Contract 74313 REL 104: 1988-053-08 EXP HRPP ODFW HATCHERY ROUND BUTTE
Project Number:
Title:
Hood River Production Operations and Maintenance (O&M) and Powerdale
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Hood 100.00%
Contract Number:
74313 REL 104
Contract Title:
1988-053-08 EXP HRPP ODFW HATCHERY ROUND BUTTE
Contract Continuation:
Previous: Next:
74313 REL 86: 1988-053-08 EXP HRPP ODFW HATCHERY ROUND BUTTE
  • 84041 REL 8: 1988-053-08 EXP HRPP ODFW HATCHERY ROUND BUTTE
Contract Status:
Issued
Contract Description:
October 1 to September 30
Project 1988-053-08
Hood River Production Program - Hatchery O&M
(Round Butte Hatchery - Pelton Ladder Extended Rearing Facilities)

Program Objectives:  ODFW, working in cooperation with PGE and the CTWSRO, at the PGE/CTWRO-owned Round Butte Hatchery and Pelton Ladder trap and rearing cell facilities, will rear up to 75,000, age 1 plus, Hood River and Deschutes River spring Chinook smolts and transfer to the Hood River Basin for release.  One complete hatchery cycle (from trapping of broodstock to release of smolts from that broodstock) is about 18 months long.  ODFW is responsible for all rearing while PGE does required maintenance at both Round Butte Hatchery and Pelton Ladder.

Work Plan Objectives:
The plan objectives are to initiate and complete the annual extended rearing activities in Pelton Ladder, identify and complete all O&M activities, continue routine hatchery operations (broodstock selection, spawning, incubation, rearing and disease control of spring Chinook fingerlings), initiate necessary facility upgrades and continue routine ancillary actions.  Work items are presented below.

Deliverables
- Produce and deliver ~75,000 spring Chinook smolts to the Moving Falls Fish Facility on the West Fork of the Hood River.

- Receive ~ 115,000 spring Chinook eyed eggs from Parkdale Hatchery (Hood River), rear ~82,000 fingerlings.  Some eggs may come from fish trapped at the Pelton Trap on the Deschutes if Hood River Program does not meet egg take goals.

- Reports need to be sent, either via e-mail or hard copy, whenever problems are encountered during the contract period (i.e.disease outbreaks or unexpected mortalities associated with hatchery fish).

- A brief summary report is due at the end of the contract period reporting the number of fish transferred to Pelton Ladder cells, the number of fish transferred to the Hood River, and the number of fish released into the Deschutes River.  Data from this report will be used by ODFW in the annual report for the HRPP M&E project (1988-053-04)
Account Type(s):
Expense
Contract Start Date:
10/01/2021
Contract End Date:
09/30/2022
Current Contract Value:
$159,174
Expenditures:
$159,173

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Documentation of Environmental Compliance Complete B: 165. NEPA and ESA compliance for project work 09/30/2022 09/01/2022
Project administration requirements completed C: 119. Manage and Administer Project 09/30/2022 08/08/2022
Rearing of spring Chinook fingerlings to smolts D: 176. Fish Management for brood year 2020 09/30/2022 03/02/2022
Complete transport of BY 2020 smolts to Hood River Basin E: 66. Transport BY 2020 smolts to Moving Falls 03/15/2022 03/02/2022
Progress toward producing ~105,000 spring Chinook smolts F: 176. Fish Management for brood year 2021 09/30/2022 09/26/2022
Progress toward 105,000 smolts G: 176. Fish Management for brood year 2022 09/30/2022 09/26/2022
Submit yearly updated maintenance plan to BPA H: 174. Produce hatchery maintenance plan and broodstock collection plan 08/31/2022 08/08/2022
Fish health monitoring, sampling, and treatment I: 60. Maintain Fish Health 09/30/2022 09/26/2022
Fully functional fish hatchery to produce quality fish J: 61. Facilities O&M 09/30/2022 09/26/2022
~115,000 juveniles fin clipped K: 158. Fin clip all BY2021 juveniles 06/15/2022 05/26/2022

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened)
  • 3 instances of WE 176 Produce Hatchery Fish
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 60 Maintain Fish Health
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 158 Mark/Tag Animals

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 165 NEPA and ESA compliance for project work
C 119 Manage and Administer Project
D 176 Fish Management for brood year 2020 09/20/2021
E 66 Transport BY 2020 smolts to Moving Falls 09/20/2021
F 176 Fish Management for brood year 2021 09/20/2021
G 176 Fish Management for brood year 2022 09/20/2021
H 174 Produce hatchery maintenance plan and broodstock collection plan
I 60 Maintain Fish Health 09/20/2021
J 61 Facilities O&M 09/20/2021
K 158 Fin clip all BY2021 juveniles 09/20/2021
L 132 Reporting data transferred to Project 1988-053-08