The new global search feature will be permanently enabled in early November 2026. Until then, you may use the toggle to revert to classic search mode (to be retired). New search
Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 84050 REL 19: 1995-057-03 EXP SOUTHERN IDAHO WILDLIFE MITIGATION - POLE CREEK
Project Number:
Project Title:
Southern Idaho Wildlife Mitigation--Shoshone-Paiute Tribes
BPA PM:
Project Stage:
Implementation
Project Area:
Province Subbasin %
Middle Snake Owyhee 100.00%
Contract Number:
84050 REL 19
Contract Title:
1995-057-03 EXP SOUTHERN IDAHO WILDLIFE MITIGATION - POLE CREEK
Contract Continuation:
Previous: Next:
84050 REL 13: 1995-057-03 EXP SOUTHERN IDAHO WILDLIFE MITIGATION - POLE CREEK
Contract Status:
Issued
Contract Description:
Project Objective

The objective of this project is to facilitate wildlife mitigation activities under the Southern Idaho Wildlife Mitigation Program in order to protect, enhance/restore and maintain riparian, shrub-steppe, and scrub-shrub wetland habitat at suitable sites in the Middle Snake Province as mitigation for wildlife losses associated with the construction of Black Canyon and Anderson Ranch hydro-electric projects.  Target species include mule deer, elk, mallard, mink, black-capped chickadee, yellow warbler, yellow-rumped warbler, ruffed grouse, blue grouse, spruce grouse, greater sage-grouse, redband trout, and bull trout. This contract has been developed to cover personnel, administrative, and operating costs.  Many of the objectives and tasks listed throughout this document are conducted on an ongoing basis throughout the contract period.

Background:
In southern Idaho, a BPA debt for wildlife habitat losses identified in the Council's Fish and Wildlife Program remains to be mitigated in the area covered by the Southern Idaho Wildlife Mitigation (SIWM) project.  The SIWM group includes the Shoshone-Paiute Tribes, the Shoshone-Bannock Tribes, and the Idaho Fish and Game Department.

Tools that will be used to identify acquisition, protection, and enhancement sites include the GAP analysis program, BPA impact assessments, regional fish and wildlife data, input from regional professionals and working groups, and maps of available properties.

Location:
The Duck Valley Indian Reservation is 289,820 acres in size and is located on the Idaho/Nevada border. There are approximately 2,300 enrolled Tribal members.  The Reservation is located in the Middle Snake Province in both the Bruneau and Owyhee subbasins.  

The Tribes will concentrate their mitigation efforts in the Middle Snake Province, which is part of the Tribes' aboriginal lands.

This contract includes work elements specific to the Pole Creek wildlife mitigation property in Owyhee County, Idaho. The Tribes are in the process of having a management plan developed for the property but until the plan is reviewed and approved by BPA the work elements contained in this statement of work are considered interim in nature.

No specific operations and maintenance budget has been assigned to the property so work tasks in Fiscal Year 2027 will be implemented and funds drawn from the preacquisition budget in order to complete important work at the ranch until a dedicated contract can be negotiated between the Tribes and BPA for long term stewardship of the property.  
Account Type(s):
Expense
Contract Start Date:
10/01/2026
Contract End Date:
09/30/2027
Current Contract Value:
$114,354
Expenditures:

