Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 84040: 1998-022-00 EXP PINE CREEK CONSERVATION AREA
Project Number:
Title:
Pine Creek Conservation Area
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau John Day 100.00%
Contract Number:
84040
Contract Title:
1998-022-00 EXP PINE CREEK CONSERVATION AREA
Contract Continuation:
Previous: Next:
81252: 1998-022-00 EXP PINE CREEK CONSERVATION AREA
  • 87094: 1998-022-00 EXP PINE CREEK CONSERVATION AREA
Contract Status:
Closed
Contract Description:
Contract for 2020 Operations & Management of the Pine Creek Conservation Area by the Confederated Tribes of Warm Springs:

The Conservation Area includes the Pine Creek Ranch and Wagner Ranch Acquisitions, and is managed by the Tribes in accordance with the Pine Creek Conservation Area Wildlife Habitat and Watershed Management Plan. This plan serves as the site-specific management plan called for in Section 3. (b) of the Memorandum of Agreement (MOA) between the Tribes and BPA. The MOA is the primary legal document guiding the Tribes' management of the property. This plan is supplemental to the MOA, and provides further definition to the Tribes commitment to manage the property for fish and wildlife habitat.

Pine Creek Conservation Area is intended, as a wildlife and watershed mitigation site, to partially offset wildlife habitat losses caused by John Day Dam on the Columbia River. Habitat management will, as specified in the MOA between BPA and the Tribes, to the extent possible, focus on strategies designed to achieve and maintain native habitat that is naturally self-sustaining.

In many cases, recovery of watershed functions or native plant communities may only occur over the course of several decades. Other changes, such as community dominance by invasive species, may be permanent without active intervention on the part of land managers. Future climate changes may also limit or prevent recovery to historic conditions.

Where possible, altered or damaged ecosystem functions will be restored through passive restoration techniques, such as the prevention of activities which degrade or prevent recovery. Passive restoration strategies will be paired with active interventions as needed, such as replacement of culverts creating fish passage barriers. It is hoped that these efforts will lead to conservation of biodiversity in the form of native fish, wildlife, and plant communities.

An additional goal for the project is to work in partnership with neighboring landowners, local, state and federal agencies, conservation organizations, and educational groups, and serve as an example of watershed recovery and wildlife habitat management in the lower John Day Basin. Successful monitoring of changes to vegetation, wildlife, fish use and distribution, and hydrology are critical to this effort.

Several specific management objectives are described in the approved Wildlife Habitat and Watershed Management Plan, and are to be addressed by this Statement of Work and its Work Elements. In most cases, WE's are ongoing activities developed in long term furtherance of the objectives. A set of administrative Work Elements within the scope of work will contribute to the achievement of all management plan objectives listed below.
Account Type(s):
Expense
Contract Start Date:
02/01/2020
Contract End Date:
01/31/2021
Current Contract Value:
$306,060
Expenditures:
$306,060

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Coordination with BPA Environmental Compliance Group Completed A: 165. Conservation Area Environmental Compliance for Ongoing O&M Activities 01/31/2021 12/31/2020
Administrative Documents Completed and Submitted to BPA B: 119. Prepare Administrative Documents and Submit to BPA 01/31/2021 12/31/2020
Maintain property C: 186. Maintain property facilities, roads and fences 01/31/2021 12/31/2020
Ranch Debris Removed D: 27. Remove Interior Wire Fences 10/26/2020 09/08/2020
Vegetation Maintained E: 198. Maintain Riparian Plantings and Control Weeds 11/16/2020 11/02/2020
Propagate Native Vegetation: Lowland Fields along Pine Creek F: 47. Continue Restoration of Lowland Fields along Pine Creek 01/31/2021 12/31/2020
Trespass Livestock Monitored and Removed G: 26. Monitor for Trespass Livestock and Coordinate Removal with Owners 01/31/2021 12/31/2020
Public Access Program Implemented H: 188. Manage Public Access and Provide Information 01/31/2021 12/31/2020
CTWS Represented in Community and Partnerships I: 99. Represent the CTWS 01/31/2021 09/08/2020
Land Exchange Implementation Actions Completed J: 172. Implement Land Exchange between Tribes and BLM (If needed) 01/31/2021 12/31/2020
Complete first draft K: 193. Begin re-writing management plan 01/29/2021 12/30/2020
Conduct Wildlife Inventories L: 115. Conduct Wildlife Inventories 01/31/2021 12/31/2020
Monitoring Data Collected and Managed M: 157. Collect 2020-2021 Monitoring Data 01/31/2021 12/31/2020
Progress Report Completed and Approved N: 132. Produce and Submit Progress Report for Prior Performance Period (Feb. 2019- Jan. 2020) 06/30/2020 05/29/2020

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 193 Produce Land Management Plan
  • 1 instance of WE 26 Investigate Trespass
  • 1 instance of WE 27 Remove Debris
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Conservation Area Environmental Compliance for Ongoing O&M Activities
B 119 Prepare Administrative Documents and Submit to BPA
C 186 Maintain property facilities, roads and fences 02/13/2020
D 27 Remove Interior Wire Fences 02/13/2020
E 198 Maintain Riparian Plantings and Control Weeds 10/10/2020
F 47 Continue Restoration of Lowland Fields along Pine Creek 10/08/2020
G 26 Monitor for Trespass Livestock and Coordinate Removal with Owners
H 188 Manage Public Access and Provide Information 02/13/2020
I 99 Represent the CTWS
J 172 Implement Land Exchange between Tribes and BLM (If needed)
K 193 Begin re-writing management plan
L 115 Conduct Wildlife Inventories 02/13/2020
M 157 Collect 2020-2021 Monitoring Data 02/13/2020
N 132 Produce and Submit Progress Report for Prior Performance Period (Feb. 2019- Jan. 2020)
O 185 Periodic Status Reports for BPA