Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 83639 REL 20: 1983-319-00 EXP NEW MARKING & MONITORING TECHNOLOGIES
Project Number:
Title:
New Marking and Monitoring Technologies
Stage:
Implementation
Area:
Province Subbasin %
Basinwide - 100.00%
Contract Number:
83639 REL 20
Contract Title:
1983-319-00 EXP NEW MARKING & MONITORING TECHNOLOGIES
Contract Continuation:
Previous: Next:
83639 REL 11: 1983-319-00 EXP NEW MARKING & MONITORING TECHNOLOGIES
  • 83639 REL 37: 1983-319-00 EXP NEW MARKING & MONITORING TECHNOLOGIES
Contract Status:
Closed
Contract Description:
The project goal is to expand fish-tracking capabilities by developing new technologies that monitor fish at critical life stages and locations. This goal covers developing PIT tag detection systems that collect data on migrating juvenile and adult salmonids through mainstem dams, including surface bypass systems, and all life-stages transiting small streams. These detection sites are utilized by the RME program to assess effectiveness of management actions for recovery of ESA-listed salmonids.
Account Type(s):
Expense
Contract Start Date:
04/01/2021
Contract End Date:
03/31/2022
Current Contract Value:
$867,216
Expenditures:
$867,216

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Order
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Funding Package - Submit draft to COTR B: 119. Administration tasks for this project 01/21/2022 01/21/2022
Environmental compliance documentation C: 165. Environmental compliance review for PIT Tag and in-stream systems 03/31/2022 03/31/2022
Evaluate installation of spillway detection system at Lower Granite Dam. D: 156. Spillway PIT-tag system - evaluation, fine tune equipment 03/31/2022 03/31/2022
Data will be collected from research and development conducted on interrogation systems E: 156. Continue development of interrogation systems 03/31/2022 03/31/2022
Submit BiOp RPA Report in cbfish.org F: 202. BiOp RPA Report for CY 2020 03/15/2022 03/15/2022
Completed Annual Report G: 132. Progress Report for the period (Jan 1, 2021) to (Dec 31, 2021) 03/31/2022 03/31/2022

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 119 Administration tasks for this project
C 165 Environmental compliance review for PIT Tag and in-stream systems
D 156 Spillway PIT-tag system - evaluation, fine tune equipment 07/20/2021
E 156 Continue development of interrogation systems 07/20/2021
F 202 BiOp RPA Report for CY 2020
G 132 Progress Report for the period (Jan 1, 2021) to (Dec 31, 2021)