Contract 85739: 2010-001-00 EXP STONEWATER RANCH FLOW AND PASSSAGE IMPROVEMENT
Project Number:
Title:
Upper Columbia Programmatic Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 25.00%
Methow 25.00%
Okanogan 25.00%
Wenatchee 25.00%
Contract Number:
85739
Contract Title:
2010-001-00 EXP STONEWATER RANCH FLOW AND PASSSAGE IMPROVEMENT
Contract Continuation:
Previous: Next:
n/a
  • 88411: 2010-001-00 EXP STONEWATER RANCH FLOW AND PASSSAGE IMPROVEMENT
Contract Status:
Closed
Contract Description:
Under this contract Trout Unlimited (TU) will develop a conceptual, 30%, 60% - 80% and final designs collaboratively with BPA.  The main deliverables of this contract include development of a collaborative design that incorporates stakeholders’ inputs for the Stonewater Ranch Flow and Passage Improvement Project on Beaver Creek, a tributary to the Wenatchee River.  The Project will replace two Beaver Creek surface water diversions with a groundwater supply (surface diversions are located at approximate RM 2 and RM 2.5), install efficient and water-conserving irrigation application infrastructure, replace or correct an improperly installed beaver dam flow device (approximate RM 2), and replace an undersized Beaver Creek culvert crossing (approximate RM 1.75) with a prefabricated bridge or similar fish-friendly structure.  The primary goals of this project are to increase instream flows through irrigation efficiency, improve fish passage, and enhance physical habitat conditions.

This project will address tributary-focused limiting factors identified in the 2019-2021 CRS BiOp including degradation of floodplain connectivity and function, channel structure and complexity, and stream flow with secondary benefits to LWD recruitment and water quality. It will address ecological concerns identified in the UC Biological Strategy for the subject assessment unit, which is a Tier I assessment with a  #2 restoration priority, including channel structure and form and peripheral and transitional habitat.  The objectivs of the project will be met through application of multiple non-prescriptive restoration techniques identified in the UC Biological Strategy, including ‘water quantity restoration’, ‘decrease water temperature’, and ‘provide improved fish passage’. Many primary limiting factors related to flow including current anthropogenic impairments to perennial flow, suboptimal summer rearing temperatures, large predicted reductions in summer flow and large predicted increases in summer stream temperatures will be addressed by this project.  This project was approved for funding through Bonneville Power Administration (BPA)/Upper Columbia Salmon Recovery Board (UCSRB) FY2020 Targeted Solicitation Notice and was reviewed and ranked by the Regional Technical Team (RTT).  The RTT is a team of technical experts familiar with the priority areas and limiting factors, and identify projects that will best contribute to the recovery of salmonids and other species of concern in the Upper Columbia.

TU will be responsible for managing the project.  

This contract covers final design (Contract Design Year 1 FY2020) and construction is planned for FY2021.


PROJECT PARTNER COLLABORATION

The Upper Columbia Salmon Recovery Board (UCSRB) is co-sponsor to Upper Columbia Programmatic Habitat Project.  As such they are a key partner to BPA and within the UC region, a local first point of contact for general Programmatic inquiries and coordination.  It is possible from time to time that the UCSRB may seek general project information and updates from TU to preform and fulfill their necessary role and obligations under the Northwest Power and Conservation Council approved Programmatic with BPA.  TU has agreed to coordinate with UCSRB and accommodate any such requests.  As examples, UCSRB may request the following:

Participation in periodic BPA-UCSRB-Sponsor check-in calls, if/as needed
Information about partner contributions for reporting cost-share
Copies of presentations about the BPA-UCSRB Programmatic project  

The contractor TU, its designated agents, sub-consultants and project stakeholders will be available, responsive and will collaboratively address contract related issues during the term of the contract.  Contract issues include but are not limited to technical, policy, regulatory, project management and associated elements related to the project.  Successful execution of this contract is contingent on alignment of the preceding contract issues with the BFAI or BPI and BPA contracting processes, project management plans, design review protocols (including but not limited to BPA HIP design review, Technical and Design Team guidance, review, input, comments, integration, stakeholder congruence with proposed actions and decisions rendered by 1) the project executive team (BPA, TU).  Arbitration and dispute resolution will occur relative to the following two tier escalation ladder: 1) conference with the project Executive Team and 2) Direct consultation between program managers.  

TU Contract Manager and TU's design consultant (a mutually agreed to and selected subcontractor) will all cooperate, coordinate, collaborate, and maintain effective communication with the BPA PM/COR, EC Lead, HIP Review Lead, and Hydraulic Engineer(s) during the entire length of this contract with regards to project design.  TU and its subcontractors will address BPA comments and concerns, and the three entities will arrive at a mutually beneficial consensus.  TU contract manager will upload all of the subcontracts being executed under this contract to cbfish.org.
Account Type(s):
Expense
Contract Start Date:
09/15/2020
Contract End Date:
09/14/2021
Current Contract Value:
$39,118
Expenditures:
$39,118

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Theo Burgoon Trout Unlimited (TU) Yes Contract Manager theo.burgoon@tu.org (509) 630-6858
Jamie Cleveland Bonneville Power Administration Yes COR jacleveland@bpa.gov (503) 230-3160
Joseph Connor Bonneville Power Administration Yes F&W Approver jwconnor@bpa.gov (503) 230-3172
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Lisa Pelly Trout Unlimited (TU) No Supervisor lpelly@tu.org (509) 888-0970
Aaron Penvose Trout Unlimited (TU) Yes Interested Party apenvose@tu.org (509) 888-0970
Sarah Walker Upper Columbia Salmon Recovery Board No Interested Party sarah.walker@ucsrb.org (509) 630-8226
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Permitting Complete A: 165. Obtain Required Permits, Authorizations, and Documentation for the Stonewater Ranch Flow and Passage project 09/14/2021
Project Design Complete B: 175. Obtain Designs for Irrigation Infrastructure, Fish Passage Impediment Removal, and Bridge 09/14/2021
Produce Stakeholder Vetted Final Design C: 191. Coordinate with Landowner and Regional Project Proponents 09/14/2021
Effective implementation management and timely contract administration F: 119. Manage BPA Contracting Requirements 09/14/2021 09/14/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain Required Permits, Authorizations, and Documentation for the Stonewater Ranch Flow and Passage project
B 175 Obtain Designs for Irrigation Infrastructure, Fish Passage Impediment Removal, and Bridge
C 191 Coordinate with Landowner and Regional Project Proponents
D 185 Periodic Status Reports for BPA
E 132 No Report Required Per COR
F 119 Manage BPA Contracting Requirements