* Expenditures data includes accruals and are based on data through 30-Sep-2026.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Accrual category:
Habitat O&M
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Christopher Cleveland Shoshone-Paiute Tribes Yes Interested Party cleveland.chris@shopai.org (208) 759-3246
Rachel Green Bonneville Power Administration Yes CO Assistant rjgreen@bpa.gov (503) 230-3882
Heidi Haak Bonneville Power Administration No Technical Contact hlhaak@bpa.gov (541) 922-6856
David Kaplowe Bonneville Power Administration Yes F&W Approver djkaplowe@bpa.gov (503) 230-5365
Verl Miller Bonneville Power Administration Yes COR VCMiller@bpa.gov (503) 230-3468
Addie Parker Shoshone-Paiute Tribes No Administrative Contact parker.addie@shopai.org (208) 759-3100
Carol Perugini Shoshone-Paiute Tribes Yes Contract Manager perugini.carol@shopai.org (775) 763-6015
JESSICA POWER Bonneville Power Administration Yes Contracting Officer jdpower@bpa.gov (503) 230-4023
Joey Thomas Shoshone-Paiute Tribes No Supervisor thomas.joey@shopai.org (208) 759-3246
John Vlastelicia Bonneville Power Administration No Env. Compliance Lead jmvlastelicia@bpa.gov (503) 230-5986


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective Implementation Management and Timely Contract Administration A: 119. Project Administration 09/30/2027
Complete environmental compliance activities B: 165. Satisfy environmental compliance requirements 09/30/2027
Identify properties for Tribes to pursue for acquisition C: 115. SIWM Parcel Identification 09/30/2027
Complete pre-acquisition tasks D: 172. Conduct pre-acquisition tasks 09/30/2027
Prioritized projects based on the most current data E: 114. SIWM Coordination 09/30/2027
Document fence work completed in annual report F: 186. Fence maintenance, maintain infrastructure at Pole Creek Ranch 09/30/2027
Document egg mass survey data from previous year in annual report G: 115. Conduct Columbia spotted frog surveys on Pole Creek Ranch 09/30/2027
Resolve trespass issues H: 26. Investigate trespass on Pole Creek Ranch 09/30/2027
Weed treatment statistics and maps I: 199. Conduct weed treatment activities 09/30/2027
Complete targeted grazing treatment on Pole Creek main parcel J: 199. Prescribed grazing treatment on main parcel of ranch 09/30/2027
2000 Stage one junipers cut K: 198. Cut and lay down 2000 stage one juniper trees from Pole Creek main parcel 09/30/2027
Native grasses and sedges planted at Pond D L: 198. Plant bare root seedlings on Pond D to complement pond bank seeding that occurred in 2023 09/30/2027
Plan for developing water source at Pole Creek property administrative site M: 114. Develop plan for developing water on-site at Pole Creek property 09/30/2027
Completed land management plan for Pole Creek property N: 193. Revise Pole Creek Land Management Plan 09/30/2027
Completed Progress (Annual) Report O: 132. Submit Progress Report for the Period (1/1/26 to 12/31/26) 05/31/2027

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Trout, Interior Redband (O. mykiss gairdnerii)
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
Wildlife
  • 2 instances of WE 199 Remove Vegetation
  • 2 instances of WE 198 Maintain Vegetation
  • 1 instance of WE 193 Produce Land Management Plan
  • 1 instance of WE 26 Investigate Trespass
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 2 instances of WE 114 Identify and Select Projects
  • 2 instances of WE 115 Produce Inventory or Assessment

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Project Administration
B 165 Satisfy environmental compliance requirements
C 115 SIWM Parcel Identification 10/01/2026
D 172 Conduct pre-acquisition tasks
E 114 SIWM Coordination
F 186 Fence maintenance, maintain infrastructure at Pole Creek Ranch 10/01/2026
G 115 Conduct Columbia spotted frog surveys on Pole Creek Ranch 10/01/2026
H 26 Investigate trespass on Pole Creek Ranch
I 199 Conduct weed treatment activities 10/01/2026
J 199 Prescribed grazing treatment on main parcel of ranch 10/01/2026
K 198 Cut and lay down 2000 stage one juniper trees from Pole Creek main parcel 10/01/2026
L 198 Plant bare root seedlings on Pond D to complement pond bank seeding that occurred in 2023
M 114 Develop plan for developing water on-site at Pole Creek property
N 193 Revise Pole Creek Land Management Plan
O 132 Submit Progress Report for the Period (1/1/26 to 12/31/26)
P 185 Periodic Status Reports for BPA