| Province | Subbasin | % |
|---|---|---|
| Upper Snake | Snake Upper | 100.00% |
| Previous: | Next: |
|---|---|
| 77111 REL 36: 1995-057-02 EXP SOUTHERN IDAHO WILDLIFE MITIGATION |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Deliverable: K. Receipt of EC documentation/clearance from BPA | B: 165. Satisfy environmental compliance requirements | 03/31/2023 | 03/31/2023 | |
| Effective implementation management and timely contract administration | C: 119. Administration of BPA contracts | 03/31/2023 | 03/31/2023 | |
| Deliverable: C.Coordinate project lands management with relevant land agencies | D: 191. Coordinate project lands management with relevant land agencies | 03/31/2023 | 03/31/2023 | |
| Develop or update (out-year) prioritized Habitat Project list: upload to Pisces | E: 114. Identify potential mitigation properties | 03/31/2023 | 03/31/2023 | |
| Deliverable: Q. Conduct pre-acquisition activities | F: 172. Conduct pre-acquisition activities | 03/31/2023 | 03/31/2023 | |
| Maintain vegetation on project lands- Bannock Creek | G: 198. Maintain vegetation on project lands- Bannock Creek | 11/26/2022 | 09/30/2022 | |
| Maintain vegetation on project lands- Legacy Springs | H: 198. Maintain vegetation on project lands- Legacy Springs | 11/26/2022 | 09/30/2022 | |
| Deliverable: D. Control Russian Olive Regrowth Bannock Creek and Legacy Springs | I: 199. Monitor and control Russian Olive Regrowth- Bannock Creek and Legacy Springs | 03/31/2023 | 03/31/2023 | |
| Deliverable: I. Maintain program infrastructure | J: 186. Maintain program infrastructure | 03/31/2023 | 03/31/2023 | |
| Benefit/Income/Spending Report | K: 194. Administer agricultural Lease- Legacy Springs | 09/01/2022 | 09/01/2022 | |
| Benefit/Income/Spending Report | L: 194. Administer agricultural Lease- Lavaside | 09/01/2022 | 09/01/2022 | |
| Monitoring results and potential restoration plan | N: 174. Develop restoration plan for Lavaside Fire impacts | 03/31/2023 | ||
| Deliverable: F. Revised Management Plan | O: 193. Revise Management Plan | 03/31/2023 | ||
| Completed Annual Report | P: 132. Submit Progress Report for the period April 2020 to March 2022 | 03/31/2023 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Wildlife |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 185 | Periodic Status Reports for BPA | |||||||
| B | 165 | Satisfy environmental compliance requirements | |||||||
| C | 119 | Administration of BPA contracts | |||||||
| D | 191 | Coordinate project lands management with relevant land agencies | |||||||
| E | 114 | Identify potential mitigation properties | |||||||
| F | 172 | Conduct pre-acquisition activities | |||||||
| G | 198 | Maintain vegetation on project lands- Bannock Creek | 04/01/2022 | ||||||
| H | 198 | Maintain vegetation on project lands- Legacy Springs | 04/01/2022 | ||||||
| I | 199 | Monitor and control Russian Olive Regrowth- Bannock Creek and Legacy Springs | 04/01/2022 | ||||||
| J | 186 | Maintain program infrastructure | 04/01/2022 | ||||||
| K | 194 | Administer agricultural Lease- Legacy Springs | 04/01/2022 | ||||||
| L | 194 | Administer agricultural Lease- Lavaside | 04/01/2022 | ||||||
| M | 174 | Develop Riparian Restoration Plan- Bannock Creek | 04/01/2022 | ||||||
| N | 174 | Develop restoration plan for Lavaside Fire impacts | 04/01/2022 | ||||||
| O | 193 | Revise Management Plan | |||||||
| P | 132 | Submit Progress Report for the period April 2020 to March 2022 |