| Province | Subbasin | % |
|---|---|---|
| Columbia Plateau | Tucannon | 100.00% |
| Previous: | Next: |
|---|---|
| 84042 REL 4: 2010-050-00 EXP EVALUATION OF TUCANNAN ENDEMIC STOCK FY 22 |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Effective implementation management and timely contract administration | B: 119. Project Implementation Management and Contract Administration | 11/30/2024 | 11/30/2024 | |
| Timely and successful compliance documentation and clearance | C: 165. Environmental Compliance | 06/30/2024 | 06/30/2024 | |
| Completed Annual Report | D: 132. WDFW will produce an annual technical progress report for the work completed, showing cumulative results and synthesis for the duration data collection/analysis studies. BPA needs to have the reports fi | 05/31/2024 | 05/31/2024 | |
| Produce accessible, error-checked datasets | E: 157. Monitor spawning and survival of hatchery steelhead at Lyons Ferry and Tucannon FH | 06/30/2024 | 06/30/2024 | |
| Mark and Tag Supplementation Steelhead for Program Evaluation | F: 158. Coded-Wire Tag Hatchery and PIT-Tag juvenile Hatchery Summer Steelhead | 02/28/2024 | 02/28/2024 | |
| PIT tag hatchery-origin spring Chinook for Program Evaluation | G: 158. PIT-Tag Tucannon River Juvenile Hatchery Spring Chinook | 03/31/2024 | 03/31/2024 | |
| Tag Natural Origin Tucannon summer Steelhead for Program Evaluation | H: 158. PIT Tag natural origin steelhead at the Tucannon River Smolt Trap | 06/30/2024 | 06/30/2024 | |
| Maintain PIT Array Sites and Produce accessible, error-checked data sets with metadata | I: 157. Maintain PIT Tag Arrays on the Tucannon River | 11/30/2024 | 11/30/2024 | |
| Produce accessible, error-checked data sets & metadata that describes the summer steelhead return to Tucannon FH | J: 157. Trap adult steelhead at the Tucannon Hatchery Trap | 06/30/2024 | 06/30/2024 | |
| Tag adult Steelhead spawners for Program Evaluation | K: 158. Tag Adult Steelhead at the Weir | 06/30/2024 | 06/30/2024 | |
| Produce accessible, error-checked data sets with metadata to estimate adult returns/escapement and spatial distribution to the Tucannon River | L: 162. Estimate adult returns/escapement and describe spatial distribution of summer steelhead (all groups) to the Tucannon River | 04/01/2024 | 04/01/2024 | |
| Produce accessible, error-checked datasets | M: 157. Genotype DNA Samples from Snake River Fall Chinook | 11/30/2024 | 11/30/2024 | |
| Produce accessible, error-checked datasets | N: 157. WDFW Steelhead Residualism Surveys in the Tucannon River | 06/30/2024 | 06/30/2024 | |
| Deliverable: An accessible, error-checked data set with metadata | O: 162. WDFW Steelhead Residualism Analysis in the Tucannon River | 06/30/2024 | 06/30/2024 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened) |
|
| Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
| Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 185 | Periodic Status Reports for BPA | |||||||
| B | 119 | Project Implementation Management and Contract Administration | |||||||
| C | 165 | Environmental Compliance | |||||||
| D | 132 | WDFW will produce an annual technical progress report for the work completed, showing cumulative results and synthesis for the duration data collection/analysis studies. BPA needs to have the reports fi | |||||||
| E | 157 | Monitor spawning and survival of hatchery steelhead at Lyons Ferry and Tucannon FH | 05/04/2023 | ||||||
| F | 158 | Coded-Wire Tag Hatchery and PIT-Tag juvenile Hatchery Summer Steelhead | 05/04/2023 | ||||||
| G | 158 | PIT-Tag Tucannon River Juvenile Hatchery Spring Chinook | 05/04/2023 | ||||||
| H | 158 | PIT Tag natural origin steelhead at the Tucannon River Smolt Trap | 05/04/2023 | ||||||
| I | 157 | Maintain PIT Tag Arrays on the Tucannon River | 05/04/2023 | ||||||
| J | 157 | Trap adult steelhead at the Tucannon Hatchery Trap | 05/04/2023 | ||||||
| K | 158 | Tag Adult Steelhead at the Weir | 05/04/2023 | ||||||
| L | 162 | Estimate adult returns/escapement and describe spatial distribution of summer steelhead (all groups) to the Tucannon River | |||||||
| M | 157 | Genotype DNA Samples from Snake River Fall Chinook | 05/04/2023 | ||||||
| N | 157 | WDFW Steelhead Residualism Surveys in the Tucannon River | 05/04/2023 | ||||||
| O | 162 | WDFW Steelhead Residualism Analysis in the Tucannon River |