Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 76913 REL 34: 2010-072-00 EXP LEMHI RIVER RESTORATION
Project Number:
Title:
Upper Salmon Basin Habitat Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
76913 REL 34
Contract Title:
2010-072-00 EXP LEMHI RIVER RESTORATION
Contract Continuation:
Previous: Next:
76913 REL 26: 2010-072-00 EXP LEMHI RIVER RESTORATION
  • 84063 REL 3: 2010-072-00 EXP UPPER SALMON BASIN RESTORATION
Contract Status:
Closed
Contract Description:
The Lemhi River Restoration Project (2010-072-00) seeks to implement habitat actions to protect in-stream and riparian habitat, improve stream flow in the Lemhi River, and assist in reconnecting tributary streams to the Lemhi River to benefit all life stages of Snake River spring/summer-run Chinook and Snake River steelhead.

This contract covers 2022-2023 actions by Idaho Department of Fish and Game (IDFG), Lemhi Soil and Water Conservation District (Lemhi SWCD), Lemhi Regional Land Trust (LRLT), and Trout Unlimited (TU).

IDFG: Lower Lemhi Eagle Valley Ranch Subreach 1 (phase 2&3), Phase 2 of the Middle Lemhi Henry Reach project.
Lemhi SWCD:  Lemhi river mile 32 and Hayden Reach Phase 1 projects.
LRLT: Upper Big Springs and Pond Outlet Restoration.
TU: Lower Canyon Creek fencing and planting.
Account Type(s):
Expense
Contract Start Date:
03/01/2022
Contract End Date:
02/28/2023
Current Contract Value:
$1,340,352
Expenditures:
$1,340,352

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Daniel Affonso Bonneville Power Administration Yes Contracting Officer dxaffonso@bpa.gov (503) 230-3893
Matt Belnap Idaho Department of Fish and Game (IDFG) Yes Technical Contact matt.belnap@idfg.idaho.gov (208) 569-1283
Daniel Bertram Idaho Governor's Office of Species Conservation Yes Contract Manager daniel.bertram@osc.idaho.gov (208) 756-6322
Jessica Buelow Idaho Department of Fish and Game (IDFG) Yes Technical Contact jessica.buelow@idfg.idaho.gov (208) 756-2271
Sharon Clark Idaho Department of Fish and Game (IDFG) Yes Interested Party sharon.clark@idfg.idaho.gov (208) 287-2784
Becky Coffey Lemhi Soil and Water Conservation District (SWCD) Yes Interested Party lswcd@hotmail.com (208) 756-3211x101
Dominique Cota Idaho Governor's Office of Species Conservation Yes Technical Contact dominique.cota@osc.idaho.gov (208) 332-1550
Jeffrey DiLuccia Idaho Department of Fish and Game (IDFG) Yes Technical Contact jeff.diluccia@idfg.idaho.gov (208) 756-2271
Mike Edmondson Idaho Governor's Office of Species Conservation No Supervisor mike.edmondson@osc.idaho.gov (208) 334-2189
Graham Freeman Idaho Governor's Office of Species Conservation Yes Supervisor graham.freeman@osc.idaho.gov (208) 332-1555
Chris Gaughan Lemhi Soil and Water Conservation District (SWCD) Yes Technical Contact chrisgaughan@outlook.com (208) 515-6484
Abbie Gongloff Idaho Governor's Office of Species Conservation Yes Technical Contact abbie.gongloff@osc.idaho.gov (208) 756-6322
Matt Green Trout Unlimited (TU) Yes Technical Contact mgreen@tu.org (208) 251-0197
Amy Hines Idaho Governor's Office of Species Conservation Yes Contract Manager amy.hines@osc.idaho.gov (208) 332-1557
Eric Leitzinger Bonneville Power Administration Yes F&W Approver ejleitzinger@bpa.gov (503) 230-3534
Timothy Ludington Bonneville Power Administration Yes COR tsludington@bpa.gov (503) 230-4988
Heidi Messner Idaho Governor's Office of Species Conservation Yes Technical Contact heidi.messner@osc.idaho.gov (208) 993-1060
Stacey Meyer Idaho Department of Fish and Game (IDFG) Yes Technical Contact stacey.meyer@idfg.idaho.gov (208) 756-6022
Justin Saydell Idaho Governor's Office of Species Conservation Yes Technical Contact justin.saydell@osc.idaho.gov (208) 756-6322
Robert Shull Bonneville Power Administration Yes Env. Compliance Lead rwshull@bpa.gov (503) 230-3962
Joe Stewart Trout Unlimited (TU) Yes Technical Contact joseph.stewart@tu.org (206) 909-3188
Jonathan Viti Idaho Governor's Office of Species Conservation Yes Technical Contact jonathan.viti@osc.idaho.gov (802) 881-1444
Caselle Wood Trout Unlimited (TU) Yes Technical Contact caselle.wood@tu.org (208) 390-2028


