Contract 78040 REL 4: 2017-005-00 EXP PACIFIC LAMPREY CONSERVATION INITIATIVE CRB PROJS
Project Number:
Title:
Pacific Lamprey Conservation Initiative
Stage:
Implementation
Area:
Province Subbasin %
Basinwide - 100.00%
Contract Number:
78040 REL 4
Contract Title:
2017-005-00 EXP PACIFIC LAMPREY CONSERVATION INITIATIVE CRB PROJS
Contract Continuation:
Previous: Next:
n/a
  • 78040 REL 15: 2017-005-00 EXP PACIFIC LAMPREY CONSERVATION INITIATIVE CRB PROJS
Contract Status:
Closed
Contract Description:
On October 26, 2017 the Council and Bonneville received a submittal from USFWS for Proposal #2017-005-00, Pacific Lamprey Conservation Initiative Columbia River Basin Projects.  The overarching goal of the proposal is to support the intent of the cooperative effort among agencies and tribes to achieve long-term persistence of Pacific Lamprey and support traditional tribal cultural use over the U.S. range by funding on--the--ground implementation of restoration actions that contribute to this effort. The purpose of the proposal is to facilitate funding for high priority lamprey restoration actions that are currently unfunded or partially funded in the Columbia River Basin. This process will work in parallel with other programs that are currently and will continue to fund lamprey restoration projects. In essence, this proposal is an umbrella type project  for Pacific Lamprey in the Basin.  That is, the Agreement Conservation Team will utilize identified priority projects from the annually updated Regional Implementation Plans (RIP) from Regional Management Units (RMU) within the Columbia and Snake River basins (i.e., Lower Columbia/Willamette, Mid-Columbia, Snake and Upper Columbia).

On October 27, 2017 the proposal was submitted to the ISRP and on November 28, 2017 the ISRP provided its review (ISRP document 2017-13) – due to the umbrella intent of the proposal the emphasis of the review focused on the operating guidelines and selection criteria that guide the implementation of the priority lamprey actions. The ISRP found the proposal “Meets Scientific Review Criteria (Qualified)”.  

The proposal received is facilitated by the USFWS and administered through Pacific States Marine Fisheries Commission (PSFMC).  The restoration actions in the appropriate RMU’s will be reviewed and selected by the Agreement Conservation Team based on the following criteria as outlined in the Pacific Lamprey Conservation Agreement Operating Guidelines;

1. Project Rationale
2. Linkage of Actions to Threats
3. Project Feasibility
4. Partner Engagement and Support
5. Monitoring and Evaluation – Contribution to Knowledge Gaps
6. Budget and Timelines

In addition, the Agreement Conservation Team’s selection criteria are consistent with those of the Council in regard to whether they:

1. Are based on sound science principles;
2. Benefit fish and wildlife;
3. Have clearly defined objectives and outcomes; and
4. Have provisions for monitoring and evaluation of results.

Following are the proposed actions that the project intends to implement this Fiscal Year (2018) to address priority restoration needs across RMUs in the Columbia/Snake and reduce overall risk to lamprey populations (see below)


Adult Passage Improvement in Lower Yakima
Adult Passage at Prosser dam – two new volitional vertical wetted wall (VWW) passage structures, modify existing VVW structures to allow volitional passage

Translocating Adult Lamprey Past lower Snake River Dams
Make improvements (safety and protection) to holding facility for adults.

Lower South Fork McKenzie River Floodplain Enhancement Project
Address primary threat for the Willamette RMU (i.e., stream and floodplain degradation). Will also address limiting factors of  fine sediment deposition, spawning gravel, off channel habitat and high flow refuge
Account Type(s):
Expense
Contract Start Date:
06/01/2018
Contract End Date:
05/31/2019
Current Contract Value:
$222,352
Expenditures:
$222,352

