Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 73982 REL 134: 1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT ENHANCEMENT
Project Number:
Title:
Walla Walla River Basin Fish Habitat Enhancement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Walla Walla 100.00%
Contract Number:
73982 REL 134
Contract Title:
1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT ENHANCEMENT
Contract Continuation:
Previous: Next:
73982 REL 102: 1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT ENHANCEMENT
  • 73982 REL 159: 1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT: PROTECT & RESTORE
Contract Status:
Closed
Contract Description:
The CTUIR Walla Walla River Basin Fish Habitat Enhancement Project, initiated in 1996, is an ongoing effort to monitor, protect, enhance, and restore the natural form and function of rivers, floodplains, and native fish habitat. Restoration project location and selection criteria is derived from various managerial guidance documents and based upon identification and addressing factors limiting salmonid production including the Middle Columbia River Steelhead Recovery Plan (NMFS 2009), Bull Trout Recovery Plan (USFWS 2015), Walla Walla Subbasin Plan (NPCC 2004), Umatilla River Vision (Jones et al. 2008), Lower Walla Walla River Geomorphic Assessment and Action Plan (CTUIR 2014), and the Lower Mill Creek Final Habitat and Passage Assessment and Strategic Action Plan (CTUIR 2017). The Project is responsible for improving physical habitat conditions for ESA-Listed salmonid species.  

Major tasks to be completed by the project in this funding cycle include:  

1) North Fork Touchet RM 2.0 - 3.3: Implement restoration actions along an approximately 1 mile reach of the river focusing on habitat complexity, floodplain reconnection, and post-construction riparian restoration.      

2) Walla Walla River Forks Confluence: Complete final designs and secure easements for priority reach established for ESA-Listed salmonid species. Project involves reactivating floodplain, improving passage and complexity, and restoring river into historic channel. Project will plan for construction in 2022.

3) Mill Creek Intake Dam Fishway: Complete modifications to the City of Walla Walla municipal water intake dam to bring the structure into compliance with established fish passage criteria.

4) South Fork Walla Walla River Adaptive Management: Complete limited adaptive management of previously completed habitat projects on the South Fork Walla Walla River to ensure continued function following major floods in February 2020.

5) Upper Walla Walla River Assessment and Action Plan: Complete inventory and assessment for the upper Walla Walla Basin used to identify and prioritize future projects.

6) Enhance riparian vegetative components at restoration project sites: Plant new vegetation and maintain previously planted areas.
Account Type(s):
Expense
Contract Start Date:
04/01/2021
Contract End Date:
03/31/2022
Current Contract Value:
$1,407,977
Expenditures:
$1,407,977

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Project administration activities managed effectively A: 119. Conduct all project management activities 03/31/2022 03/31/2022
Environmental compliance B: 165. Produce environmental compliance for on the ground work 03/31/2022 03/31/2022
Projects identified and prioritize; short and long term C: 114. Identify and select habitat projects that benefit salmonids 03/31/2022 03/31/2022
Provide technical support through interagency coordination and public forum D: 122. Provide technical support on related resource topics 03/31/2022 03/31/2022
Complete outreach and education activities E: 99. Public outreach and education 03/31/2022 03/31/2022
Maintained Vegetation F: 198. Maintain Vegetation at Past Projects 03/31/2022 03/31/2022
Photo point monitoring G: 186. Implementation Monitoring and Adaptive Management of Past Project Sites 03/31/2022 08/10/2021
Construction Management Complete H: 100. North Fork Touchet RM 2.0 - 3.3 - Construction Management 03/31/2022 12/31/2021
Restoration of the North Fork Touchet River RM 2 - 3.3 I: 29. North Fork Touchet RM 2.0 - 3.3 - Increase Complexity 12/31/2021 12/31/2021
Reconnect floodplain J: 180. North Fork Touchet RM 2.0 - 3.3 - Remove Berm and Excavate Floodplain 09/30/2021 08/13/2021
Vegetation Planted L: 47. North Fork Touchet RM 2.0 - 3.3 - Riparian Planting 03/31/2022 03/25/2022
Produce final design P: 175. Walla Walla River Forks Confluence - Produce Final Designs 03/31/2022 03/31/2022
Upload final design set Q: 175. South Fork Walla Walla River Adaptive Management 01/31/2022 03/31/2022
Complete NWPCC proposal and review process S: 141. Other Reports for BPA 12/31/2021 09/23/2021
Completed Annual Report T: 132. Annual Progress Report (4/1/20) to (3/31/21) 07/31/2021 08/03/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 115 Produce Inventory or Assessment
  • 2 instances of WE 175 Produce Design
  • 1 instance of WE 100 Construction Management
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 115 Produce Inventory or Assessment
  • 2 instances of WE 175 Produce Design
  • 1 instance of WE 100 Construction Management
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 115 Produce Inventory or Assessment
  • 2 instances of WE 175 Produce Design
  • 1 instance of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Conduct all project management activities
B 165 Produce environmental compliance for on the ground work
C 114 Identify and select habitat projects that benefit salmonids
D 122 Provide technical support on related resource topics
E 99 Public outreach and education
F 198 Maintain Vegetation at Past Projects
G 186 Implementation Monitoring and Adaptive Management of Past Project Sites
H 100 North Fork Touchet RM 2.0 - 3.3 - Construction Management
I 29 North Fork Touchet RM 2.0 - 3.3 - Increase Complexity 06/30/2021
J 180 North Fork Touchet RM 2.0 - 3.3 - Remove Berm and Excavate Floodplain 06/30/2021
K 30 [CCR-46254] CANCELED: North Fork Touchet RM 2.0 - 3.3 - Create Side Channel 06/30/2021
L 47 North Fork Touchet RM 2.0 - 3.3 - Riparian Planting 06/30/2021
M 184 [CCR-46254] CANCELED: Mill Creek Intake Dam Fishway Improvement 09/10/2021
N 29 [CCR-46254] CANCELED: South Fork Walla Walla River Adaptive Management
O 115 Develop Upper Walla Walla River Assessment & Action Plan
P 175 Walla Walla River Forks Confluence - Produce Final Designs 09/10/2021
Q 175 South Fork Walla Walla River Adaptive Management 09/10/2021
R 115 South Fork Touchet River Habitat Inventory
S 141 Other Reports for BPA
T 132 Annual Progress Report (4/1/20) to (3/31/21)
U 185 Periodic Status Reports for BPA