Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 56662 REL 226: 2009-003-00 EXP UPPER COLUMBIA HABITAT RESTORATION
Project Number:
Title:
Upper Columbia Habitat Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 20.00%
Methow 40.00%
Wenatchee 40.00%
Contract Number:
56662 REL 226
Contract Title:
2009-003-00 EXP UPPER COLUMBIA HABITAT RESTORATION
Contract Continuation:
Previous: Next:
56662 REL 200: 2009-003-00 EXP UPPER COLUMBIA HABITAT RESTORATION
  • 89361: 2009-003-00 EXP UPPER COLUMBIA HABITAT RESTORATION
Contract Status:
Issued
Contract Description:
This contract will fund the Yakama Nation Fisheries Upper Columbia Habitat Restoration Project to seek, design and implement fish habitat restoration projects throughout the Methow, Entiat, and Wenatchee subbasins for the Calendar Year 2021 performance period.  Administrative tasks related to this SOW, such as reporting and inventory management, are provided under BPA Contract 56662 REL 215.

This contract details salmon habitat restoration work being designed or implemented in the Upper Columbia Spring Chinook Salmon and Steelhead recovery area under the guidance of the Upper Columbia Spring Chinook Salmon and Steelhead Recovery Plan and the 2017 Biological Strategy Update.  Yakama Nation Fisheries uses project and ecological concern prioritizations contained within the 2017 Biological Strategy Update and within Habitat and Geomorphic Reach Assessments reviewed by the Upper Columbia Regional Technical Team to determine which project action types and locations to pursue.  At the project level, Yakama Nation Fisheries subcontracts with technical consultants to develop salmon habitat restoration actions that best address prioritized ecological concerns limiting salmon and steelhead productivity and abundance.  

Work Element actions in 2021 include:

RESTORATION ACTIONS (2021 CONSTRUCTION ACTIONS)

Methow Subbasin:
Lower Chewuch Assessment Unit - Eight Mile Creek Barrier Removal  and Chewuch RM 4.6 Side Channel Restoration
Middle Methow Assessment Unit - M2 Alder Creek Floodplain Side Channel Restoration and M2 Golden Doe Large Wood Restoration
Lower Twisp Assessment Unit - Twisp River Habitat Wood Harvest

Wenatchee Subbasin:
Upper Wenatchee Assessment Unit - Skinney Creek Channel Reconstruction and Nason Confluence Side Channel Restoration

Entiat Subbasin:
Middle Entiat Assessment Unit - Entiat Upper Stillwaters Upper Burns Restoration

DESIGN PROJECTS (2021 ENGINEERING AND DESIGN PROJECTS)

Methow Subbasin:
Lower Twisp Assessment Unit - Upper Twisp River and Tributaries Project (USFS Lands – Little Bridge Creek) and Twisp Horseshoe Phase 2 Large Wood Structures and Newby Narrows Phase 2
Upper Twisp Assessment Unit - Upper Twisp River and Tributaries Project (USFS Lands – War and Mystery) and Scaffold Camp Side Channel
Upper Methow Assessment Unit - Fawn Creek Large Wood Restoration and Methow Basin EWD Instream Flow Project
Upper Chewuch Assessment Unit - Chewuch Old Yeller (USFS Lands)

Wenatchee Subbasin:
Nason Creek Assessment Unit - Nason Creek N1 DOT Project and Upper Nason Creek Project (USFS Lands)
Upper Wenatchee Assessment Unit - Chiwawa Fan Side Channel Restoration (USFS Lands) and Chiwawa Outlet Restoration
Lower Wenatchee Assessment Unit - Lower Wenatchee River Reach 3 Restoration

Entiat Subbasin:
Upper-Middle Entiat Assessment Unit - Entiat Stillwaters Silver Falls and Fox Creek Restoration
Mad River Assessment Unit - Mad River (USFS) Projects

For all three subbasins, this contract also details a scope of work for continuing to partner with the United States Forest Service to implement salmon recovery actions on USFS managed lands.  Through a cooperative agreement with the USFS, the Yakama Nation provides some cost reimbursement coverage to the USFS for federal staff costs on conducting NEPA and environmental compliance review on Yakama Nation sponsored projects.

