Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 92053: 2007-398-00 EXP YAK TRIB ACCESS & HABITAT PRGM 2023
Project Number:
Title:
Yakima Basinwide Tributary Passage and Flow
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
92053
Contract Title:
2007-398-00 EXP YAK TRIB ACCESS & HABITAT PRGM 2023
Contract Continuation:
Previous: Next:
89876: 2007-398-00 EXP YTAHP FY22
  • 94307: 2007-398-00 EXP FY24 YTAHP
Contract Status:
Issued
Contract Description:
Under CR-359771 the following work and services will be accomplished by the YTAHP Team:

BPA funding for FY 2023 will support the implementation of 10 fish passage and habitat restoration projects, ongoing riparian vegetation and site stewardship on 3 projects and provided significant work toward project development, permits, design and/or funding for an additional 8 projects. The projects completed in FY 2023 will cumulatively result in screening 7.3 cfs of diverted surface water, restore fish passage to 6.1 miles of tributary habitat and install over .48 miles of riparian planting on seven streams in the Yakima Basin.  

Project Background:

The Yakima Tributary Access & Habitat Program was formed in 2001 in response to the listing of Middle Columbia River steelhead and bull trout under the Endangered Species Act.  The objectives of the program are to screen surface water diversions, restore fish passage and enhance salmonid habitat.  The focus of the program is on Yakima River tributaries that historically supported salmonids and on riparian areas where fish passage is restored.  The YTAHP fills a unique and important role in salmonid recovery by facilitating a voluntary program in which private landowners can come into compliance with fish screening and passage laws.

In general, projects on tributaries are prioritized sequentially, moving upstream from the confluence with the Yakima River; as projects are completed, the regained habitat is connected to the mainstem and available to anadromous fish.  YTAHP has concentrated on tributaries upstream of Union Gap where salmonids are known to have occurred historically.  Streams have been surveyed for fish passage barriers, analyzed for screening of diversions, and assessed for habitat quality using WDFW’s Salmonid Screening, Habitat Enhancement, and Restoration (SSHEAR) protocol.  At times projects may appear out of sequence but do fit in the context of multi-year planning.  YTAHP uses BPA funds to leverage cost share funds from a variety of other sources, thus expanding the funding pie.  For passage projects, YTAHP works with local landowners and irrigation water delivery entities who voluntarily participate.  BPA funds are used only for planning, design, permitting and implementation.  There are no changes to facility ownership status or operation and maintenance responsibilities resulting from YTAHP work.  BPA takes on no responsibilities for ownership or O&M.

The Current YTAHP Roles and Responsibilities are as follows:
Brian Miller- Washington Resource & Conservation (RC&D) Council YTAHP Program Manager
Mike Tobin- North Yakima Conservation District (NYCD) District Manager
Justin Bader- NYCD Yakima Tributary Access and Habitat Program Coordinator
Anna Lael- Kittitas Conservation County District (KCCD) District Manager
Mark Crowley- KCCD Conservation Planner for YTAHP projects
Cassandra Weeks- WDFW YTAHP Permitting, Environment Compliance & Watershed Project Coordination    
Account Type(s):
Expense
Contract Start Date:
04/01/2023
Contract End Date:
03/31/2024
Current Contract Value:
$858,227
Expenditures:
$806,734

