Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 90369: 2010-001-00 EXP BARKLEY BEAR IMPLEMENTATION - PHASE 3
Project Number:
Title:
Upper Columbia Programmatic Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 25.00%
Methow 25.00%
Okanogan 25.00%
Wenatchee 25.00%
Contract Number:
90369
Contract Title:
2010-001-00 EXP BARKLEY BEAR IMPLEMENTATION - PHASE 3
Contract Continuation:
Previous: Next:
86023: 2010-001-00 EXP BARKLEY BEAR IMPLEMENTATION - PHASE 2
Contract Status:
Closed
Contract Description:
This contract covers the work for the third and final phase, which will be completed during the summer of 2022.

Methow Salmon Recovery Foundation (MSRF) and its partners, including BPA, Bureau of Reclamation (Reclamation), and UCSRB are implementing a reach-scale salmon habitat enhancement project in the Middle Methow (M2) River in FFYs 2020, 2021, and 2022.  Project actions were developed under previous contracts for the M2 Barkley Bear Habitat Project funded through the BPA targeted solicitation process.  The project is being implemented in three phases, with the first phase implemented in the summer of 2020 under contract 83074 and the second Phase implemented in summer 2021 under contract 86023. This contract covers the work for the third and final phase, which will be completed during the summer of 2022.

The goal of this Barkley Bear Phase 3 contract is to complete all remaining project elements and final site restoration, ensure the benefits of previously implemented actions, and maintain the riparian plantings to meet permit requirements related to survival.  

The majority of environmental compliance for project activities, including Section 7 ESA consultation via the BPA HIP process, and Section 106, have been completed under previous contracts.  Remaining environmental compliance items include HIP renewal for calendar year 2022 prior to Phase 3 actions.  SEPA review, WDFW Hydraulic Project Authorization, and Corps of Engineers Nationwide permits, County Shorelines and Floodplain Development, and Department of Ecology water quality permits have also been completed under previous contracts, but may need to be updated or renewed for construction in 2022.  

Lastly,  MSRF expects to complete all remaining work items under ongoing contracts for project construction and revegetation/site restoration actions to be completed under this contract. In the event that either contractor previously selected is unavailable during the required work window, MSRF will select a qualified contractor from our maintained roster.

The contractor (MSRF), its designated agents, sub-consultants and project stakeholders will be available to BPA to work collaboratively to address any contract related issues during the term of the contract.  Contract issues include but are not limited to technical, policy, regulatory, project management and associated elements related to the project.  Successful execution of this contract is contingent on alignment of the preceding contract issues with the BIC and BPA contracting processes, project management plans, and integration of input and comments from BPA.

MSRF’s Contract Manager and consultants will all cooperate, coordinate, collaborate, and maintain effective communication with BPA PM/COR, EC Lead, HIP Review Lead, and Hydraulic Engineer during the entire length of this contract.  MSRF and its subcontractors will address BPA comments and concerns, and the two entities will arrive at a mutual beneficial consensus.  MSRF contract manager will upload all the subcontracts executed under this contract in cbfish.org.

MSRF will not submit an annual report under this contract.  MSRF will provide the Upper Columbia Salmon Recovery Board (UCSRB) sufficient information so they, UCSRB, can assemble a comprehensive annual report for all contracts under project #2010-001-00 including this contract.  Report will then be submitted by the Upper Columbia Salmon Recovery Board (UCSRB) to BPA to fulfill deliverable.  UCSRB will submit and upload report under project 2010-001-00, Upper Columbia Programmatic Habitat.
Account Type(s):
Expense
Contract Start Date:
06/01/2022
Contract End Date:
05/31/2023
Current Contract Value:
$106,817
Expenditures:
$106,817

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Complete environmental compliance permitting processes A: 165. Obtain/Renew Required Permits, Authorizations, and Documentation for the Barkley Bear project 12/31/2022 12/28/2022
Effective implementation management and timely contract administration B: 119. Manage BPA Contracting Requirements 05/31/2023 05/31/2023
Remove irrigation head gate E: 208. Remove Barkley Diversion Head gate 09/15/2022 09/15/2022
Completed channel improvements F: 30. Improve Side Channel Connections 09/15/2022 09/15/2022
Increased floodplain complexity G: 29. Instream and Floodplain Complexity Elements 09/15/2022 09/15/2022
Maintain native riparian plantings H: 198. Maintain Native Riparian Plantings 05/31/2023 05/31/2023

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 208 Irrigation Infrastructure Construction or Replacement
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 208 Irrigation Infrastructure Construction or Replacement

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain/Renew Required Permits, Authorizations, and Documentation for the Barkley Bear project
B 119 Manage BPA Contracting Requirements
C 185 Periodic Status Reports for BPA
D 132 No Report Required Per COR
E 208 Remove Barkley Diversion Head gate 06/01/2022
F 30 Improve Side Channel Connections 06/01/2022
G 29 Instream and Floodplain Complexity Elements 06/01/2022
H 198 Maintain Native Riparian Plantings 06/01/2022