Future salmon habitat restoration design and implementation work is contemplated to be added to this contract under upcoming Contract Change Requests.  
Account Type(s):
Expense
Contract Start Date:
01/01/2021
Contract End Date:
12/31/2021
Current Contract Value:
$4,507,205
Expenditures:
$2,659,862

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Shannon Adams Yakama Confederated Tribes No Administrative Contact adas@yakamafish-nsn.gov (509) 945-0754
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Victoria Bohlen Bonneville Power Administration Yes COR vlbohlen@bpa.gov (503) 230-3506
Jason Breidert Yakama Confederated Tribes Yes Technical Contact brej@yakamafish-nsn.gov (509) 860-5351
Chris Butler Yakama Confederated Tribes Yes Technical Contact butlerc@yakamafish-nsn.gov (509) 449-8215
Christopher Clemons Yakama Confederated Tribes Yes Technical Contact clec@yakamafish-nsn.gov (509) 881-5746
Joseph Connor Bonneville Power Administration Yes F&W Approver jwconnor@bpa.gov (503) 230-3172
Annet Dillman Yakama Confederated Tribes No Administrative Contact dila@yakamafish-nsn.gov (509) 865-2255
Minda Donnelly Department of Energy - IGE No Interested Party minda.donnelly@doe.gov (702) 295-0874
Madeleine Eckmann Yakama Confederated Tribes Yes Technical Contact eckm@yakamafish-nsn.gov (509) 449-2091
Tamera Hoptowit Yakama Confederated Tribes No Administrative Contact Hopta@yakamafish-nsn.gov (509) 865-5121x6354
Tana Hoptowit Yakama Confederated Tribes Yes Administrative Contact hopt@yakamafish-nsn.gov (509) 865-5121x6318
Jarred Johnson Yakama Confederated Tribes Yes Technical Contact johj@yakamafish-nsn.gov (509) 881-1462
Crystal Miller Department of Energy - IGE No Interested Party crystal.miller@doe.gov (702) 295-0779
Brandon Rogers Yakama Confederated Tribes Yes Supervisor rogb@yakamafish-nsn.gov (509) 949-4109
Jared Sanchey Yakama Confederated Tribes No Interested Party jared_sanchey@yakama.com (509) 865-5121
Hans Smith Yakama Confederated Tribes Yes Contract Manager h.smith@methownet.com (509) 449-2750
Emily Wiegert Department of Energy - IGE No Interested Party emily.wiegert@doe.gov (123) 456-7890
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448
Jae Woo Department of Energy - IGE No Interested Party jae.woo@doe.gov (702) 295-0874


