Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 91955: 2008-301-00 EXP HAB RESTORATION PLAN/DESIGN/IMPLEMENT WSR
Project Number:
Title:
Habitat Restoration Planning/Design/Implementation within boundaries of Warm Springs Reservation, lower Deschutes River, Oregon
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Deschutes 100.00%
Contract Number:
91955
Contract Title:
2008-301-00 EXP HAB RESTORATION PLAN/DESIGN/IMPLEMENT WSR
Contract Continuation:
Previous: Next:
89827: 2008-301-00 EXP HAB RESTORATION PLAN/DESIGN/IMPLEMENT WSR
  • 94335: 2008-301-00 EXP HAB RESTORATION PLAN/DESIGN/IMPLEMENT WSR
Contract Status:
Issued
Contract Description:
This contract will support ongoing aquatic habitat restoration work on the Warm Springs Reservation within the Deschutes Basin. This is the 2023 contract for project 2008-301-00 that provides the operational funding to implement the Aquatic Restoration Strategy developed in 2018 for watershed on the Warm Springs Reservation. The majority of this contract is covering FY23 program costs (personnel, vehicles, office space ect.).  Habitat restoration implementation will be completed though the following stand alone contract and extension:  

Shitike Creek Headworks Removal and Restoration  (Contract 89810)

Under this contract the riparian protection fence network along with water developments will be maintained protecting over 50 miles of critical anadromous fish habitat in the Warm Springs River Watershed.  Maintenance and improvements will be focused on the lower Warm Springs River and lower Deschutes River protection fence segments.  A design will be developed for the 2024 placement of LWD within the Warm Springs River and Beaver Creek.

Project planning and prioritization will be a primary focus of this contract and continue to occur using the scoring matrix developed to accompany the 2018 Aquatic Restoration Strategy for the Reservation lands.  This scoring matrix will be used to show the relative rank or score of current and future projects proposed on the Reservation using BPA funds.  These scoring outputs and project descriptions will be updated through the reporting work elements under this contract, and provide project planning for future contracts.  
Account Type(s):
Expense
Contract Start Date:
03/01/2023
Contract End Date:
02/29/2024
Current Contract Value:
$548,844
Expenditures:
$455,541

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Jay Chong Bonneville Power Administration Yes Contracting Officer jxchong@bpa.gov (503) 230-4007
Israel Duran Bonneville Power Administration Yes Env. Compliance Lead induran@bpa.gov (503) 230-3967
El Freda Gentry Confederated Tribes of Warm Springs No Administrative Contact elfreda.gentry@wstribes.org (541) 553-3375
Brad Houslet Confederated Tribes of Warm Springs Yes Interested Party brad.houslet@ctwsbnr.org (541) 553-2039
Lyman Jim Confederated Tribes of Warm Springs Yes Supervisor lyman.jim@ctwsbnr.org (541) 553-3587
Jessica Power Bonneville Power Administration No CO Assistant jdpower@bpa.gov (503) 230-4023
Angelina SiJohn Confederated Tribes of Warm Springs No Administrative Contact angelina.sijohn@wstribes.org (541) 553-3219
Allan Whiting Bonneville Power Administration Yes COR AHWhiting@bpa.gov (503) 230-3786
Jesse Wilson Bonneville Power Administration Yes F&W Approver jcwilson@bpa.gov (503) 230-4506


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration A: 119. Manage Restoration Program 02/29/2024
Environmental Compliance Complete B: 165. Obtain Environmental Compliance 02/29/2024
Education and Outreach Complete C: 99. Fisheries Habitat Staff administration of the "Eggs to Fry" Program in Jefferson County schools. 02/29/2024
Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish D: 114. Prioritize and Select Future Projects for Planning, Design, and Implementation 02/29/2024
Construction Management Complete E: 100. Shitike Construction Management 12/30/2023
Trespass Livestock Managed F: 26. Investigate trespass within riparian exclosures 02/29/2024
Fence Maintained G: 186. Maintain Riparian Fencing 11/30/2023
Water Developments Maintained H: 186. Maintain Water Developments 02/29/2024
Produce Final LWD Addition Plans I: 175. WSR LWD Phase II and Middle Beaver Creek LWD 02/29/2024
Log Springs Riparian Fence Complete J: 40. Log Springs Meadow Riparian Fence Extension. 02/29/2024
Completed Annual Report K: 132. Submit Progress Report for the period (3/1/2020) to (2/28/2023) 02/29/2024

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 26 Investigate Trespass
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 100 Construction Management
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 26 Investigate Trespass
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage Restoration Program
B 165 Obtain Environmental Compliance
C 99 Fisheries Habitat Staff administration of the "Eggs to Fry" Program in Jefferson County schools.
D 114 Prioritize and Select Future Projects for Planning, Design, and Implementation
E 100 Shitike Construction Management
F 26 Investigate trespass within riparian exclosures
G 186 Maintain Riparian Fencing 03/01/2023
H 186 Maintain Water Developments 03/01/2023
I 175 WSR LWD Phase II and Middle Beaver Creek LWD 03/01/2023
J 40 Log Springs Meadow Riparian Fence Extension. 03/01/2023
K 132 Submit Progress Report for the period (3/1/2020) to (2/28/2023)
L 185 Periodic Status Reports for BPA