Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 84051 REL 66: 2008-104-00 EXP LAND & WATER ACQUISITION-CTCR QLE
Project Number:
Project Title:
Upper Columbia Land & Water Acquisition
BPA PM:
Project Stage:
Implementation
Project Area:
Province Subbasin %
Columbia Cascade Entiat 25.00%
Methow 25.00%
Okanogan 25.00%
Wenatchee 25.00%
Contract Number:
84051 REL 66
Contract Title:
2008-104-00 EXP LAND & WATER ACQUISITION-CTCR QLE
Contract Continuation:
Previous: Next:
84051 REL 42: 2008-104-00 EXP LAND & WATER ACQUISITION-CTCR QLE
Contract Status:
Issued
Contract Description:
2008-104-00 Land & Water works in partnership with irrigation districts and private landowners to enhance instream flows in local tributaries. These efforts are focused on modernizing irrigation infrastructure, improving conveyance efficiency, and optimizing water withdrawal practices. These projects (PVWUA, Fulton Ditch, Casia Lodge) support sustainable water use while maintaining agricultural productivity and improving aquatic habitat conditions for salmonids.

This contract also encompasses preacquisition activities for land and water in Columbia River tributary subbasins upstream of Rock Island dam. Acquiring land and water rights to for instream flow enhancement in these areas will protect habitat for ESA-listed salmonids including upper Columbia River (UCR) spring Chinook, UCR summer steelhead and bull trout. This habitat will also benefit non-listed species including summer Chinook, coho salmon, sockeye salmon, and Pacific lamprey.

Based upon available information, candidate parcels and water right will be prioritized using the Upper Columbia Biological Strategy and the recently released Upper Columbia Regional Technical Team – Habitat Action Prioritization within the Upper Columbia River Basin.  In both Okanogan and Methow River subbasins, Ecosystem Diagnosis and Treatment (EDT) information exists as well and will be used to prioritize areas for habitat protection. Other sources of information such as subbasin plans, limiting factors analysis, and empirical data (i.e. redd distribution, groundwater input, etc.) may also guide selection of properties to acquire. Priority will be given to parcels that contain or are adjacent to watercourses with high quality fish habitat but are at risk of degradation due to development potential, and lands that contain or are adjacent to watercourses that provide opportunity for habitat restoration activities that benefit ESA listed fish. At this time the Colville Tribes do not propose to use funds from Project 2008-104-00 for post-acquisition restoration activities. Rather, appropriate restoration or habitat quality improvement projects shall use other sources of funding, potential sources of which are the state Salmon Recovery Funding Board, Priest Rapids Coordinating Committee Habitat Subcommittee, or Habitat Conservation Plan (HCP) Tributary Committee for both Douglas and Chelan County Public Utility Districts, and other BPA funded projects (e.g. Project 2023-001-00).  
Account Type(s):
Expense
Contract Start Date:
07/01/2026
Contract End Date:
06/30/2027
Current Contract Value:
$1,171,493
Expenditures:

* Expenditures data includes accruals and are based on data through 30-Apr-2026.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Accrual category:
Planning & Design
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Review all projects with Environmental Compliance Lead B: 165. CCT - Environmental Compliance 06/30/2027
Prioritized projects C: 114. Transaction Development and Facilitation 06/30/2027
Water Rights Documentation D: 154. Develop water rights transactions 06/30/2027
Effective implementation management and timely contract administration E: 119. Manage BPA Contracting Requirements 06/30/2027
Water Rights Documentation Submission F: 164. Upper Columbia Basin Water acquisition 06/30/2027
Submit Land Purchase Documentation G: 172. Pre Acquisition Activities 06/30/2027
Completed Progress (Annual) Report H: 132. Submit Progress Report for the period 7/01/2026 to 6/30/2027 06/30/2027
Upload copies of 60% to 100% Design I: 175. Loup Loup Creek Irrigation Efficiency Project, 60% - 100% Design 06/30/2027
Upload 100% Design J: 175. Fulton Ditch 100% Design 06/30/2027
Upload Plan to CBfish K: 174. Antoine Creek Source Switch 06/30/2027
Upload Plan to CBfish L: 174. Foghorn Ditch Feasibility Study 06/30/2027
New well(s) installed and irrigation system hook up M: 208. Casia Lodge Source Switch Project 06/30/2027

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 175 Produce Design
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
  • 1 instance of WE 164 Acquire Water Instream
Steelhead (Oncorhynchus mykiss) - All Populations
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 208 Irrigation Infrastructure Construction or Replacement
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
  • 1 instance of WE 164 Acquire Water Instream

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 165 CCT - Environmental Compliance
C 114 Transaction Development and Facilitation
D 154 Develop water rights transactions
E 119 Manage BPA Contracting Requirements
F 164 Upper Columbia Basin Water acquisition
G 172 Pre Acquisition Activities
H 132 Submit Progress Report for the period 7/01/2026 to 6/30/2027
I 175 Loup Loup Creek Irrigation Efficiency Project, 60% - 100% Design
J 175 Fulton Ditch 100% Design
K 174 Antoine Creek Source Switch
L 174 Foghorn Ditch Feasibility Study
M 208 Casia Lodge Source Switch Project