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
All administrative tasks fulfilled with timely quality products B: 119. Perform project management and administrative duties 12/31/2021 12/31/2021
USFS Environmental Compliance on Yakama Nation Fisheries Projects (BPA's EC covered in REL 215) D: 165. FY 21 USFS NEPA 2017-164 (BPA's EC covered in REL 215) 12/31/2021 12/31/2021
Permit and Construction Level Restoration Plans for the Upper Twisp Project Area E: 175. Upper Twisp River and Tributaries Project Design (USFS Projects) 2016-162 12/31/2021
Finalized Restoration Plan for Twisp Horseshoe USFS Lands F: 175. Twisp Horseshoe Phase 2 (USFS) Restoration Engineering 2010-39 12/31/2021
Permit Level and Final Designs and Report for the Scaffold Camp Project Area G: 175. Scaffold Camp Design 2015-146 12/31/2021
Conceptual Designs and Report for the Newby Narrows Project Area H: 175. Newby Narrows Phase 2 Designs 2015-153 12/31/2021 12/31/2021
Finalize Restoration Plan for the Fawn Creek Project Area I: 175. Fawn Creek Project - Design 2015-147 12/31/2021
Conceptual Designs and Report for the Old Yeller Project Area of the Chewuch River J: 175. Chewuch Old Yeller (USFS) Concpetual Designs 2019-208 12/31/2021 12/31/2021
Confidential Water Rights Evaluation K: 154. Methow Basin EWD Instream Flow Project - Water Rights Assessment 2015-152 12/31/2021
Alternative Water Delivery Feasibility Assessment L: 175. Methow Basin EWD Instream Flow Project - Eng. Feasibility Assessment 2015-152 12/31/2021
Nason Creek N1 DOT Permit Level Designs N: 175. Nason Creek N1 DOT Design 2018-198 12/31/2021
Finalize Conceptual and Permitting Designs and Report for the Upper Nason Creek Project Area O: 175. Upper Nason Creek Design 2020-207 12/31/2021 12/31/2021
Chiwawa Fan Finalized Restoration Plan P: 175. Chiwawa Fan - Design 2016-165 12/31/2021
Permit Level Restoration Plan for the Chiwawa River Outlet Project Area Q: 175. Chiwawa Outlet Design 2019-205 12/31/2021
Lower Wenatchee Reach 3 Concept Level Restoration Plan and Permitting Plan Sets R: 175. Lower Wenatchee River Reach 3 Design 2017-186 12/31/2021
Permit and Construction Level Restoration Plans for the Silver Falls and Fox Creek Sites S: 175. Entiat Silver Falls and Fox Creek Restoration Design 2019-210 12/31/2021 12/31/2021
Conceptual Designs and Report for the Mad River (USFS) Project Area T: 175. Mad River (USFS) Conceptual Design 2017-172 12/31/2021
Construction Management Complete W: 100. Chewuch RM 4.6 Oversight 2017-176 12/31/2021 12/31/2021
Completed channel construction X: 30. Chewuch RM 4.6 Construction 2017-176 12/31/2021 12/31/2021
Construction Management Complete Y: 100. M2 Alder Creek Floodplain Design and Oversight (w/Golden Doe) 2017-191 12/31/2021 12/30/2021
Completed channel construction Z: 30. M2 Alder Creek Floodplain Construction 2017-191 12/31/2021
Completed Wood Structure Installations AA: 29. M2 Golden Doe Mainstem Wood Structures 2017-191 12/31/2021 12/30/2021
Construction Management Complete AC: 100. Skinney Creek Construction Oversight 2015-144 12/31/2021 12/31/2021
Completed channel construction AD: 30. Skinney Creek Construction (Channel Reconstruction) 2015-144 12/31/2021 12/31/2021
Completed Channel construction AE: 29. Skinney Creek Construction (Large Wood Restoration) 2015-144 12/31/2021 12/31/2021
Construction Management Complete AF: 100. Nason Confluence - Construction Management 2013-105 12/31/2021 12/31/2021
Completed channel construction AG: 30. Nason Confluence Construction 2013-105 12/31/2021 12/31/2021
Construction Management Complete AH: 100. Entiat Upper Stillwaters USFS Construction Management 2017-167 12/31/2021 12/31/2021
Completed channel construction AI: 30. Entiat Upper Stillwaters USFS Construction 2017-167 12/31/2021 08/06/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 3 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 5 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 14 instances of WE 175 Produce Design
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
  • 6 instances of WE 100 Construction Management
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 3 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 5 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 13 instances of WE 175 Produce Design
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
  • 6 instances of WE 100 Construction Management
Trout, Bull (S. confluentus) (Threatened)
  • 2 instances of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 119 Perform project management and administrative duties
C 132 (No annual report required for this contract)
D 165 FY 21 USFS NEPA 2017-164 (BPA's EC covered in REL 215)
E 175 Upper Twisp River and Tributaries Project Design (USFS Projects) 2016-162 10/20/2020
F 175 Twisp Horseshoe Phase 2 (USFS) Restoration Engineering 2010-39 10/20/2020
G 175 Scaffold Camp Design 2015-146 10/20/2020
H 175 Newby Narrows Phase 2 Designs 2015-153 10/20/2020
I 175 Fawn Creek Project - Design 2015-147 10/20/2020
J 175 Chewuch Old Yeller (USFS) Concpetual Designs 2019-208 10/20/2020
K 154 Methow Basin EWD Instream Flow Project - Water Rights Assessment 2015-152
L 175 Methow Basin EWD Instream Flow Project - Eng. Feasibility Assessment 2015-152 06/07/2021
M 172 Western Rivers Methow Acquisition Support 2018-200
N 175 Nason Creek N1 DOT Design 2018-198 10/20/2020
O 175 Upper Nason Creek Design 2020-207 10/20/2020
P 175 Chiwawa Fan - Design 2016-165 10/20/2020
Q 175 Chiwawa Outlet Design 2019-205 10/20/2020
R 175 Lower Wenatchee River Reach 3 Design 2017-186 10/20/2020
S 175 Entiat Silver Falls and Fox Creek Restoration Design 2019-210 10/20/2020
T 175 Mad River (USFS) Conceptual Design 2017-172 06/07/2021
U 100 Eight Mile Barrier Removal Oversight 2015-141
V 85 Eight Mile Barrier Removal 2015-141
W 100 Chewuch RM 4.6 Oversight 2017-176
X 30 Chewuch RM 4.6 Construction 2017-176 06/01/2021
Y 100 M2 Alder Creek Floodplain Design and Oversight (w/Golden Doe) 2017-191
Z 30 M2 Alder Creek Floodplain Construction 2017-191 05/04/2021
AA 29 M2 Golden Doe Mainstem Wood Structures 2017-191 04/28/2021
AB 29 Twisp River Wood Harvest 2016-162
AC 100 Skinney Creek Construction Oversight 2015-144
AD 30 Skinney Creek Construction (Channel Reconstruction) 2015-144 06/08/2021
AE 29 Skinney Creek Construction (Large Wood Restoration) 2015-144 06/08/2021
AF 100 Nason Confluence - Construction Management 2013-105
AG 30 Nason Confluence Construction 2013-105 06/03/2021
AH 100 Entiat Upper Stillwaters USFS Construction Management 2017-167
AI 30 Entiat Upper Stillwaters USFS Construction 2017-167 06/07/2021