Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 74017 REL 85: 2002-068-00 EXP HABITAT RESTORATION RM&E
Project Number:
Title:
Evaluate Stream Habitat- Nez Perce Tribe Watershed Monitoring and Evaluation (M&E) Plan
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
74017 REL 85
Contract Title:
2002-068-00 EXP HABITAT RESTORATION RM&E
Contract Continuation:
Previous: Next:
74017 REL 66: 2002-068-00 EXP HABITAT RESTORATION RM&E
Contract Status:
Closed
Contract Description:
Contract Summary

The objective of this contract is to complete project-level habitat monitoring and evaluation activities in support of, and in collaboration with, a Programmatic Approach for Action Effectiveness Monitoring (AEM) developed by the Northwest Fisheries Science Center and the Bonneville Power Administration. Specifically, a multiple before-after control-impact (MBACI) experimental design will be utilized to monitor and evaluate the effectiveness of partial passage barrier projects implemented in Northeast Oregon and North-Central Idaho. Collaboration and support will be extended to AEM coordinators at Cramer Fish Sciences to analyze and interpret the data, as well as for the completion of associated reports for the Programmatic AEM MBACI activities. As new protocols for AEM monitoring of floodplain projects are currently under development by Cramer Fish Sciences, additional habitat monitoring that is not currently associated with the AEM program will be conducted under this year’s contract.

CY21 Implementation Summary

The habitat restoration actions identified for monitoring and evaluation under this contract include:

• Lostine River - Sheep Ridge Diversion partial barrier project
• Lower Grande Ronde Subbasin - Buford Creek Culvert partial barrier project
• East Fork of South Fork Salmon River - Cox Creek Culvert partial barrier project
• South Fork Clearwater River floodplain and side-channel reconnection project (proposed)
• Red River large woody debris project (proposed)
• Newsome Creek large woody debris project (proposed)
• American River floodplain reconnection project (tentative)
• Lochsa River Watershed restoration project (spatially distributed eDNA surveys)
• Lolo Creek Watershed restoration project (spatially distributed electrofishing surveys)
Account Type(s):
Expense
Contract Start Date:
04/01/2021
Contract End Date:
03/31/2022
Current Contract Value:
$207,638
Expenditures:
$207,638

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Clint Chandler Nez Perce Tribe Yes Contract Manager clintc@nezperce.org (208) 621-3550
Lisa Dexter Bonneville Power Administration No Administrative Contact lldexter@bpa.gov (503) 230-3893
Arleen Henry Nez Perce Tribe No Interested Party arleenh@nezperce.org (208) 621-3833
David Kaplowe Bonneville Power Administration Yes F&W Approver djkaplowe@bpa.gov (503) 230-5365
Matthew Schwartz Bonneville Power Administration Yes COR mdschwartz@bpa.gov (503) 230-4225
Emmit Taylor, Jr. Nez Perce Tribe No Supervisor emmitt@nezperce.org (208) 621-3544
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Environmental compliance documentation submitted to BPA A: 165. Provide environmental compliance information to BPA 03/31/2022 03/29/2022
AEM MBACI Partial Barrier monitoring data B: 157. Partial Barrier data collection 09/10/2021 08/24/2021
Floodplain reconnection monitoring data C: 157. Floodplain Reconnection data collection 03/31/2022 09/02/2021
Produce accessible, error-checked datasets D: 157. Backpack electrofishing data collection 03/31/2022 03/29/2022
Environmental DNA field samples E: 157. eDNA data collection 03/31/2022 06/16/2021
FY 2022 Contract Package, FY 2021 Accrual Estimate, FY 2021 Cost Share F: 119. Management, Coordination, and Communication 11/30/2021 12/15/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Provide environmental compliance information to BPA
B 157 Partial Barrier data collection 04/01/2021
C 157 Floodplain Reconnection data collection 04/01/2021
D 157 Backpack electrofishing data collection 04/01/2021
E 157 eDNA data collection 04/01/2021
F 119 Management, Coordination, and Communication 04/01/2021
G 132 Collaborate to Produce Annual AEM Program Report
H 185 Periodic Status Reports for BPA