Contract 82051: 2001-032-00 EXP HANGMAN CREEK FISHERIES
Project Number:
Title:
Coeur D'Alene Fisheries Enhancement-Hangman Creek
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Spokane 100.00%
Contract Number:
82051
Contract Title:
2001-032-00 EXP HANGMAN CREEK FISHERIES
Contract Continuation:
Previous: Next:
78986: 2001-032-00 EXP HANGMAN CREEK FISHERIES
Contract Status:
Closed
Contract Description:
The Scope of Work and budget presented in this document represent the activities associated with the Coeur 'd Alene Tribe's resident fish enhancement project on Hangman Creek within the Spokane Sub-basin corresponding to the contract period May 1, 2019 to April 30, 2020. Total amount of this budget request is $355,000 The Coeur d'Alene Tribe has requested that BPA transfer $47,900 dollars from funds available to BPA project #199004400 to Project #200103200 in order to meet the Tribe's restoration priorities.

Ongoing objectives include:
o Determine areas that are in need of restoration to supply spawning and rearing habitat for Redband and other naturally reproducing trout.
o Support an educational outreach program to facilitate a “holistic watershed protection process managed thru BPA Project #199004400.
o Implement a habitat/in-stream restoration strategy that will provide self-sustaining, naturally reproducing, and harvestable populations of native trout.
o Implement a monitoring and evaluation program to determine the effectiveness of habitat/in-stream restoration project.

The Hangman Creek watershed has experienced land use changes that have resulted in degraded in-stream habitat for fish and other aquatic species. Conserving habitats in the upper tributaries is a priority along with increasing fish distribution and reconnecting fragmented populations. A primary method of accomplishing habitat enhancement is to enlist beaver in a holistic strategy to address multiple ecological and hydrologic process deficiencies. Beaver influenced channel and floodplain morphology and vegetation historically, but alteration of their habitat and trapping have substantially reduced their influence and the ability for their populations to rebound. The absence of large wood to serve as foundations for dams and impacts to the availability of suitable dam-building material in the riparian zone have influenced the resilience of beaver dams currently. If conditions could be made more favorable for their re-establishment, it is likely that channel conditions and in-stream habitat could be restored to a more desired state, thereby restoring fish habitat, the riparian zone, and the floodplain in the process.

The following work will facilitate measured progress toward achieving the objectives for the project during this scope of work:

1) Implementing restoration designs for utilizing beaver as a partner in restoring natural hydrologic function, overbank flow, and connection between streams and riparian habitats.

WE D:  A large scale design will be completed in this contract for construction in 2020.

WE E - Reactivation of historic channel alignments in Hangman Creek on the newly acquired Shaw property.

A 3rd EPA grant awarded as an $60,000 cost share will supply plant materials for two work elements 1) WE G for new acres and another riparian treatment in the form of cedar plugs and potted trees, willow cuttings and large deciduous potted plants. 2) WE J for maintenance of acres already treated in the k'wne' 'ulchiyark'wmntsut project area.

WE H involves funding for plant materials donated by Spokane Falls Chapter of Trout Unlimited.

WE K will provide a temporary source of food and building materials for beaver by providing clippings at key locations with active beaver colonies. This work element will also repair analog beaver dams built in the previous contract

WE K - Construction of 1,000 feet of wildlife exclusion fencing to minimize damage to plantings by animal browse.

In addition to restoration of Hangman Creek, construction of a short access road and parking lot for tribal cultural activities to include, but not limited to, Chinook salmon stocking
for subsistence fishing (WE F)

2) RM&E activities to track status and trends for water quality and fish populations and their movement.
This includes WE's for continuous temperature monitoring throughout the watershed (WE S&X); as well as discharge and hydrolab monitoring (WE R), RM&E activities associated with trout populations and movement include summer backpack electroshock surveys (WE O & SU), evaluate status and trends in redband trout populations, and spring migration trapping (WE N & V ) and associated pit tagging technology (WEs P, T & W) to monitor seasonal movements of redband trout in specific reaches of the upper Hangman watershed.

Fixed PIT-tag antennae arrays will be installed at three locations on Hangman Creek to monitor mainstem use by redband trout: one at the mouth of Indian Creek; at the mouth of Nehchen Creek; and a new station within the k'wne' 'ulchiyark'wmtsut restoration area. New tributary stations will be installed at Indian Creek, Smith Creek, Nehchen Creek and Sheep Creek.

