Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 96337: 2010-001-00 EXP CF GOODWIN SIDE CHANNEL FINAL DESIGN 2
Project Number:
Title:
Upper Columbia Programmatic Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 25.00%
Methow 25.00%
Okanogan 25.00%
Wenatchee 25.00%
Contract Number:
96337
Contract Title:
2010-001-00 EXP CF GOODWIN SIDE CHANNEL FINAL DESIGN 2
Contract Continuation:
Previous: Next:
95507: 2010-001-00 EXP GOODWIN SIDE CHANNEL FINAL DESIGN
Contract Status:
Issued
Contract Description:
This is contract 2 of 2 for the final design of Goodwin Side Channel. Contract 1 of 2 is 95507.

Cascade Fisheries (CF) will continue to lead  a design process to complete a habitat restoration project at the Goodwin Side Channel Site (GSC). The goals for this restoration project are: 1. Improve rearing habitat in the GSC by increasing connection to groundwater; 2. Enhance the floodplain and side channel habitat functions through improved connections with the river while taking advantage of the benefits provided by  groundwater inflow.; 3.Promote native woody vegetation cover throughout the floodplain by planting where current RCG patches exist and preserving existing mature native riparian forest.; 4. Increase Large Wood Cover and habitat complexity; 5.Increase floodplain inundation.  For this contract period CF will advance designs from 60% - Final, and complete environmental compliance tasks.

Under a previous contract (90897) an alternatives analysis was conducted where conceptual alternatives that all meet the high level project goals, but with different methods and metrics, were developed. The design team chose the most suitable alternative to advance to the next design stage. After a preferred alternative was chosen, the designs were progressed to 15% (conceptual) level.

Under a previous contract (93203) in FY 2024 Cascade Fisheries, the design consultant, BPA, and project stakeholder worked collaboratively to advance designs to the 30% (preliminary) and 60% (permit set) level. At each design phase, Cascade Fisheries consulted with BPA and project stakeholders to gather feedback that was incorporated into the next design phase. Cascade Fisheries lead the effort to complete EC tasks including wetland determinate and cultural resources survey between the 30% and permit set design levels.

For the current contract Cascade Fisheries, the design consultant, BPA, and project stakeholders will work collaboratively to advance designs from the permit set (60%) to final designs. This contract will also include applying for all necessary environmental/regulatory approvals necessary for the project. Environmental compliance is expected to include an HPA (WDFW), NWP 27 (USACE), Section 401 CWA certification (ECY), No-rise and floodplain permit (Chelan County), ESA compliance (BPA), Section 106 NHPA compliance (BPA).

The project area occurs on 10.75 acres on the left bank floodplain of the Wenatchee River starting at RM 11.15 and ending at RM 11.5. The project falls within the Wenatchee River Ollala 01 reach of the Wenatchee River – Ollala Canyon Assessment Unit within the Upper Columbia Salmon Recovery Region’s prioritization scheme. This Assessment Unit is listed as a tier 1 priority for Steelhead restoration. At the reach scale, winter rearing is listed as a high priority life stage for both spring chinook and steelhead, while summer rearing is a medium priority life stage for steelhead. The highest ranking limiting factors for this reach are cover-wood and off-channel/side-channel habitat, and the second highest ranking limiting factor is floodplain connectivity.

The current habitat benefit of the existing side channel is limited by its infrequent surface water connection with the mainstem. From 2000-2020, the side channel was connected (at or above 8,000 CFS) for an average of only 36 days a year. This connection overwhelmingly occurred during spring freshet, and the side channel is inaccessible during the critical summer and winter rearing months.

The proposed restoration project improves floodplain connectivity and frequency of fish access to the Goodwin Side Channel, which addresses the highest-ranking species, life stages, and limiting factors for this reach of the Wenatchee River.
Account Type(s):
Expense
Contract Start Date:
02/01/2025
Contract End Date:
01/31/2026
Current Contract Value:
$34,000
Expenditures:
$2,345

* Expenditures data includes accruals and are based on data through 28-Feb-2025.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Prepare and Submit Permit applications B: 165. Initiate and continue Work for Required Permits, Authorizations, and Documentation for the project 09/14/2025
Complete Final Designs C: 175. CF and BPA collaboratively develop Final project designs 09/14/2025
Effective implementation management and timely contract administration D: 119. Manage BPA contracting requirements 09/14/2025

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 165 Initiate and continue Work for Required Permits, Authorizations, and Documentation for the project
C 175 CF and BPA collaboratively develop Final project designs
D 119 Manage BPA contracting requirements