Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 73982 REL 78: 2000-038-01 EXP WALLA WALLA HATCHERY EPC CONSTRUCTION SUPPORT
Project Number:
Title:
Walla Walla Hatchery Plan and Preliminary Design – Expense
BPA PM:
Stage:
Closed
Area:
Province Subbasin %
Columbia Plateau Walla Walla 100.00%
Contract Number:
73982 REL 78
Contract Title:
2000-038-01 EXP WALLA WALLA HATCHERY EPC CONSTRUCTION SUPPORT
Contract Continuation:
Previous: Next:
73982 REL 16: 2000-038-01 EXP WALLA WALLA HATCHERY - CTUIR DESIGN SUPPORT
Contract Status:
Closed
Contract Description:
This contract covers CTUIR work to participate in finalizing the NPCC Step process, resulting in a hatchery plan, design, cost estimate and environmental clearance for the South Fork Walla Walla spring chinook hatchery to proceed to construction.  Key deliverables of this contract include: finalizing the hatchery HGMP, providing input to EC (permitting, ESA, NEPA), input to/review of final design, input to NPCC Step 2 and 3 decisions,  CTUIR work to track construction progress, and preparation to assume O&M of the hatchery facilities.
Account Type(s):
Expense
Contract Start Date:
10/01/2019
Contract End Date:
09/30/2021
Current Contract Value:
$178,872
Expenditures:
$178,872

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Julie Burke Umatilla Confederated Tribes (CTUIR) Yes Administrative Contact julieburke@ctuir.org (541) 429-7292
Gary James Umatilla Confederated Tribes (CTUIR) Yes Supervisor garyjames@ctuir.org (541) 429-7285
Jon Lovrak Umatilla Confederated Tribes (CTUIR) Yes Contract Manager jonlovrak@ctuir.org (541) 429-7278
Jennifer McKenna Bonneville Power Administration No CO Assistant jmmckenna@bpa.gov (503) 314-8915
Cody Rodriguez Bonneville Power Administration Yes Contracting Officer clrodriguez@bpa.gov (503) 230-4262
Carolyn Sharp Bonneville Power Administration Yes Env. Compliance Lead casharp@bpa.gov (503) 230-5206
John Skidmore Bonneville Power Administration Yes F&W Approver jtskidmore@bpa.gov (503) 230-5494
Andrew Traylor Bonneville Power Administration Yes COR awtraylor@bpa.gov (503) 230-3268


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Relevant Administrative documentation B: 119. Construction Review Budget Package 09/30/2021 09/30/2021
Provide Technical Review of Construction Submittals C: 122. CTUIR input to Submittals and Requests for Information (RFIs) 09/30/2021 09/30/2021
Water Quality Report D: 165. Environmental Compliance Support Services 06/30/2021 12/31/2020
Construction Management Complete E: 100. Hatchery Construction Oversight 09/30/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 04/01/2018
B 119 Construction Review Budget Package 04/01/2018
C 122 CTUIR input to Submittals and Requests for Information (RFIs) 04/01/2018
D 165 Environmental Compliance Support Services
E 100 Hatchery Construction Oversight
F 132 Submit Progress Report for the period (MMM YYYY) to (MMM YYYY)