Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 79905 REL 11: 1992-026-01 EXP WALLOWA FISH PASSAGE GREEN VALLEY RANCH DESIGN
Project Number:
Title:
Grande Ronde Model Watershed
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Blue Mountain Grande Ronde 100.00%
Contract Number:
79905 REL 11
Contract Title:
1992-026-01 EXP WALLOWA FISH PASSAGE GREEN VALLEY RANCH DESIGN
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
This contract is for the design of the Wallowa River-Green Valley Ranch Diversion Project. Currently the diversion structure can be a partial barrier and may become a full barrier as a result of natural channel processes. Currently all life stages of Snake River Spring Chinook, Snake River Summer Steelhead, and Bull Trout occupy this area. All of which are ESA listed species. In the future, Sockeye may be reintroduced. This technical assistance contract will be used to hire an engineering firm to produce designs, specifications, permitting documentation, and construction bidding documentation for the replacement of the existing structure. With this task complete, the sponsor will seek implementation funding with plans to hire a contractor for implementation in 2022.
Account Type(s):
Expense
Contract Start Date:
04/01/2021
Contract End Date:
03/31/2022
Current Contract Value:
$63,150
Expenditures:
$63,150

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Grant
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
EC completed related to Wallowa River-Green Valley Diversion design. A: 165. Environmental Compliance for Wallowa River Fish Passage Green Valley Ranch Design 03/31/2022
Implementation ready design for the Wallowa River-Green Valley Ranch Diversion Project B: 175. Produce Implementation Ready Designs for the Green Valley Ranch Diversion Improvement Project 03/31/2022
Effective implementation management and timely contract administration C: 119. Project/Contract Administration 03/31/2022 03/31/2022

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 175 Produce Design
Sockeye (O. nerka) - Other
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance for Wallowa River Fish Passage Green Valley Ranch Design
B 175 Produce Implementation Ready Designs for the Green Valley Ranch Diversion Improvement Project
C 119 Project/Contract Administration
D 185 Quarterly Status Reports
E 132 N/A