175 Riparian/Meadow Restoration - Little Bear Creek/Nora Creek - Continuation of Planning and Design 07/25/2016
K 30 Riparian/Meadow Restoration - Little Bear Creek/Nora Creek - Initiate Implementation 06/23/2017
L 198 Replant and Maintain Riparian Plantings 06/20/2017
M 186 Maintain Restoration Structures within Project Areas Previously Constructed 10/17/2016
N 190 Beaver Relocation Program 06/20/2017
O 99 Nutrient Management - Agriculture Input Modification 09/01/2016
P 132 Submit Progress Report for the period September 2015 to August 2016 09/01/2016