| Province | Subbasin | % |
|---|---|---|
| Columbia River Estuary | Columbia Estuary | 50.00% |
| Elochoman | 5.00% | |
| Grays | 5.00% | |
| Lower Columbia | Columbia Lower | 30.00% |
| Kalama | 5.00% | |
| Sandy | 5.00% |
* Expenditures data includes accruals and are based on data through 31-Oct-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Environmental Compliance Complete | B: 165. Ensure All Environmental Compliance is Complete | 09/30/2024 | 09/30/2024 | |
| Effective implementation management and timely contract administration | C: 119. Provide Management and Administration of Projects | 09/30/2024 | 09/30/2024 | |
| Completed 2023 Annual Report uploaded to cbfish.org | D: 132. Submit ANNUAL Progress Report for the period Jan 2023 to Dec 2023 | 04/30/2024 | 04/30/2024 | |
| Submit 2023 Stewardship Fund Reports | E: 141. Other Reports for BPA | 07/26/2024 | 07/26/2024 | |
| Submit LAND MANAGEMENT PLANS to BPA | F: 193. Submit outstanding LAND MANAGEMENT PLANS to BPA | 09/30/2024 | 09/30/2024 | |
| Work With Landowners and WWR if approached about potential project | H: 114. Meet with stakeholders when approached with new project | 09/30/2024 | 09/30/2024 | |
| Regional Data Sharing/CEERP Coordination Meetings/ERTG Participation | I: 191. Expert Regional Technical Group (ERTG) Participation | 09/30/2024 | 09/30/2024 | |
| Submit Final Realty Package for BPA-identified Priority Acquisitions | J: 172. Conduct All Necessary Due Diligence Related to Land Acquisitions | 09/30/2024 | 09/30/2024 | |
| COLUMBIA STOCK RANCH-- Vegetation Maintenance | K: 198. COLUMBIA STOCK RANCH -- CWTD RESTORATION -- Maintain Vegetation | 09/30/2024 | 09/30/2024 | |
| LOWER ELOCHOMAN 3--Site Preparation for Planting | L: 199. LOWER ELOCHOMAN III -- RESTORATION -- Vegetation Control | 09/30/2024 | 09/30/2024 | |
| LOWER ELOCHOMAN 3--Vegetation Established | M: 47. LOWER ELOCHOMAN III -- RESTORATION -- Planting | 09/30/2024 | 09/30/2024 | |
| LOWER ELOCHOMAN 3--Plant Maintenance | N: 198. LOWER ELOCHOMAN III -- RESTORATION -- Plant Maintenance | 09/30/2024 | 09/30/2024 | |
| RAISTAKKA ROAD--60% Project Design completed | O: 175. RAISTAKKA--DESIGN-- 60% DESIGN | 09/30/2024 | 09/30/2024 | |
| RESTORATION DESIGN CHALLENGES-- Reed Canarygrass Study | Q: 157. RESTORATION DESIGN CHALLENGES Project | 09/30/2024 | 09/30/2024 | |
| Collect Level 3 AEMR-- PRE-construction--RAISTAKKA ROAD | R: 157. RAISTAKKA FLOODPLAIN - Collect PRE-construction AEMR Level 3 Data | 09/30/2024 | 09/30/2024 | |
| Collect Level 3 AEMR data for LE2--Post-construction--Year 5 | S: 157. LOWER ELOCHOMAN II - Collect POST-Construction Year 5 AEMR Level 3 data | 09/30/2024 | 09/30/2024 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (Oncorhynchus tshawytscha) - All Populations |
|
| Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened) |
|
| Chum (Oncorhynchus keta) - Columbia River ESU (Threatened) |
|
| Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened) |
|
| Coho (O. kisutch) - Unspecified Population |
|
| Steelhead (Oncorhynchus mykiss) - All Populations |
|
| Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened) |
|
| Wildlife |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 185 | Periodic Status Reports for BPA | |||||||
| B | 165 | Ensure All Environmental Compliance is Complete | |||||||
| C | 119 | Provide Management and Administration of Projects | |||||||
| D | 132 | Submit ANNUAL Progress Report for the period Jan 2023 to Dec 2023 | |||||||
| E | 141 | Other Reports for BPA | |||||||
| F | 193 | Submit outstanding LAND MANAGEMENT PLANS to BPA | |||||||
| G | 132 | Submit Data for LCEP 2023 RME Report | |||||||
| H | 114 | Meet with stakeholders when approached with new project | |||||||
| I | 191 | Expert Regional Technical Group (ERTG) Participation | |||||||
| J | 172 | Conduct All Necessary Due Diligence Related to Land Acquisitions | |||||||
| K | 198 | COLUMBIA STOCK RANCH -- CWTD RESTORATION -- Maintain Vegetation | 05/16/2024 | ||||||
| L | 199 | LOWER ELOCHOMAN III -- RESTORATION -- Vegetation Control | 05/16/2024 | ||||||
| M | 47 | LOWER ELOCHOMAN III -- RESTORATION -- Planting | 05/16/2024 | ||||||
| N | 198 | LOWER ELOCHOMAN III -- RESTORATION -- Plant Maintenance | 05/16/2024 | ||||||
| O | 175 | RAISTAKKA--DESIGN-- 60% DESIGN | 07/19/2023 | ||||||
| P | 27 | *CANCELED---RAISTAKKA--RESTORATION--Structure Removal | 08/24/2023 | ||||||
| Q | 157 | RESTORATION DESIGN CHALLENGES Project | 07/19/2023 | ||||||
| R | 157 | RAISTAKKA FLOODPLAIN - Collect PRE-construction AEMR Level 3 Data | 07/19/2023 | ||||||
| S | 157 | LOWER ELOCHOMAN II - Collect POST-Construction Year 5 AEMR Level 3 data | 07/19/2023 |