WE Q is a non-native fish removal project on Nehchen Creek where a genetically confirmed population of illegally introduced cutthroat trout have occupied the upper reaches of the mainstem. Non-native fish removal began in summer of 2015. WE N and O help monitor the responses to removal efforts.

3) Reporting on project activities and outcomes.
A technical report will be drafted during this contract as a means of reporting on the RM&E data compiled from the 2017-2018 field seasons (WE AB)  
Account Type(s):
Expense
Contract Start Date:
05/01/2019
Contract End Date:
04/30/2020
Current Contract Value:
$350,851
Expenditures:
$350,851

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Daniel Affonso Bonneville Power Administration No Interested Party dxaffonso@bpa.gov (503) 230-3893
Thomas Biladeau Coeur D'Alene Tribe Yes Interested Party tbiladeau@cdatribe-nsn.gov (209) 686-6307
Lisa Dexter Bonneville Power Administration Yes Contracting Officer lldexter@bpa.gov (503) 230-3893
Jon Firehammer Coeur D'Alene Tribe Yes Technical Contact jfirehammer@cdatribe-nsn.gov (208) 686-7037
Cameron Heusser Coeur D'Alene Tribe Yes Interested Party cheusser@cdatribe-nsn.gov (208) 686-5521
David Kaplowe Bonneville Power Administration Yes F&W Approver djkaplowe@bpa.gov (503) 230-5365
Bruce Kinkead Coeur D'Alene Tribe Yes Contract Manager bkinkead@cdatribe-nsn.gov (208) 686-6071
Timothy Ludington Bonneville Power Administration Yes COR tsludington@bpa.gov (503) 230-4988
Robert Shull Bonneville Power Administration Yes Env. Compliance Lead rwshull@bpa.gov (503) 230-3962
Angelo Vitale Coeur D'Alene Tribe Yes Supervisor ajvitale@cdatribe-nsn.gov (208) 686-6903


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Completed NEPA Checklist A: 165. NEPA analysis and documentation 04/30/2020 04/30/2020
Selection of Restoration Projects B: 114. Identify and select new restoration projects in the Hangman watershed 04/30/2020
Designs completed for summer of 2019 and 2020 C: 175. Produce Designs to Reactivate Side Channels and agrade channel on Shaw Property 04/30/2020
Completed channel construction D: 30. Connect Relict Side Channels on Hangman Creek: Shaw Property 04/30/2020 09/30/2019
Enhanced Floodplain Communities on Hangman Creek E: 47. Riparian enhancement at Hangman Creek, EPA Grant 2018 04/03/2020 03/18/2020
Enhanced Floodplain Communities on Hangman Creek F: 47. Riparian enhancement at Hangman Creek, Trout Unlimited 2019 04/30/2020 03/18/2020
Provide native willow cuttings for future restoration projects G: 47. Native Willow Nursery 04/30/2020 03/27/2020
Newly planted riparian plants maintained, protected, and or replaced H: 198. Maintain vegetation on Hangman Creek, k'wne' 'ulchiyark'wmtsut 04/30/2020 03/20/2020
Provide dam building materials for 6 dams I: 186. Maintain beaver dams in Hangman Creek with hardwood supplementation 04/30/2020 03/18/2020
Installation of Wildlife Exclusion Measures J: 40. Install wildlife exclusion fencing on Hangman Creek 04/30/2020 03/13/2020
Roads and Culverts Surveyed and Results Summarized K: 115. Forest Road Inventory and Assessment in portions of Hangman Creek Watershed 04/30/2020 04/30/2020
Produce data from redband trout captured in migrant traps in Hangman Creek watershed L: 157. Sample Redband trout and non-native salmonids using migration traps 04/30/2020 04/01/2020
Produce Data from Electroshock Sampling of Fish in Hangman Watershed M: 157. Sample Redband trout in Hangman Creek utilizing backpack electro-shocking 10/04/2019 09/13/2019
PIT-tag juvenile and adult Redband Trout in Hangman Creek project area. N: 158. Uniquely mark Redband Trout in Upper Hangman 04/30/2020 04/30/2020
Removal of non-native cutthroat trout from Nehchen Creek O: 190. Remove non-native cutthroat trout from Nehchen Creek 04/30/2020 04/30/2020
Collect Water Quality Data in the Hangman Creek Watershed P: 157. Collect water quality and quantity data in Hangman Creek 04/30/2020 03/20/2020
Collect Continuous Temperature Data in the Hangman Creek Watershed Q: 157. Monitor water temperature in Hangman Creek 02/07/2020 02/28/2020
Collect Interrogation Data from Stationary PIT tag Antenna Arrays in the Hangman Creek Watershed R: 157. Collect data and maintain fixed PIT tag antennae arrays 04/30/2020 04/30/2020
Examination of distribution and density patterns at the sub-watershed and watershed scale S: 162. Analyze data generated from sampling salmonids in tributary habitats in upper Hangman watershed 02/14/2020 01/03/2020
Abundance and life-history information for migratory redband trout in upper Hangman T: 162. Analyze data generated for redband trout captured in migrant traps in Hangman Creek 02/14/2020 01/03/2020
Pit Tag Array Data Analyzed U: 162. Analyze data logged at stationary PIT antenna arrays for Redband trout in Hangman Creek 02/14/2020 01/06/2020
Water Temperature Analyzed V: 162. Analyze stream temperature data in Hangman Creek 04/03/2020 04/03/2020
GIS Summarization of Project Data Collected and Updated Trout Distribution for input to Regional Map W: 161. Summarize Redband trout population status and habitat in Hangman Creek using GIS 04/30/2020 04/30/2020
Coordination of RM&E and Restoration for Redband partners in the Upper Columbia basin X: 191. Coordinate restoration and RM&E with Upper Columbia and Spokane Sub-basin partners 04/01/2020 04/28/2020
Completed Annual Report Y: 132. Submit Progress Report for the period (May 2017 - April 2019) 04/14/2020 04/14/2020
Management and Administration of Project Z: 119. Manage and administer projects 04/30/2020 04/30/2020

