| Province | Subbasin | % |
|---|---|---|
| Intermountain | Pend Oreille | 100.00% |
| Previous: | Next: |
|---|---|
| 84069 REL 36: 1992-061-02 EXP ALBENI FALLS WILDLIFE MITIGATION - KALISPEL |
|
* Expenditures data includes accruals and are based on data through 31-Oct-2025.
| Full Name | Organization | Write Permission | Contact Role | Work Phone | |
|---|---|---|---|---|---|
| Daphne Day | Bonneville Power Administration | No | Env. Compliance Lead | deday@bpa.gov | (503) 230-5263 |
| Ray Entz | Kalispel Tribe | Yes | Supervisor | rentz@knrd.org | (509) 445-1147 |
| Bart George | Kalispel Tribe | Yes | Contract Manager | bgeorge@kalispeltribe.com | (509) 671-6149 |
| David Kaplowe | Bonneville Power Administration | Yes | F&W Approver | djkaplowe@bpa.gov | (503) 230-5365 |
| Kendra Maroney | Kalispel Tribe | Yes | Technical Contact | kmaroney@kalispeltribe.com | (509) 671-2376 |
| TC Peterson | Kalispel Tribe | Yes | Contract Manager | tcpeterson@kalispeltribe.com | (509) 445-1147 |
| JESSICA POWER | Bonneville Power Administration | Yes | CO Assistant | jdpower@bpa.gov | (503) 230-4023 |
| Elizabeth Santana | Bonneville Power Administration | Yes | COR | easantana@bpa.gov | (503) 230-3560 |
| Jolene Seymour | Kalispel Tribe | No | Administrative Contact | jseymour@kalispeltribe.com | (509) 445-1147 |
| Karen Wolfe | Bonneville Power Administration | Yes | Contracting Officer | ktwolfe@bpa.gov | (503) 230-3448 |
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Effective implementation management and timely contract administration | B: 119. Oversight of New Projects, Implementation, Construction, O&M, RM&E w/ participating agencies | 02/28/2026 | ||
| Final Report | C: 165. Complete Permit Applications and Provide Documentation to Obtain Compliance. | 02/28/2026 | ||
| Final Report | D: 191. Internal Coordination | 02/28/2026 | ||
| Final Status Reporting | E: 172. Pre-Acquisition work | 02/28/2026 | ||
| Completed Progress (Annual) Report | F: 132. Annual Report for 2023 Contract Cycle | 02/28/2026 | ||
| Final Report | G: 186. Fence Maintenance Idaho | 01/05/2026 | ||
| Quarterly and Final Report | H: 181. Create and enhance Wetland Ponds on Washington Management Area | 11/01/2025 | ||
| Final Report | I: 47. Plant created wetland areas with trees and shrubs. | 02/28/2026 | ||
| Final Report | J: 26. Secure Properties and Provide Enforcement Management. | 02/28/2026 | ||
| Final Report | K: 38. Maintain Access to Water Control Structures. | 02/01/2026 | ||
| Final Report | L: 186. Maintain Existing Water Control Structures and Replace Flow Control Culverts on Wetland Enhancement Sites. | 02/28/2026 | ||
| Final Report | M: 186. Maintain buildings | 02/28/2026 | ||
| Final Report | N: 199. Removal Vegetation Idaho Mitigation Lands | 02/28/2026 | ||
| Final Report | O: 198. Maintain planted vegetation in Washington | 10/28/2025 | ||
| Final Report | P: 188. Provide/maintain parking and kiosks for visitors as needed | 02/28/2026 | ||
| Final Report | Q: 198. Maintain planted vegetation in Idaho | 10/30/2025 | ||
| Final Report | R: 186. Fence Maintenance Washington | 10/28/2025 | ||
| Final Report | S: 47. Plant Native Trees and Shrubs-WA management units. | 02/28/2026 | ||
| Final Report | T: 199. Remove Vegetation WA Mitigation Properties | 02/28/2026 | ||
| Final Report | U: 198. Maintain field Nursery for plant materials | 02/28/2026 | ||
| Final Report | V: 193. Complete Management Plans for new and update existing plans. | 02/28/2026 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Wildlife |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 185 | Periodic Status Reports for BPA | |||||||
| B | 119 | Oversight of New Projects, Implementation, Construction, O&M, RM&E w/ participating agencies | |||||||
| C | 165 | Complete Permit Applications and Provide Documentation to Obtain Compliance. | |||||||
| D | 191 | Internal Coordination | |||||||
| E | 172 | Pre-Acquisition work | |||||||
| F | 132 | Annual Report for 2023 Contract Cycle | |||||||
| G | 186 | Fence Maintenance Idaho | 03/27/2025 | ||||||
| H | 181 | Create and enhance Wetland Ponds on Washington Management Area | 03/27/2025 | ||||||
| I | 47 | Plant created wetland areas with trees and shrubs. | 03/27/2025 | ||||||
| J | 26 | Secure Properties and Provide Enforcement Management. | |||||||
| K | 38 | Maintain Access to Water Control Structures. | 03/27/2025 | ||||||
| L | 186 | Maintain Existing Water Control Structures and Replace Flow Control Culverts on Wetland Enhancement Sites. | 03/27/2025 | ||||||
| M | 186 | Maintain buildings | 03/27/2025 | ||||||
| N | 199 | Removal Vegetation Idaho Mitigation Lands | 03/27/2025 | ||||||
| O | 198 | Maintain planted vegetation in Washington | 03/27/2025 | ||||||
| P | 188 | Provide/maintain parking and kiosks for visitors as needed | 03/27/2025 | ||||||
| Q | 198 | Maintain planted vegetation in Idaho | 03/27/2025 | ||||||
| R | 186 | Fence Maintenance Washington | 03/27/2025 | ||||||
| S | 47 | Plant Native Trees and Shrubs-WA management units. | 03/27/2025 | ||||||
| T | 199 | Remove Vegetation WA Mitigation Properties | 03/27/2025 | ||||||
| U | 198 | Maintain field Nursery for plant materials | 03/27/2025 | ||||||
| V | 193 | Complete Management Plans for new and update existing plans. |