Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 88637: 2010-001-00 EXP MERRITT OXBOW DESIGN
Project Number:
Title:
Upper Columbia Programmatic Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 25.00%
Methow 25.00%
Okanogan 25.00%
Wenatchee 25.00%
Contract Number:
88637
Contract Title:
2010-001-00 EXP MERRITT OXBOW DESIGN
Contract Continuation:
Previous: Next:
85994: 2010-001-00 EXP MERRITT OXBOW DESIGN
Contract Status:
Closed
Contract Description:
Justification for this Contract Change Request 47346 - Cost increase to cover implementation

The expected cost of the project, based on the engineer's estimate, increased significantly since the time of contract development. The design engineer, RioASE, spent significant time engineering the details of the constructed riffle in the summer of 2021 after the initial contract was developed. Rio determined that a majority of the riffle matrix material would need to be bigger than the material predicted to be excavated onsite and would need to be imported. The import of material is in part responsible for the cost increase. The 80% design also included an additional constructed riffle in the side channel, which was note included in designs during the initial contract development. Additionally, the amount of material that need to be excavated increased significantly, from about 3,100CY to about 4,900CY to accommodate the over excavation necessary for the constructed riffles. It was determined that about 3,500CY of this material would need to be hauled offsite, adding about $56,000 to the cost estimate. Finally, the cost of construction labor, materials (especially large wood), and diesel, all significantly increased since the initial contract development. All of this led to an engineer's cost estimate of $580,000 based on the final design.

In the spring of 2022 Cascade Fisheries conducted a formal RFP process to procure bids to complete the project. Three bids were received on April 14. The low bid was $525,000, about $55,000 below the engineer's estimate. This cost increase will cover the amount needed to award the contract to the low bidder, and implement the project in the summer of 2022.

This is a one and done agreement.  That is, after the work is completed, there will be no contract renewal.

Under this contract Cascade Columbia Fisheries Enhancement Group (CCFEG) d.b.a Cascade Fisheries (CF) will complete a final design collaboratively with BPA and project stakeholders, complete environmental compliance, and implement the project.  An 80% design was developed for this project in FY 21 under funding agreements from BPA ( BPA agreement #: 85994) and the SRFB agreement.  This restoration project will by implemented in FY22 to address high priority ecological concerns in Nason Creek by establishing a perennial side channel with connection to off channel wetland habitat, installing wood structures to increase instream complexity and habitat, and establishing riparian vegetation in the floodplain and newly created side channel.  The project is located on Chelan-Douglas Land Trust (CDLT) and US Forest Service (USFS)  property at RM 10.8 - 11 on Nason Creek.  

The project will benefit ESA listed spring Chinook salmon, steelhead, and bull trout in Nason Creek.  The main deliverables of this contract include development of collaborative, progressively advanced, designs that incorporate stakeholders’ input, leading to a final design, the submittal and securing of environmental permits, and project implementation.  This project was approved for funding through Bonneville Power Administration (BPA)/Upper Columbia Salmon Recovery Board (UCSRB) FY2020 Targeted Solicitation Notice and was reviewed and ranked by the Regional Technical Team (RTT).  The RTT is a team of technical experts familiar with the priority areas and limiting factors, and identify projects that will best contribute to the recovery of salmonids and other species of concern in the Upper Columbia.

The goal of this project is to improve abundance, productivity and spatial structure for ESA-listed species by addressing the highest priority ecological concerns in Nason Creek, which is the highest priority assessment unit for restoration in the Wenatchee Basin.  The ecological concerns that this project will address in priority order are: 1) Peripheral and Transitional Habitat (Side Channel and Wetland Connections) 2) Channel Structure and Form (Bed and Channel Form) 3) Riparian Condition 4) Channel Structure and Form (Instream Structural Complexity).  Implementation of this project will address these ecological concerns by: excavating 836 feet of side channel to create a perennially flowing connection to the mainstem, connecting the new side channel to relic oxbows and “First Bend” side channel to create a total of over 1700 linear feet of perennial side channel, providing a total of 0.43 acres of off channel habitat at low flow and 2.67 acres off channel habitat at the 1.25 year event, install approximately 24 wood structures to improve instream habitat complexity and cover, densely planting approximately 3750 willow, cottonwood and dogwood live stakes along new side channel, and helping ensure success by controlling invasive weeds at the project site.