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Effective implementation management and timely contract administration A: 119. Routine/daily administration of work elements 02/28/2023 02/27/2023
Complete all required EC and obtain permits prior to implementation of project B: 165. Produce Environmental Compliance Documentation 02/28/2023 02/21/2023
Completed Annual Report D: 132. Submit Progress Report for the period March 2021 through February 2022 08/31/2022 09/21/2022
Effective implementation management and timely contract administration E: 119. IDFG: Manage and Administer Project 02/28/2023 02/15/2023
Develop or update (out-year) prioritized Habitat Project list: upload to Pisces F: 114. IDFG: Lemhi River Project Development 02/28/2023 02/21/2023
Complete construction on phase 2 & 3 EVR Subreach 1 on lower Lemhi River. G: 29. IDFG: Lower Lemhi Eagle Valley Ranch Subreach 1 Phase 2 & 3 Implementation 02/28/2023
Submit final design and bid documents for Bohannon Diversion 3 pump station I: 175. IDFG: Bohannon Diversion 3 Pump Station Evaluation 01/31/2023
Submit design and bid documents for EVR Subreach 4 on the lower Lemhi River J: 175. IDFG: Lower Lemhi Eagle Valley Ranch Sub-reach 4 - Complete Sub-reach 4 Design 02/28/2023 02/21/2023
Unscheduled maintenance on habitat/passage/structures completed as needed. K: 186. IDFG: Perform Unscheduled Maintenance of Habitat Project Sites 02/28/2023 02/21/2023
Effective implementation management and timely contract administration L: 119. Lemhi SWCD: Project Implementation: Manage and Administer 02/28/2023 02/23/2023
Provide project management and construction oversight M: 100. Lemhi SWCD Project Implementation: Provide Project Implementation Support & Construction Oversight 02/28/2023 02/23/2023
Develop or update (out-year) prioritized Habitat Project list: upload to Pisces N: 114. Lemhi SWCD Project Implementation: Identify and Select Projects 02/28/2023 02/23/2023
Vegetation managed through noxious and non-native weed herbicide treatments O: 199. Lemhi SWCD: Lemhi Vegetation: Initial treatment 11/30/2022 11/30/2022
Vegetation maintenance activities complete P: 198. Lemhi SWCD: Lemhi Vegetation: Ongoing treatment 02/28/2023 02/23/2023
Planting Completed Q: 47. Lemhi SWCD: Lemhi Vegetation Management: Rehabilitate Project Sites 12/30/2022 12/21/2022
Final designs completed and submitted to BPA R: 175. Lemhi SWCD: Middle Lemhi Hayden Reach Phase I - Design 02/28/2023 07/08/2022
2022 construction is complete S: 29. Lemhi SWCD: Middle Lemhi Hayden Reach Phase I - Implementation 02/28/2023
Provide final design U: 175. Lemhi SWCD: L-45 Diversion and Restoration Design 02/28/2023
Fence repair and site demobilization complete X: 186. TU: Lower Canyon Creek: Repair existing fence and site demobilization 02/28/2023 07/11/2022
Final design completed and uploaded in cbfish. AF: 175. LRLT: Lemhi River and Kenney Creek Jackson Project 02/28/2023
Habitat project imagery and geo referenced maps for use by cooperators. AG: 161. IDFG: Maintain cloud-based repository for habitat project imagery and geo referenced maps for project planning and cooperator use. 02/28/2023 02/21/2023
Eagle Valley Ranch Subreach 1 phase 1 replanted AI: 47. IDFG: Fall revegetation of Eagle Valley Ranch sub reach 1 phase 1 and phase 2. 02/28/2023 02/21/2023
Fence installed. AJ: 40. IDFG: Revegetation fencing 02/28/2023 02/21/2023

