Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 87055: 2007-399-00 EXP UP SALMON SCREEN TRIB PASS CONST
Project Number:
Title:
Upper Salmon Screen Tributary Passage
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
87055
Contract Title:
2007-399-00 EXP UP SALMON SCREEN TRIB PASS CONST
Contract Continuation:
Previous: Next:
84422: 2007-399-00 EXP UP SALMON SCREEN TRIB PASS
  • 89620: 2007-399-00 EXP UP SALMON SCREEN TRIB PASS
Contract Status:
Closed
Contract Description:
To provide management and operational support for a capital construction program dedicated to the protection of anadromous fish from loss in water diversions, improve fish passage at diversions for juvenile and adult anadromous fish, and improve stream flow conditions where possible.  Staff will process environmental regulatory documents, provide oversight to archaeologists and consulting engineers, engage in scoping activities, and negotiate with private landowners for habitat projects.  All projects require compliance with State of Idaho and Federal regulations including, but not limited to, IDAPA Title 42, IDAPA Title 36, National Environmental Policy Act, Clean Water Act, Endangered Species Act, Federal Land Management Policy Act, National Historical Preservation Act, and Magnuson-Stevens Fishery Conservation and Management Act.  

Project Coordination:  The Idaho Department of Fish & Game (IDFG) coordinates other funding sources with this Bonneville Power Administration (BPA) contract in order to maximize the potential for anadromous fish recovery efforts in the Salmon River basin.  

In this contract period, The IDFG Anadromous Fish Screen, Passage, and Habitat Program expects to finalize designs, fabricate, install, and maintain six new fish screens including the Lemhi River-21 (L-21), Lemhi River-26 (L-26), Lemhi River-27 (L-27), Lemhi River-28 (L-28), Canyon Creek-02 (LCanyC-02), and East Fork Salmon River-16 (SEF-16) fish screens.  This includes one new fish screen on a previously unscreened diversions, and 5 older fish screens that are being replaced with new screens designed to meet NMFS Juvenile Fish Screen Criteria.  These projects combined with screen approximately 108 cubic feet per second (c.f.s.) in critical habitat for Chinook salmon, steelhead, and bull trout.  Additionally, one small grade control rock weir will be installed on the Canyon Creek, and a railcar bridge (89 ft) for the East Fork-16 fish screen access.  Included in this capital contract is the request for the purchase of excavator to replace an older excavator (1994) for the installation and maintenance of the 280 fish screens for the program.

Account Type(s):
Expense
Contract Start Date:
02/01/2021
Contract End Date:
01/31/2022
Current Contract Value:
$848,000
Expenditures:
$848,000

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Contract renewal and management actions A: 119. Project administration. 01/31/2022 01/31/2022
Provide BPA with all necessary EC/permit B: 165. Complete all environmental compliance tasks 01/31/2022 01/31/2022
Completed FSOC/NOAA Criteria Fish Screen C: 208. Lemhi River-21 (L-21) Fish Screen 12/24/2021 12/24/2021
Completed FSOC-NOAA Criteria Fish Screen D: 208. Lemhi River-26 (L-26) Fish Screen 12/01/2021 12/01/2021
Completed FSOC/NOAA Criteria Fish Screen E: 208. Lemhi River-28 (L-28) Fish Screen. 12/31/2021 12/31/2021
Completed FSOC/NOAA Criteria Fish Screen F: 208. East Fork Salmon River-16 (SEF-16) Fish Screen 12/31/2021
Canyon Creek-02 Diversion Installation G: 208. Canyon Creek-02 Diversion Project 01/31/2022
90 Foot Railcar Bridge for East Fork Salmon River-16 Fish Screen Project. H: 208. East Fork Salmon River-16 Fish Screen Access Bridge 01/31/2022
Completed FSOC/NOAA Criteria Fish Screen I: 208. Canyon Creek-02 (LCanyCR-02) Fish Screen 01/31/2022
Final Project Designs J: 175. Final Designs or Construction 11/15/2021 11/01/2021
Completed FSOC/NOAA Criteria Fish Screen K: 208. Lemhi River-27 (L-27) Fish Screen 12/01/2021 12/01/2021
Completed Annual Report L: 132. Submit Progress Report for the period February 1st, 2020 to January 31, 2021 01/31/2022

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 208 Irrigation Infrastructure Construction or Replacement
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 175 Produce Design
  • 7 instances of WE 208 Irrigation Infrastructure Construction or Replacement
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 175 Produce Design
  • 8 instances of WE 208 Irrigation Infrastructure Construction or Replacement

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Project administration.
B 165 Complete all environmental compliance tasks
C 208 Lemhi River-21 (L-21) Fish Screen 06/28/2021
D 208 Lemhi River-26 (L-26) Fish Screen 06/28/2021
E 208 Lemhi River-28 (L-28) Fish Screen. 06/28/2021
F 208 East Fork Salmon River-16 (SEF-16) Fish Screen 08/24/2021
G 208 Canyon Creek-02 Diversion Project 05/28/2021
H 208 East Fork Salmon River-16 Fish Screen Access Bridge 08/24/2021
I 208 Canyon Creek-02 (LCanyCR-02) Fish Screen 05/28/2021
J 175 Final Designs or Construction 05/28/2021
K 208 Lemhi River-27 (L-27) Fish Screen 06/28/2021
L 132 Submit Progress Report for the period February 1st, 2020 to January 31, 2021
M 185 Periodic Status Reports for BPA