Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 94307: 2007-398-00 EXP FY24 YTAHP
Project Number:
Title:
Yakima Basinwide Tributary Passage and Flow
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
94307
Contract Title:
2007-398-00 EXP FY24 YTAHP
Contract Continuation:
Previous: Next:
92053: 2007-398-00 EXP YAK TRIB ACCESS & HABITAT PRGM 2023
Contract Status:
Issued
Contract Description:
Under CR-366941 the following work and services will be accomplished by the YTAHP Team:

BPA funding for FY 2024 will support the implementation of 15 fish passage and habitat restoration projects, ongoing riparian vegetation and site stewardship on 6 projects and provided significant work toward project development, permits, design and/or funding for an additional 10 projects. The projects completed in FY 2024 will cumulatively result in screening 29.1 cfs of diverted surface water, restore fish passage to 5.7 miles of tributary habitat and install over .18 mile of riparian planting on eight streams in the Yakima Basin.  

Project Background:

The Yakima Tributary Access & Habitat Program was formed in 2001 in response to the listing of Middle Columbia River steelhead and bull trout under the Endangered Species Act.  The objectives of the program are to screen surface water diversions, restore fish passage and enhance salmonid habitat.  The focus of the program is on Yakima River tributaries that historically supported salmonids and on riparian areas where fish passage is restored.  The YTAHP fills a unique and important role in salmonid recovery by facilitating a voluntary program in which private landowners can come into compliance with fish screening and passage laws.

In general, projects on tributaries are prioritized sequentially, moving upstream from the confluence with the Yakima River; as projects are completed, the regained habitat is connected to the mainstem and available to anadromous fish.  YTAHP has concentrated on tributaries upstream of Union Gap where salmonids are known to have occurred historically.  Streams have been surveyed for fish passage barriers, analyzed for screening of diversions, and assessed for habitat quality using WDFW’s Salmonid Screening, Habitat Enhancement, and Restoration (SSHEAR) protocol.  At times projects may appear out of sequence but do fit in the context of multi-year planning.  YTAHP uses BPA funds to leverage cost share funds from a variety of other sources, thus expanding the funding pie.  For passage projects, YTAHP works with local landowners and irrigation water delivery entities who voluntarily participate.  BPA funds are used only for planning, design, permitting and implementation.  There are no changes to facility ownership status or operation and maintenance responsibilities resulting from YTAHP work.  BPA takes on no responsibilities for ownership or O&M.

The Current YTAHP Roles and Responsibilities are as follows:
Brian Miller- Washington Resource & Conservation (RC&D) Council YTAHP Program Manager
Mike Tobin- North Yakima Conservation District (NYCD) District Manager
Justin Bader- NYCD Yakima Tributary Access and Habitat Program Coordinator
Anna Lael- Kittitas Conservation County District (KCCD) District Manager
Mark Crowley- KCCD Conservation Planner for YTAHP projects
Cassandra Weeks- WDFW YTAHP Permitting, Environment Compliance & Watershed Project Coordination  
Account Type(s):
Expense
Contract Start Date:
04/01/2024
Contract End Date:
03/31/2025
Current Contract Value:
$1,200,241
Expenditures:

