| Province | Subbasin | % |
|---|---|---|
| Middle Snake | Owyhee | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Complete project administration | A: 119. Project administration | 09/30/2018 | 09/28/2018 | |
| Receipt of EC documentation/clearance from BPA | B: 165. Satisfy environmental compliance requirements | 09/30/2018 | 09/28/2018 | |
| Complete parcel identification | C: 115. SIWM Parcel Identification | 09/30/2018 | 09/28/2018 | |
| Complete pre-acquisition activities | D: 172. Conduct pre-acquisitional tasks | 07/31/2018 | 09/28/2018 | |
| Coordination with other wildlife mitigation entities in the region | E: 114. SIWM Coordination | 09/30/2018 | 09/28/2018 | |
| Management Plan for Pole Creek Ranch | F: 174. Produce management plan for Pole Creek Ranch | 07/31/2018 | ||
| Maintenance of fence completed, 2018 photopoints documented, debris at ranch headquarters cleaned up | G: 186. Fence maintenance, photopoints, maintain infrastructure at Pole Creek Ranch | 09/30/2018 | 09/28/2018 | |
| Completed Native Plant Inventory Data Forms and Photos for Native Plant Inventory Database | H: 115. Conduct baseline native plant survey on Pole Creek Ranch | 07/31/2018 | 09/28/2018 | |
| Completed Columbia Spotted Frog Surveys | I: 115. Conduct Columbia spotted frog surveys on Pole Creek Ranch | 07/31/2018 | 09/28/2018 | |
| Noxious Weed Maps | J: 115. Conduct noxious weed surveys on Pole Creek Ranch | 07/31/2018 | 09/28/2018 | |
| GPS data on existing fences | K: 115. Assess and GPS existing fences on Pole Creek Ranch | 09/30/2018 | 09/28/2018 | |
| Investigate and resolve trespass issues | L: 26. Investigate trespass on Pole Creek Ranch | 09/30/2018 | 09/28/2018 | |
| Completed Annual Report | M: 132. Submit Progress Report for the period (1/1/17 to 12/31/17) | 04/30/2018 | 02/16/2018 | |
| Weed treatment documentation | O: 199. Conduct weed treatment activities | 09/30/2018 | 07/26/2018 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Trout, Interior Redband (O. mykiss gairdnerii) |
|
| Wildlife |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 119 | Project administration | 08/01/2017 | ||||||
| B | 165 | Satisfy environmental compliance requirements | 08/01/2017 | ||||||
| C | 115 | SIWM Parcel Identification | 07/27/2017 | ||||||
| D | 172 | Conduct pre-acquisitional tasks | 08/01/2017 | ||||||
| E | 114 | SIWM Coordination | 08/01/2017 | ||||||
| F | 174 | Produce management plan for Pole Creek Ranch | 07/27/2017 | ||||||
| G | 186 | Fence maintenance, photopoints, maintain infrastructure at Pole Creek Ranch | 11/08/2017 | ||||||
| H | 115 | Conduct baseline native plant survey on Pole Creek Ranch | 08/01/2017 | ||||||
| I | 115 | Conduct Columbia spotted frog surveys on Pole Creek Ranch | 07/27/2017 | ||||||
| J | 115 | Conduct noxious weed surveys on Pole Creek Ranch | 07/27/2017 | ||||||
| K | 115 | Assess and GPS existing fences on Pole Creek Ranch | 07/27/2017 | ||||||
| L | 26 | Investigate trespass on Pole Creek Ranch | 08/01/2017 | ||||||
| M | 132 | Submit Progress Report for the period (1/1/17 to 12/31/17) | 08/01/2017 | ||||||
| N | 185 | Periodic Status Reports for BPA | 08/01/2017 | ||||||
| O | 199 | Conduct weed treatment activities | 07/12/2018 |