| Ensure environmental compliance requirements are complete |
A: 165. Complete Environmental Compliance Requirements |
|
03/31/2026 |
|
| Install HDX antennas and cameras in old fishway and the lamprey ramps |
B: 157. Install video cameras for lamprey ramps and the old fishway and HDX antenna in old fishway |
|
03/31/2026 |
|
| Review video of hard drives for lamprey passage. |
C: 162. Video review for lamprey recorded passing old fishway and lamprey ramps |
|
03/31/2026 |
|
| Capture, Mark, Inspect Lamprey and Operate HDX Array(s) at Willamette Falls |
D: 157. Collect and examine lamprey to calculate adult escapement |
|
03/31/2026 |
|
| Analyze PIT tag detections from PIT antenna arrays |
E: 162. Analyze PIT tag detections from antenna arrays in WFFL, old fishway, and Abernethy Creek |
|
03/31/2026 |
|
| Tag Adult Lamprey at Willamette Falls |
F: 158. HDX tag adult Pacific lamprey at Willamette Falls |
|
03/31/2026 |
|
| Develop Plan to collect tissue samples of ammocoetes above and below Willamette Falls, begin sampling and analyze tissue samples. |
G: 156. Collect tissue samples from ammocoetes near tributary mouths and rearing habitats in the mainstem Willamette River downstream of Willamette Falls |
|
03/31/2026 |
|
| Conduct Creel Surveys |
H: 157. Conduct creel surveys |
|
03/31/2026 |
|
| Estimate Lamprey Harvest at Willamette Falls |
I: 162. Record and Report Harvest |
|
03/31/2026 |
|
| Collect Larval Lamprey Samples |
J: 157. Collect tissue samples from ammocoetes |
|
03/31/2026 |
|
| Collect Larval Lamprey Samples |
K: 162. Analysis of tissue samples from larval lamprey |
|
03/31/2026 |
|
| Willamette Falls Pacific Lamprey Technical Working Group (WFPLTWG) |
L: 191. Participate in Willamette Falls Pacific Lamprey Technical Working Group (WFPLTWG) |
|
03/31/2026 |
|
| Effective implementation management and timely contract administration |
M: 119. Manage Project |
|
03/31/2026 |
|
| Completed Progress (Annual) Report |
N: 132. Submit Progress Report for the period January 1, 2021 - December 31, 2021 |
|
03/31/2026 |
|
| Completed Progress (Annual) Report |
O: 132. Submit Progress Report for the period January 1, 2022 - December 31, 2022 |
|
03/31/2026 |
|
| Completed Progress (Annual) Report |
P: 132. Submit Progress Report for the period January 1, 2023 - December 31, 2023 |
|
03/31/2026 |
|
| Completed Progress (Annual) Report |
Q: 132. Submit Progress Report for the period January 1, 2024 - December 31, 2024 |
|
03/31/2026 |
|