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration B: 119. RC&D management of the YTAHP program & subcontractor administrative work 03/31/2025
Watershed coordination activities have been completed C: 191. Watershed Coordination 03/31/2025
Completed Annual Report D: 132. Submit annual report for 04/01/2023 - 03/31/2024 (FY 2023) 09/01/2024
Technical input into project development E: 122. Technical Review 03/31/2025
Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish F: 114. Identify and Select projects 08/01/2024
Produce Environmental Documentation G: 165. Produce Environmental Compliance Documentation - Permitting 03/31/2025
Vegetation maintenance activities completed H: 198. Naches River- Edgar Riparian Protection and Enhancement- Phase 1- Maintain Vegetation (Continued from WE H on the FY 2023 Contract 92053) 03/31/2025
Vegetation Maintenance activities completed I: 198. Naches River- Edgar Riparian Protection and Enhancement- Phase 2- Maintain Vegetation (Related to WE L on Contract 92053) 03/31/2025
Fish screen is installed. J: 208. Wenas Creek RM 8.0- Wagner- Fish Screen (New) 01/01/2025
Vegetation maintenance activities completed K: 198. Wenas Creek- McKinney- Maintain Vegetation- (Continued from WE J on Contract 92053) 03/31/2025
Fence installed L: 40. Wenas Creek RM 18.0- Leier Riparian Buffer Establishment- Install Fence- (New) 03/31/2025
Upload final design set M: 175. Wenas Creek- Purdin Ditch Fish Screening & Passage- Produce Design (Continued from WE M on Contract 92053) 09/30/2024
Diversion removal is complete N: 208. Wenas Creek- Purdin Ditch Fish Screening & Passage- Remove Diversion (Continued for WE N on Contract 92053) 01/01/2025
Fish screen is installed O: 208. Wenas Creek- Purdin Ditch Fish Screening & Passage- Install Fish Screen (New) 01/01/2025
Planting of vegetation is complete P: 47. Wenas Creek- Purdin Ditch Fish Screening & Passage- Plant Vegetation (Continued from WE 0 on Contract 92053) 03/31/2025
Upload final design set Q: 175. Wenas Creek- Fish Passage and Screening Project- Produce Design (Continued from WE P on Contract 92053) 03/31/2025
Upload final design set R: 175. Wenas Creek- Haas Fish Screening and Passage- Produce Design (New) 03/31/2025
Complete Permit Ready Designs S: 175. Coleman Creek 4.6 - Raap (continued from WE Q in 2022 Contract 89876) 03/31/2025
Project Design Phase Complete T: 175. Cascade at Coleman Intersection (continued from WE R in 2023 Contract 92053) 01/01/2025
Project Design Phase Complete U: 175. Naneum Creek - Ellensburg Water Company Intersection (continued from WE T in 2023 Contract 92053) 01/01/2025
Develop Design to Permit Ready Status V: 175. Cooke Creek 3.86 and Cooke 4.25 - Fish Screen and Passage - Continued from WE AF CCR48725 03/31/2025
Permit Ready Designs Completed W: 175. Naneum Creek at McCullough Rd Fish Passage (new) 03/31/2025
Permit Ready Designs X: 175. Naneum 1.56 Culvert Fish Passage (new) 03/31/2025
Complete design for automated brush Y: 175. Manastash Creek Diversions Operations & Maintenance - Keach/Jensen Automated Brush 01/01/2025
Maintain Riparian Vegetation Z: 198. Parke Creek 1.01 Maintenance (connected to WE X in 2023 contract 92053) 03/31/2025
Complete Native Tree & Shrub Planting AA: 47. Coleman Creek 2.5 Planting (connected to WE AD in contract 92053) 12/01/2024
Plant trees and shrubs AB: 47. Naneum 2.9 and 3.2 Planting (WE AB in Contract 92053 and WE AE in this Contract) 03/31/2025
Install Trees and Shrubs AC: 47. Coleman 4.4 Schomer Planting (connected to WE Z in 2023 contract 92053) 01/01/2025
Plant at project site AD: 47. Cooke 4.25 Planting (new) 03/31/2025
Fish Passage AE: 85. Naneum 3.2 Fish Passage (continued from WE S and WE AB in 2023 Contract 92053) 03/31/2025
Complete Fish Screen and Irrigation Infrastructure Construction AF: 208. Coleman 4.4 Schomer - Fish Screen and Irrigation System (Continuation of WE Z in 2023 contract 92053) 05/31/2024
Fish Screen and irrigation infrastructure completed AG: 208. Cooke Creek 4.25 Fish Screen and Passage (New) 03/31/2025
Fish Screen and Passage Complete AH: 208. Cascade at Coleman Creek Fish Passage and Screening 03/31/2025
Fish Passage Barrier Removed AI: 208. Naneum Creek - Ellensburg Water Company Intersection 03/31/2025
Complete Compressor Replacements AJ: 186. Manastash Creek Diversions Operation & Maintenance (CCR- 48725 in 2022/23) 03/31/2025
Automated Brush System Operational AK: 186. Manastash Creek Diversions Operations & Maintenance - Keach/Jensen Automated Brush 03/31/2025
Install Fish Screen AL: 208. Whiskey Creek Barriers RM 1.5-1.7 (connected to WE V in contract 92053) 03/31/2025