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Cutthroat Trout, Westslope (O. c. lewisi)
  • 1 instance of WE 190 Remove, Exclude and/or Relocate Animals
  • 1 instance of WE 47 Plant Vegetation
Trout, Interior Redband (O. mykiss gairdnerii)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 40 Install Fence
  • 3 instances of WE 47 Plant Vegetation
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 175 Produce Design
  • 5 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
  • 4 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 NEPA analysis and documentation 05/01/2019
B 114 Identify and select new restoration projects in the Hangman watershed 05/01/2019
C 175 Produce Designs to Reactivate Side Channels and agrade channel on Shaw Property 03/12/2019
D 30 Connect Relict Side Channels on Hangman Creek: Shaw Property 03/12/2019
E 47 Riparian enhancement at Hangman Creek, EPA Grant 2018 03/12/2019
F 47 Riparian enhancement at Hangman Creek, Trout Unlimited 2019 05/01/2019
G 47 Native Willow Nursery 03/15/2019
H 198 Maintain vegetation on Hangman Creek, k'wne' 'ulchiyark'wmtsut 03/12/2019
I 186 Maintain beaver dams in Hangman Creek with hardwood supplementation 03/12/2019
J 40 Install wildlife exclusion fencing on Hangman Creek 03/15/2019
K 115 Forest Road Inventory and Assessment in portions of Hangman Creek Watershed 03/12/2019
L 157 Sample Redband trout and non-native salmonids using migration traps 03/12/2019
M 157 Sample Redband trout in Hangman Creek utilizing backpack electro-shocking 03/12/2019
N 158 Uniquely mark Redband Trout in Upper Hangman 03/12/2019
O 190 Remove non-native cutthroat trout from Nehchen Creek 03/12/2019
P 157 Collect water quality and quantity data in Hangman Creek 03/12/2019
Q 157 Monitor water temperature in Hangman Creek 03/12/2019
R 157 Collect data and maintain fixed PIT tag antennae arrays 03/12/2019
S 162 Analyze data generated from sampling salmonids in tributary habitats in upper Hangman watershed 05/01/2019
T 162 Analyze data generated for redband trout captured in migrant traps in Hangman Creek 05/01/2019
U 162 Analyze data logged at stationary PIT antenna arrays for Redband trout in Hangman Creek 05/01/2019
V 162 Analyze stream temperature data in Hangman Creek 05/01/2019
W 161 Summarize Redband trout population status and habitat in Hangman Creek using GIS 05/01/2019
X 191 Coordinate restoration and RM&E with Upper Columbia and Spokane Sub-basin partners 05/01/2019
Y 132 Submit Progress Report for the period (May 2017 - April 2019) 05/01/2019
Z 119 Manage and administer projects 05/01/2019
AA 185 Periodic Status Reports for BPA 05/01/2019