| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Effective implementation management and timely contract administration | A: 119. Administration of BPA contract. | 09/30/2027 | ||
| Submit relevant Environmental Compliance documentation | B: 165. Complete Environmental Compliance Requirements. | 07/01/2027 | ||
| Rebuilt and properly functioning automated PLC system and crane at the Three Mile Falls Dam left bank fish screen complex. | C: 208. Repairs on the Three Mile Falls Dam Left Bank Fish Screen Complex | 07/01/2027 | ||
| Rebuilt and properly functioning Feed Fish Screen Complex | D: 208. Refurbish the Feed Fish Screen Complex | 07/01/2027 | ||
| Rebuilt and properly functioning Maxwell Fish Screen Complex. | E: 208. Refurbish the Maxwell Fish Screen Complex | 07/01/2027 | ||
| Upgraded Stanfield Fish Screen Complex | F: 208. Upgrade the Stanfield Fish Screen Complex | 07/01/2027 | ||
| Upgraded Westland Fish Screen Complex | G: 208. Upgrade the Westland Fish Screen Complex | 07/01/2027 | ||
| Refurbished the Gardena/Burlingame fish screen facility. | H: 208. Refurbish the Gardena/Burlingame Fish Screen Complex | 07/01/2027 | ||
| Upgraded Little Walla Walla Fish Screen Complex | I: 208. Refurbish the Little Walla Walla Fish Screen Complex | 07/01/2027 | ||
| Garden City Lowden II Fish Screen Cleaning System Repaired | J: 208. Repair or replace the fish screen cleaning system at the Garden City Lowden II Fish Screen Complex | 07/01/2027 | ||
| Completed Progress (Annual) Report | L: 132. Submit Progress Report for the period October 2025 through September 2026 and from October 2026 through September 2027 | 08/15/2027 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 119 | Administration of BPA contract. | |||||||
| B | 165 | Complete Environmental Compliance Requirements. | |||||||
| C | 208 | Repairs on the Three Mile Falls Dam Left Bank Fish Screen Complex | 10/02/2025 | ||||||
| D | 208 | Refurbish the Feed Fish Screen Complex | 10/02/2025 | ||||||
| E | 208 | Refurbish the Maxwell Fish Screen Complex | |||||||
| F | 208 | Upgrade the Stanfield Fish Screen Complex | |||||||
| G | 208 | Upgrade the Westland Fish Screen Complex | 10/02/2025 | ||||||
| H | 208 | Refurbish the Gardena/Burlingame Fish Screen Complex | 10/02/2025 | ||||||
| I | 208 | Refurbish the Little Walla Walla Fish Screen Complex | 10/02/2025 | ||||||
| J | 208 | Repair or replace the fish screen cleaning system at the Garden City Lowden II Fish Screen Complex | 10/02/2025 | ||||||
| K | 185 | Periodic Status Reports for BPA | |||||||
| L | 132 | Submit Progress Report for the period October 2025 through September 2026 and from October 2026 through September 2027 |