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 198 Maintain Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 3 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 35 Develop Pond
  • 3 instances of WE 40 Install Fence
  • 4 instances of WE 47 Plant Vegetation
  • 2 instances of WE 114 Identify and Select Projects
  • 5 instances of WE 175 Produce Design
  • 2 instances of WE 100 Construction Management
  • 1 instance of WE 208 Irrigation Infrastructure Construction or Replacement
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 208 Irrigation Infrastructure Construction or Replacement
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 4 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 35 Develop Pond
  • 3 instances of WE 40 Install Fence
  • 4 instances of WE 47 Plant Vegetation
  • 2 instances of WE 114 Identify and Select Projects
  • 5 instances of WE 175 Produce Design
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
  • 2 instances of WE 100 Construction Management
  • 2 instances of WE 208 Irrigation Infrastructure Construction or Replacement

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Routine/daily administration of work elements
B 165 Produce Environmental Compliance Documentation
C 185 Periodic Status Reports for BPA
D 132 Submit Progress Report for the period March 2021 through February 2022
E 119 IDFG: Manage and Administer Project
F 114 IDFG: Lemhi River Project Development
G 29 IDFG: Lower Lemhi Eagle Valley Ranch Subreach 1 Phase 2 & 3 Implementation 08/29/2022
H 29 IDFG: Complete Middle Lemhi Henry Reach Phase 2. 09/20/2022
I 175 IDFG: Bohannon Diversion 3 Pump Station Evaluation 02/11/2022
J 175 IDFG: Lower Lemhi Eagle Valley Ranch Sub-reach 4 - Complete Sub-reach 4 Design 02/11/2022
K 186 IDFG: Perform Unscheduled Maintenance of Habitat Project Sites 06/10/2022
L 119 Lemhi SWCD: Project Implementation: Manage and Administer
M 100 Lemhi SWCD Project Implementation: Provide Project Implementation Support & Construction Oversight
N 114 Lemhi SWCD Project Implementation: Identify and Select Projects
O 199 Lemhi SWCD: Lemhi Vegetation: Initial treatment 04/27/2022
P 198 Lemhi SWCD: Lemhi Vegetation: Ongoing treatment 04/27/2022
Q 47 Lemhi SWCD: Lemhi Vegetation Management: Rehabilitate Project Sites 04/27/2022
R 175 Lemhi SWCD: Middle Lemhi Hayden Reach Phase I - Design 02/11/2022
S 29 Lemhi SWCD: Middle Lemhi Hayden Reach Phase I - Implementation 09/21/2022
T 208 Lemhi SWCD: Lemhi River Mile 32 Restoration and Diversion Consolidation
U 175 Lemhi SWCD: L-45 Diversion and Restoration Design 02/11/2022
V 47 TU: Lower Canyon Creek: Plant Vegetation
W 40 TU: Lower Canyon Creek: Install Fence
X 186 TU: Lower Canyon Creek: Repair existing fence and site demobilization
Y 29 LRLT: Upper Big Springs and Pond Outlet Restoration: In-stream Features
Z 100 LRLT: Upper Big Springs and Pond Outlet Restoration: Construction Oversight
AA 30 LRLT- Upper Big Springs and Pond Outlet Restoration: New Channel Construction
AB 35 LRLT: Upper Big Springs and Pond Outlet Restoration: Pond Outlet Relocation
AC 40 LRLT: Upper Big Springs and Pond Outlet Restoration: Install Fence
AD 47 LRLT: Upper Big Springs and Pond Outlet Restoration: Plant Vegetation
AE 188 LRLT: Lemhi Kiosks
AF 175 LRLT: Lemhi River and Kenney Creek Jackson Project 06/13/2022
AG 161 IDFG: Maintain cloud-based repository for habitat project imagery and geo referenced maps for project planning and cooperator use.
AH 208 IDFG: Reconstruct the Bohannon Creek Diversion #3 10/26/2022
AI 47 IDFG: Fall revegetation of Eagle Valley Ranch sub reach 1 phase 1 and phase 2. 08/29/2022
AJ 40 IDFG: Revegetation fencing 08/29/2022