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 4 instances of WE 198 Maintain Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 40 Install Fence
  • 5 instances of WE 47 Plant Vegetation
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 114 Identify and Select Projects
  • 10 instances of WE 175 Produce Design
  • 8 instances of WE 208 Irrigation Infrastructure Construction or Replacement

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 119 RC&D management of the YTAHP program & subcontractor administrative work
C 191 Watershed Coordination
D 132 Submit annual report for 04/01/2023 - 03/31/2024 (FY 2023)
E 122 Technical Review
F 114 Identify and Select projects
G 165 Produce Environmental Compliance Documentation - Permitting
H 198 Naches River- Edgar Riparian Protection and Enhancement- Phase 1- Maintain Vegetation (Continued from WE H on the FY 2023 Contract 92053) 04/01/2024
I 198 Naches River- Edgar Riparian Protection and Enhancement- Phase 2- Maintain Vegetation (Related to WE L on Contract 92053)
J 208 Wenas Creek RM 8.0- Wagner- Fish Screen (New)
K 198 Wenas Creek- McKinney- Maintain Vegetation- (Continued from WE J on Contract 92053)
L 40 Wenas Creek RM 18.0- Leier Riparian Buffer Establishment- Install Fence- (New)
M 175 Wenas Creek- Purdin Ditch Fish Screening & Passage- Produce Design (Continued from WE M on Contract 92053)
N 208 Wenas Creek- Purdin Ditch Fish Screening & Passage- Remove Diversion (Continued for WE N on Contract 92053)
O 208 Wenas Creek- Purdin Ditch Fish Screening & Passage- Install Fish Screen (New)
P 47 Wenas Creek- Purdin Ditch Fish Screening & Passage- Plant Vegetation (Continued from WE 0 on Contract 92053)
Q 175 Wenas Creek- Fish Passage and Screening Project- Produce Design (Continued from WE P on Contract 92053)
R 175 Wenas Creek- Haas Fish Screening and Passage- Produce Design (New)
S 175 Coleman Creek 4.6 - Raap (continued from WE Q in 2022 Contract 89876)
T 175 Cascade at Coleman Intersection (continued from WE R in 2023 Contract 92053)
U 175 Naneum Creek - Ellensburg Water Company Intersection (continued from WE T in 2023 Contract 92053)
V 175 Cooke Creek 3.86 and Cooke 4.25 - Fish Screen and Passage - Continued from WE AF CCR48725
W 175 Naneum Creek at McCullough Rd Fish Passage (new)
X 175 Naneum 1.56 Culvert Fish Passage (new)
Y 175 Manastash Creek Diversions Operations & Maintenance - Keach/Jensen Automated Brush
Z 198 Parke Creek 1.01 Maintenance (connected to WE X in 2023 contract 92053)
AA 47 Coleman Creek 2.5 Planting (connected to WE AD in contract 92053)
AB 47 Naneum 2.9 and 3.2 Planting (WE AB in Contract 92053 and WE AE in this Contract)
AC 47 Coleman 4.4 Schomer Planting (connected to WE Z in 2023 contract 92053)
AD 47 Cooke 4.25 Planting (new)
AE 85 Naneum 3.2 Fish Passage (continued from WE S and WE AB in 2023 Contract 92053)
AF 208 Coleman 4.4 Schomer - Fish Screen and Irrigation System (Continuation of WE Z in 2023 contract 92053)
AG 208 Cooke Creek 4.25 Fish Screen and Passage (New)
AH 208 Cascade at Coleman Creek Fish Passage and Screening
AI 208 Naneum Creek - Ellensburg Water Company Intersection
AJ 186 Manastash Creek Diversions Operation & Maintenance (CCR- 48725 in 2022/23)
AK 186 Manastash Creek Diversions Operations & Maintenance - Keach/Jensen Automated Brush
AL 208 Whiskey Creek Barriers RM 1.5-1.7 (connected to WE V in contract 92053)