Province | Subbasin | % |
---|---|---|
Upper Snake | Snake Upper | 100.00% |
Previous: | Next: |
---|---|
84068 REL 15: 2008-905-00 EXP SUPPLEMENTATION PROJECTS |
* Expenditures data includes accruals and are based on data through 31-Mar-2025.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Effective and timely contract administration | B: 119. Management and Administration | 03/31/2026 | ||
Completion of Environmental Compliance Requirements | C: 165. Provide all EC documentation to BPA | 03/31/2026 | ||
Fish Marking Completed. | D: 158. Panther Creek Chinook Salmon Project | 02/28/2026 | ||
Produce accessible, error-checked datasets | E: 157. Panther Creek Chinook Salmon Project - Monitoring, Research, and Evaluation | 03/31/2026 | ||
All data analyzed and stored in secure data repositories. | F: 162. Analyze monitoring, research, and evaluation data | 03/31/2026 | ||
Research findings available to share with project partners, watershed managers, and other stakeholders in the Panther Creek basin | G: 161. Disseminate data from Panther Creek Supplementation Work | 03/31/2026 | ||
Outplant up to 800,000 BY 2025 Chinook Salmon Eyed Eggs in Panther Creek | H: 176. BY 2025 production activities for the Panther Creek Chinook Salmon Project | 11/30/2025 | ||
Completed Progress (Annual) Report | I: 132. Submit Progress Report for the period (04/01/2025) to (03/31/2026) | 03/31/2026 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | |||||||
B | 119 | Management and Administration | |||||||
C | 165 | Provide all EC documentation to BPA | |||||||
D | 158 | Panther Creek Chinook Salmon Project | 04/01/2025 | ||||||
E | 157 | Panther Creek Chinook Salmon Project - Monitoring, Research, and Evaluation | 04/01/2025 | ||||||
F | 162 | Analyze monitoring, research, and evaluation data | |||||||
G | 161 | Disseminate data from Panther Creek Supplementation Work | |||||||
H | 176 | BY 2025 production activities for the Panther Creek Chinook Salmon Project | 04/01/2025 | ||||||
I | 132 | Submit Progress Report for the period (04/01/2025) to (03/31/2026) |