Cascade Fisheries will be responsible for managing the project.  BPA, CDLT, USFS and other project stakeholders will provide design review.  NEPA, ESA, and cultural consultation activities will be led by BPA as the lead action agency.

PROJECT PARTNER COLLABORATION

The Upper Columbia Salmon Recovery Board (UCSRB) is co-sponsor to Upper Columbia Programmatic Habitat Project.  As such they are a key partner to BPA and within the UC region, a local first point of contact for general Programmatic inquiries and coordination.  It is possible from time to time that the UCSRB may seek general project information and updates from CF to preform and fulfill their necessary role and obligations under the Northwest Power and Conservation Council approved Programmatic with BPA.  CF has agreed to coordinate with UCSRB and accommodate any such requests.  As examples, UCSRB may request the following:

Participation in periodic BPA-UCSRB-Sponsor check-in calls, if/as needed
Information about partner contributions for reporting cost-share
Copies of presentations about the BPA-UCSRB Programmatic project  

The contractor CCFEG, its designated agents, sub-consultants and project stakeholders will be available, responsive and will collaboratively address contract related issues during the term of the contract.  Contract issues include but are not limited to technical, policy, regulatory, project management and associated elements related to the project.  Successful execution of this contract is contingent on alignment of the preceding contract issues with the BFAI or BPI and BPA contracting processes, project management plans, design review protocols (including but not limited to BPA engineering design review, Technical and Design Team guidance, review, input, comments, integration, stakeholder congruence with proposed actions and decisions rendered by 1) the project executive team (BPA, CCFEG).  Arbitration and dispute resolution will occur relative to the following two tier escalation ladder: 1) conference with the project Executive Team and 2) Direct consultation between program managers.  

CCFEG Contract Manager and CCFEG's design consultant (a mutually agreed to and selected subcontractor) will all cooperate, coordinate, collaborate, and maintain effective communication with the BPA PM/COR, EC Lead, and Hydraulic Engineer(s) during the entire length of this contract with regards to project design.  CCFEG, USFS and its subcontractors will address BPA comments and concerns, and the three entities will arrive at a mutually beneficial consensus.  CCFEG contract manager will upload all of the subcontracts being executed under this contract to cbfish.org.  
Account Type(s):
Expense
Contract Start Date:
09/28/2021
Contract End Date:
09/27/2022
Current Contract Value:
$345,236
Expenditures:
$345,236

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Environmental Compliance Attained A: 165. Complete work for Required Permits, Authorizations, and Documentation for the Merritt Restoration Project 05/30/2022 06/30/2022
Produce Final Designs B: 175. CF & BPA Collaboratively Develop Final Designs 04/30/2022 04/30/2022
Coordinate w/UC Wenatchee stakeholders C: 191. CF will Coordinate with Stakeholders and BPA 09/27/2022 09/26/2022
Pre-construction weed control completed D: 199. Pre-construction noxious weed control within project footprint 06/15/2022 06/15/2022
Install 23 Large Wood Structures and 1 constructed riffle E: 29. Wood habitat structures and constructed riffle 08/15/2022 09/26/2022
Completed channel construction F: 30. New side channel 08/15/2022 09/26/2022
Effective implementation management and timely contract administration I: 119. Manage BPA Contracting Requirements 09/27/2022 09/26/2022

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Complete work for Required Permits, Authorizations, and Documentation for the Merritt Restoration Project
B 175 CF & BPA Collaboratively Develop Final Designs
C 191 CF will Coordinate with Stakeholders and BPA
D 199 Pre-construction noxious weed control within project footprint
E 29 Wood habitat structures and constructed riffle
F 30 New side channel
G 185 Periodic Status Reports for BPA
H 132 No Report to BPA Required Per COR --Summary to UCSRB
I 119 Manage BPA Contracting Requirements