| Province | Subbasin | % |
|---|---|---|
| Blue Mountain | Grande Ronde | 100.00% |
| Previous: | Next: |
|---|---|
| n/a |
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Environmental Compliance Completed | A: 165. Environmental Compliance | 08/15/2018 | 08/15/2018 | |
| Complete Construction of all 25 woody material structures prior to the end of the instream work window. | B: 29. Install engineered log jam (ELJ) structures | 10/15/2018 | 09/28/2018 | |
| Complete Fish Salvage | C: 28. Fish Salvage | 10/15/2018 | 09/12/2018 | |
| Completed channel construction | D: 30. New Channel Excavation | 10/15/2018 | 09/28/2018 | |
| Bridge Abutments installed | E: 33. Bridge Abutment Installation | 10/15/2018 | 10/15/2018 | |
| Complete Willow Planting | F: 47. Willow Trenching | 10/15/2018 | 10/15/2018 | |
| Effective implementation management and timely contract administration | G: 119. Project/Contract Administration | 07/31/2020 | 02/06/2019 | |
| Completed Annual Report | H: 132. Completion Report | 07/31/2020 | 02/06/2019 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
| Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | Environmental Compliance | 08/01/2018 | ||||||
| B | 29 | Install engineered log jam (ELJ) structures | 06/18/2018 | ||||||
| C | 28 | Fish Salvage | 06/18/2018 | ||||||
| D | 30 | New Channel Excavation | 07/18/2018 | ||||||
| E | 33 | Bridge Abutment Installation | 08/01/2018 | ||||||
| F | 47 | Willow Trenching | 06/18/2018 | ||||||
| G | 119 | Project/Contract Administration | 08/01/2018 | ||||||
| H | 132 | Completion Report | 08/01/2018 | ||||||
| I | 185 | Quarterly Status Reports | 08/01/2018 |