* Expenditures data includes accruals and are based on data through 30-Apr-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Catherine Al-Sheikhly Pacific States Marine Fisheries Commission No Administrative Contact kalsheikhly@psmfc.org (503) 595-3224
Michael Arredondo Pacific States Marine Fisheries Commission No Interested Party marredondo@psmfc.org (503) 595-3100
Randy Fisher Pacific States Marine Fisheries Commission No Supervisor randy.fisher@psmfc.org (503) 595-3100
Pam Kahut Pacific States Marine Fisheries Commission No Supervisor pam_kahut@psmfc.org (503) 595-3100
Ralph Lampman Yakama Confederated Tribes No Interested Party lamr@yakamafish-nsn.gov (509) 388-3871
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Siena Lopez-Johnston Bonneville Power Administration Yes COR smlopez@bpa.gov (503) 230-3635
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Tabatha Rood Bonneville Power Administration Yes Interested Party tmrood@bpa.gov (503) 230-5736
Christopher Roper Bonneville Power Administration No CO Assistant cproper@bpa.gov (503) 230-3514
Bob Rose Yakama Confederated Tribes Yes Technical Contact rosb@yakamafish-nsn.gov (509) 388-3871
Dave Statler Nez Perce Tribe Yes Technical Contact daves@nezperce.org (208) 621-3575
Christina Wang US Fish and Wildlife Service (USFWS) Yes Technical Contact christina_wang@fws.gov (360) 604-2583
Jared Weybright Mckenzie Watershed Alliance Yes Technical Contact jared@mckenziewc.org (458) 201-8150
Chris Wheaton Pacific States Marine Fisheries Commission No cwheaton@psmfc.org (503) 595-3100
Steve Williams Pacific States Marine Fisheries Commission Yes Contract Manager swilliams@psmfc.org (503) 595-3100


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Applicable permits and any necessary environmental clearance completed/received A: 165. Obtain Environmental Clearance - NEPA, ESA, etc. 05/31/2019 05/31/2019
VWW Installation and Improvements Complete B: 184. Prosser Dam - Vertical Wetted Wall Installation and Modification to Existing 05/31/2019 05/31/2019
Operation and Maintenance of VWW structures C: 186. Prosser Dam - Vertical Wetted Wall Operation & Maintenance 05/31/2019 05/31/2019
Trap and Haul Adult Lamprey from Columbia and Willamette River D: 28. NPT Snake Basin - Adult Lamprey Collection, Transport, Hold and Release 05/31/2019 05/31/2019
Updated facilities for lamprey translocation E: 61. NPT Snake Basin - Upgrade Lamprey Translocation Infrastructure 05/31/2019 05/31/2019
Create habitat & address limiting factors for lamprey F: 29. MWC SF McKenzie - Harvest and Placement of Large Wood 09/30/2018 09/30/2018
Effective implementation management and timely contract administration G: 119. PSMFC - Administer the Contract 05/31/2019 05/31/2019
Develop or update (out-year) prioritized Habitat Project list: upload to Pisces H: 114. Utilize Regional Implementation Plans for Out-Year Project Prioritization and Selection 02/28/2019 02/28/2019
Completed Annual Report I: 132. Prosser Dam VWW - Submit Progress Report for the period 06/01/2018 to 5/31/2018 05/31/2019
Completed Annual Report J: 132. MWC SF McKenzie - Submit Progress Report for the period 6/1/2018 - 12/31/2018 05/31/2019
Completed Annual Report K: 132. NPT Snake Basin Translocation - Submit Progress Report for the period 6/1/2018 - 12/31/2018 05/31/2019

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 28 Trap and Haul
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
Lamprey, Western Brook (L. richardsoni)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain Environmental Clearance - NEPA, ESA, etc. 06/01/2018
B 184 Prosser Dam - Vertical Wetted Wall Installation and Modification to Existing 06/01/2018
C 186 Prosser Dam - Vertical Wetted Wall Operation & Maintenance 06/01/2018
D 28 NPT Snake Basin - Adult Lamprey Collection, Transport, Hold and Release 06/01/2018
E 61 NPT Snake Basin - Upgrade Lamprey Translocation Infrastructure 06/11/2018
F 29 MWC SF McKenzie - Harvest and Placement of Large Wood 05/15/2018
G 119 PSMFC - Administer the Contract 06/01/2018
H 114 Utilize Regional Implementation Plans for Out-Year Project Prioritization and Selection 06/01/2018
I 132 Prosser Dam VWW - Submit Progress Report for the period 06/01/2018 to 5/31/2018 06/01/2018
J 132 MWC SF McKenzie - Submit Progress Report for the period 6/1/2018 - 12/31/2018 06/01/2018
K 132 NPT Snake Basin Translocation - Submit Progress Report for the period 6/1/2018 - 12/31/2018 06/01/2018
L 185 Periodic Status Reports for BPA 06/01/2018