Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 74780: 2007-399-00 EXP UP SALMON SCREEN TRIB PASS
Project Number:
Title:
Upper Salmon Screen Tributary Passage
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
74780
Contract Title:
2007-399-00 EXP UP SALMON SCREEN TRIB PASS
Contract Continuation:
Previous: Next:
71413: 2007-399-00 EXP UP SALMON SCREEN TRIB PASS FOR IDFG
  • 78455: 2007-399-00 EXP UP SALMON SCREEN TRIB PASS
Contract Status:
Closed
Contract Description:
To provide management and operational support for a capital construction program dedicated to the protection of anadromous fish from loss in water diversions, improve fish passage at diversions for juvenile and adult anadromous fish, and improve stream flow conditions where possible.  Staff will process environmental regulatory documents, provide oversight to archaeologists and consulting engineers, engage in scoping activities, and negotiate with private landowners for habitat projects.  All projects require compliance with State of Idaho and Federal regulations including, but not limited to, IDAPA Title 42, IDAPA Title 36, National Environmental Policy Act, Clean Water Act, Endangered Species Act, Federal Land Management Policy Act, National Historical Preservation Act, and Magnuson-Stevens Fishery Conservation and Management Act.  

Project Coordination:  The Idaho Department of Fish & Game (IDFG) coordinates other funding sources with this Bonneville Power Administration (BPA) contract in order to maximize the potential for anadromous fish recovery efforts in the Salmon River basin.  

Background:   Since the 1800s, anadromous fish runs in the Columbia River have declined drastically.  Historically,  IDFG estimates that the Salmon River basin produced 39% of the spring Chinook salmon and 45% of the summer Chinook salmon in the Columbia River Basin (Idaho Department of Fish & Game, 1985).  Steelhead estimates for the Salmon River basin are not available but production was substantial.  Due to the low return of spring Chinook salmon to Idaho in 1974, all but treaty harvest was curtailed.  Since then,  harvest has been limited to a tribal fishery and occasional harvest of surplus hatchery stocks.  

Irrigation diversions date back to the 1860's in the Salmon River basin of the Snake River drainage and have impacted anadromous fish in a number of ways.  These impacts included loss of habitat, entrainment of smolts on their migration to the ocean,  and returning adults have been blocked by irrigation diversion wing dams.  Riparian corridors have been degraded by various management actions.

In 1938 the U.S. Congress passed the Mitchell Act in an attempt to partially mitigate for losses resulting from hydroelectric projects, logging, mining, and agricultural developments.  The Act provided a mechanism for conserving fishery resources of the Columbia River basin and created the Columbia River Fisheries Development Program (CRFDP).  The CRFDP program was extended to include the upper basin (above McNary) in 1956.  Between 1958 and 1966, IDFG constructed more than 200 screens on the main stem Salmon River and tributaries.  Today about 235 screens are in operation in Idaho.  

Funding was first provided to the IDFG  by BPA in 1994 for anadromous fisheries projects falling outside the scope of the Mitchell Act.  These funds were used in non-traditional ways to eliminate or consolidate irrigation diversions, improve fish passage, conserve water and provide proper screening of water withdrawals.  These projects have been undertaken by IDFG on a tributary wide basis to maximize the potential for success.
Account Type(s):
Expense
Contract Start Date:
09/27/2016
Contract End Date:
01/31/2018
Current Contract Value:
$521,622
Expenditures:
$521,622

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
All administrative tasks fulfilled with timely quality products A: 119. Routine administration of contract 01/31/2018 12/31/2017
Provide BPA with all necessary EC/permits B: 165. Provide to BPA any requested EC/permits 09/26/2017 09/26/2017
Final Project Designs C: 175. Final Designs for Construction 01/31/2018 12/31/2017
Completed FSOC/NOAA criteria fish screen D: 69. Lemhi River-08A (L-08A) Fish Screen Project 11/10/2017 12/31/2017
Completed FSOC/NOAA criteria fish screen. E: 69. Hawley Creek -02 (LHawC-02) Fish Screen Project 09/26/2017 09/26/2017
Hawley Creek-02 Diversion Installation F: 84. Hawley Creek-02 Diversion Project 09/26/2017 09/26/2017
Completed FSOC/NOAA criteria fish screen. G: 69. Canyon Creek -04 (LCanyC-04) Fish Screen Project 09/26/2017 07/26/2017
Canyon Creek-04 Diversion Installation H: 84. Canyon Creek-04 Diversion Project 09/26/2017 09/26/2017
Completed FSOC/NOAA criteria fish screen I: 69. Pratt-Mulkey Pump Fish Screen Project 09/26/2017 09/26/2017
Completed FSOC/NOAA criteria fish screen. J: 69. Pratt Creek- Hedt Fish Screen Project 01/31/2018
Completed FSOC/NOAA criteria fish screen L: 69. Valley Creek -05/06 (SVC-05/06) Fish Screen Project 01/31/2018
Completed FSOC/NOAA criteria fish screen M: 69. Salmon River -23A (S-23A) Fish Screen Project 09/26/2017 09/26/2017
Unobstructed Bayhorse Creek Stream Channel N: 85. Bayhorse Creek Bridge Replacement Project 01/05/2018
Unobstructed Carmen Creek Stream Channel O: 85. Carmen Creek-03 Bridge Replacement Project 01/31/2018 12/31/2017
Completed Annual Report P: 132. Submit Progress Report for the period October 2015 to September 2016 01/31/2018
Completed Annual Report R: 132. Submit Progress Report for the period October 2012 to September 2015 01/31/2018
Completed FSOC/NMFS criteria fish screen S: 69. Lemhi River-60 (L-60) Fish Screen Project 12/31/2017 12/31/2017
Completed FSOC/NMFS criteria fish screen T: 69. Lemhi River-62 (L-62) Fish Screen Project 12/31/2017 12/31/2017

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 10 instances of WE 69 Install Fish Screen
  • 2 instances of WE 84 Remove/Install Diversion
  • 2 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 10 instances of WE 69 Install Fish Screen
  • 2 instances of WE 84 Remove/Install Diversion
  • 2 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Routine administration of contract 09/27/2016
B 165 Provide to BPA any requested EC/permits 09/27/2016
C 175 Final Designs for Construction 08/23/2017
D 69 Lemhi River-08A (L-08A) Fish Screen Project 07/12/2017
E 69 Hawley Creek -02 (LHawC-02) Fish Screen Project 09/27/2016
F 84 Hawley Creek-02 Diversion Project 09/27/2016
G 69 Canyon Creek -04 (LCanyC-04) Fish Screen Project 09/27/2016
H 84 Canyon Creek-04 Diversion Project 09/27/2016
I 69 Pratt-Mulkey Pump Fish Screen Project 09/27/2016
J 69 Pratt Creek- Hedt Fish Screen Project 09/27/2016
K 69 Elk Creek -01 (SVCEC-01) Fish Screen Project
L 69 Valley Creek -05/06 (SVC-05/06) Fish Screen Project
M 69 Salmon River -23A (S-23A) Fish Screen Project 05/31/2017
N 85 Bayhorse Creek Bridge Replacement Project
O 85 Carmen Creek-03 Bridge Replacement Project 11/28/2017
P 132 Submit Progress Report for the period October 2015 to September 2016 09/27/2016
Q 185 Periodic Status Reports for BPA 09/27/2016
R 132 Submit Progress Report for the period October 2012 to September 2015 09/27/2016
S 69 Lemhi River-60 (L-60) Fish Screen Project 08/23/2017
T 69 Lemhi River-62 (L-62) Fish Screen Project 08/23/2017