Contract 75948: 2001-029-00 EXP FORD HATCHERY O&M

Last Modified: Amy Mai, 01/10/2017 11:13 AM   
Basics

Project Number:
Title:
Ford Hatchery Operations and Maintenance (O&M)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Columbia Upper 100.00%
Contract Number:
75948
Contract Title:
2001-029-00 EXP FORD HATCHERY O&M
Contract Continuation:
Previous: Next:
72199: 2001-029-00 EXP FORD HATCHERY O&M
Contract Status:
Closed
Contract Description:
The goal of this project is to operate and maintain Ford Hatchery to enhance the recreational  kokanee fisheries in Banks Lake.  The Ford Hatchery will augment production at Spokane Tribal kokanee/rainbow trout hatchery by producing 700,000 Kokanee @ 60/lb. totaling 11,666 lbs. for Banks Lake.


Non-BPA funded activities:
In addition to the 700,000 at 60 fpp, Ford Hatchery will release 147,000 Kokanee into Banks Lake @ 200/lb. in June.  This program is funded by WDFW.   Ford Hatchery's production will contribute to 847,000  kokanee fry/fingerlings for Banks Lake. Current objectives included the increased use of native/indigenous stocks where available for propagation in the Lake Roosevelt subbasin.  Also, Ford Hatchery will continue to produce resident trout (80,000 lbs.) to promote the sport fisheries in put-and-take trout fishing lakes in eastern Washington (WDFW Management Region 1). Funding for the resident trout comes from WDFW at no cost to BPA.
Account Type(s):
Expense
Contract Start Date:
04/01/2017
Contract End Date:
03/31/2018
Current Contract Value:
$137,509
Expenditures:
$137,509

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Mitch Combs Washington Department of Fish and Wildlife (WDFW) Yes Technical Contact mitch.combs@dfw.wa.gov (509) 738-6971
Chris Donley Washington Department of Fish and Wildlife (WDFW) No Supervisor christopher.donley@dfw.wa.gov (509) 892-1001x307
Michael Garrity Washington Department of Fish and Wildlife (WDFW) No Interested Party michael.garrity@dfw.wa.gov (360) 810-0877
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Janice Jackson Washington Department of Fish and Wildlife (WDFW) No Administrative Contact janice.jackson@dfw.wa.gov (360) 902-2444
Rachel Kulak Bonneville Power Administration Yes Contracting Officer rakulak@bpa.gov (503) 230-5091
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Amy Mai Bonneville Power Administration Yes COR aemai@bpa.gov (503) 230-7349
Christopher Roper Bonneville Power Administration No CO Assistant cproper@bpa.gov (503) 230-3514
Brian Russell Washington Department of Fish and Wildlife (WDFW) Yes Technical Contact brian.russell@dfw.wa.gov (509) 625-5169
Tybee Sheidler Bonneville Power Administration No CO Assistant tasheidler@bpa.gov (503) 230-3820
Rich Watson Washington Department of Fish and Wildlife (WDFW) Yes Contract Manager rich.watson@dfw.wa.gov (509) 892-7862
Jacob Wolfe Washington Department of Fish and Wildlife (WDFW) Yes Technical Contact jacob.wolfe@dfw.wa.gov (509) 258-4269
Elham Zolmajd-Haghighi Bonneville Power Administration No ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Obtain permits A: 165. Obtain NEPA Clearance and Permits 03/31/2018 03/31/2018
700,000 BY 2015 Kokanee for Banks Lake B: 176. Kokanee, BY 2016 April through October 2016 (rear/transfer/release) 03/31/2018 03/31/2018
850,000 BY 2017 Kokanee for Banks Lake C: 176. Kokanee BY 2017, January through March 2017 (Receive kokanee eggs) 03/31/2018 03/31/2018
Fully functional hatchery D: 61. Hatchery Maintenance 03/31/2018 03/31/2018
Produce Annual Operations and Maintenance Plan E: 174. Produce Annual Operations Plan 03/31/2018 02/06/2018
Timely submission of all necessary reports. F: 119. Management and Administration 03/31/2018 03/31/2018
FY15 annual report G: 132. Submission of FY 15 Annual Report 06/30/2017
FY16 annual report H: 132. Submission of FY 16 Annual Report 03/31/2018 03/15/2018

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Kokanee (Oncorhynchus nerka)
  • 2 instances of WE 176 Produce Hatchery Fish
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain NEPA Clearance and Permits 04/01/2017
B 176 Kokanee, BY 2016 April through October 2016 (rear/transfer/release) 04/01/2017
C 176 Kokanee BY 2017, January through March 2017 (Receive kokanee eggs) 04/01/2017
D 61 Hatchery Maintenance 04/01/2017
E 174 Produce Annual Operations Plan 04/01/2017
F 119 Management and Administration 04/01/2017
G 132 Submission of FY 15 Annual Report 04/01/2017
H 132 Submission of FY 16 Annual Report 04/01/2017
I 185 Periodic Status Reports for BPA 04/01/2017