| Province | Subbasin | % |
|---|---|---|
| Columbia River Estuary | Columbia Estuary | 50.00% |
| Elochoman | 5.00% | |
| Grays | 5.00% | |
| Lower Columbia | Columbia Lower | 30.00% |
| Kalama | 5.00% | |
| Sandy | 5.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Produce the Necessary Environmental Compliance | B: 165. Ensure All Environmental Compliance is Complete | 09/30/2019 | 09/30/2019 | |
| All administration tasks fulfilled with timely, quality products | C: 119. Provide Management and Administration of Projects | 09/30/2019 | 09/30/2019 | |
| Documentation Describing Priority Projects | D: 114. Identify Priority Land Acquisition and Restoration Projects | 09/30/2019 | 09/30/2019 | |
| Final Realty Package for Priority Acquisitions | E: 172. Conduct All Necessary Due Diligence Related to Land Acquisition | 09/30/2019 | 09/30/2019 | |
| Attach 2018 Annual Report in Pisces | F: 132. Submit Progress Report for the period Jan 2018 to Dec 2018 | 03/15/2019 | 03/31/2019 | |
| Wallacut River Planting | H: 47. WALLACUT RIVER--RESTORATION -- Planting | 06/01/2019 | 06/01/2019 | |
| Kerry Island Planting | I: 47. KERRY ISLAND-- RESTORATION-- Planting | 04/30/2019 | 03/31/2019 | |
| Floodplain Re-vegetation | J: 47. COLUMBIA STOCK RANCH -- RESTORATION -- Planting | 09/30/2019 | 09/30/2019 | |
| Exclusion Fencing | K: 40. COLUMBIA STOCK RANCH -- RESTORATION -- Fencing | 09/30/2019 | 09/30/2019 | |
| Floodplain Habitat Planting | L: 47. LOWER ELOCHOMAN II -- RESTORATION -- Plant Vegetation | 05/31/2019 | 05/31/2019 | |
| Floodplain Reconnection | M: 180. LOWER ELOCHOMAN II -- RESTORATION -- Remove remnant levee and contour floodplain | 09/30/2019 | 09/30/2019 | |
| Vegetation Control | N: 199. LOWER ELOCHOMAN III -- RESTORATION -- Vegetation Control | 09/30/2019 | 09/30/2019 | |
| Produce accessible, error-checked datasets | O: 157. Restoration Design Challenges Project | 09/30/2019 | 09/30/2019 | |
| Level 3 AEMR data-- Lower Elochoman Pre-construction data | P: 157. LOWER ELOCHOMAN PHASE II - Collect PRE - Construction year 0 AEMR Level 3 data | 09/30/2019 | 09/30/2019 | |
| Level 3 AEMR Data -- Lower Elochoman III PRE-Construction | Q: 157. LOWER ELOCHOMAN III - Collect PRE-Construction Year 0 AEMR Level 3 Data | 09/30/2019 | 09/30/2019 | |
| Level 3 AEMR data-- Wallacut Post-construction Year 3 | R: 157. WALLACUT - Collect POST-Construction Year 3 AEMR Level 3 data | 09/30/2019 | 09/30/2019 | |
| Level 3 AEMR data-- Kerry Island Post-Construction Year 3 | S: 157. KERRY ISLAND - Collect POST-Construction Year 3 AEMR Level 3 data | 09/30/2019 | 09/30/2019 | |
| Produce accessible, error-checked datasets | T: 157. KANDOLL FARM - Collect POST Construction year 5 | 09/30/2019 | 09/30/2019 | |
| Produce accessible, error-checked datasets | U: 157. WALLUSKI NORTH - Collect POST Construction year 10 data | 09/30/2019 | 09/30/2019 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (Oncorhynchus tshawytscha) - All Populations |
|
| Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened) |
|
| Chum (Oncorhynchus keta) - Columbia River ESU (Threatened) |
|
| Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened) |
|
| Coho (O. kisutch) - Unspecified Population |
|
| Steelhead (Oncorhynchus mykiss) - All Populations |
|
| Wildlife |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 185 | Periodic Status Reports for BPA | 10/01/2018 | ||||||
| B | 165 | Ensure All Environmental Compliance is Complete | 10/01/2018 | ||||||
| C | 119 | Provide Management and Administration of Projects | 10/01/2018 | ||||||
| D | 114 | Identify Priority Land Acquisition and Restoration Projects | 10/01/2018 | ||||||
| E | 172 | Conduct All Necessary Due Diligence Related to Land Acquisition | 10/01/2018 | ||||||
| F | 132 | Submit Progress Report for the period Jan 2018 to Dec 2018 | 10/01/2018 | ||||||
| G | 132 | Submit Data for estuary 2018 RME Report | 10/01/2018 | ||||||
| H | 47 | WALLACUT RIVER--RESTORATION -- Planting | 08/13/2018 | ||||||
| I | 47 | KERRY ISLAND-- RESTORATION-- Planting | 08/13/2018 | ||||||
| J | 47 | COLUMBIA STOCK RANCH -- RESTORATION -- Planting | |||||||
| K | 40 | COLUMBIA STOCK RANCH -- RESTORATION -- Fencing | |||||||
| L | 47 | LOWER ELOCHOMAN II -- RESTORATION -- Plant Vegetation | |||||||
| M | 180 | LOWER ELOCHOMAN II -- RESTORATION -- Remove remnant levee and contour floodplain | |||||||
| N | 199 | LOWER ELOCHOMAN III -- RESTORATION -- Vegetation Control | |||||||
| O | 157 | Restoration Design Challenges Project | 08/13/2018 | ||||||
| P | 157 | LOWER ELOCHOMAN PHASE II - Collect PRE - Construction year 0 AEMR Level 3 data | 08/13/2018 | ||||||
| Q | 157 | LOWER ELOCHOMAN III - Collect PRE-Construction Year 0 AEMR Level 3 Data | 08/13/2018 | ||||||
| R | 157 | WALLACUT - Collect POST-Construction Year 3 AEMR Level 3 data | 10/17/2018 | ||||||
| S | 157 | KERRY ISLAND - Collect POST-Construction Year 3 AEMR Level 3 data | 08/13/2018 | ||||||
| T | 157 | KANDOLL FARM - Collect POST Construction year 5 | 08/13/2018 | ||||||
| U | 157 | WALLUSKI NORTH - Collect POST Construction year 10 data | 08/13/2018 |