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Effective implementation management and timely contract administration B: 119. RC&D management of the YTAHP program & subcontractor administrative work 03/31/2024 03/28/2024
Watershed coordination activities have been completed C: 191. Watershed Coordination 03/31/2024 03/28/2024
Completed Annual Report D: 132. Submit annual report for 04/01/2022 - 03/31/2023 (FY 2022) 01/01/2024 09/01/2023
Technical input into project development E: 122. Technical Review 03/31/2024 03/28/2024
Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish F: 114. Identify and Select projects 08/01/2023 08/01/2023
Produce Environmental Compliance Documentation G: 165. Produce Environmental Compliance Documentation - Permitting 03/31/2024 03/28/2024
Vegetation maintenance activities were implemented H: 198. Naches River- Maintain Vegetation- Edgar (Related to WE K on the FY 2022 Contract 89876) 03/31/2024 03/28/2024
Fish screen is installed I: 208. Wenas Creek- Fish Screen- Faxon (New) 12/31/2023 08/01/2023
Vegetation maintenance activities are complete J: 198. Wenas Creek- Maintain Vegetation- McKinney (Related to WE J on Contract 89876) 03/31/2024 03/28/2024
Vegetation has been planted K: 47. Naches River- Plant Vegetation- Edgar Phase 2 (New) 03/31/2024
Fence is installed L: 40. Naches River- Install Fence- Edgar Phase 2 (New) 03/31/2024
Upload final design set M: 175. Wenas Creek- Purdin Ditch Fish Screening & Passage- Produce Design (Continued from WE M on Contract 89876) 03/31/2024 03/28/2024
Irrigation Diversion is Removed N: 208. Wenas Creek- Purdin Ditch Fish Screening & Passage- Remove Diversion (New) 03/31/2024
Vegetation has been planted. O: 47. Wenas Creek- Purdin Ditch Fish Screening & Passage- Plant Vegetation (New) 03/31/2024
Project concepts and preferred alternative (typically 30% design) developed and submitted for review P: 175. Wenas Creek- Fish Passage and Screening Project- Produce Design (Continued from WE N on Contract 89876) 03/31/2024
Produce bid ready designs and specifications R: 175. Cascade at Coleman Intersection (continued from WE R in 2022 Contract 89876) 03/31/2024
Produce bid ready designs and specifications S: 175. Naneum 2.9 and 3.2 - Screening and Passage (continued from WE T on the 2022 Contract 89876) 03/31/2024
Final project designs T: 175. Naneum Creek - Ellensburg Water Company Intersection (continued from WE T in 2022 Contract 89876) 03/31/2024
Produce final designs and specifications U: 175. Big Creek No. 2 - Ensign Ranch (new) 03/31/2024
Permit Ready Designs V: 175. Whiskey Creek Barriers RM 1.5-1.7 (new) 03/31/2024
Vegetation maintenance activity has been implemented W: 198. Coleman 3.4 Olmstead Park (continued from WE V in 2022 Contract 89876) 03/31/2024 03/28/2024
Maintain planting site X: 198. Parke Creek 1.01 (connected to WE AC in 2021 contract 87467) 03/31/2024 03/28/2024
Plant trees and shrubs on Coleman Creek Y: 47. Coleman Creek 2.5 (connected to WE AC in 2022 Contract 89876) 03/31/2024 03/28/2024
Install fish screen and fish passage structures Z: 208. Coleman Creek 4.4 -Schomer/Beard (Continued from WE S on the FY 2020 Contract 84929) 03/31/2024 03/15/2024
Install Fish Screen and Correct Barriers AB: 208. Naneum 2.9 and 3.2 Screening and Passage (new) 03/31/2024
Fish Passage AD: 85. CCR- 48725 Coleman 2.5 Valley Land Co 03/31/2024 01/31/2024
Compressor Replacements AE: 186. CCR- 48725 Manastash Creek Diversions Operation & Maintenance 03/31/2024
Complete Permit Ready Designs AF: 175. CCR 48725 - Cooke Creek 3.86 and 4.25 03/31/2024

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 4 instances of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 40 Install Fence
  • 3 instances of WE 47 Plant Vegetation
  • 2 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 114 Identify and Select Projects
  • 9 instances of WE 175 Produce Design
  • 5 instances of WE 208 Irrigation Infrastructure Construction or Replacement

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 119 RC&D management of the YTAHP program & subcontractor administrative work
C 191 Watershed Coordination
D 132 Submit annual report for 04/01/2022 - 03/31/2023 (FY 2022)
E 122 Technical Review
F 114 Identify and Select projects
G 165 Produce Environmental Compliance Documentation - Permitting
H 198 Naches River- Maintain Vegetation- Edgar (Related to WE K on the FY 2022 Contract 89876) 04/01/2023
I 208 Wenas Creek- Fish Screen- Faxon (New) 05/03/2023
J 198 Wenas Creek- Maintain Vegetation- McKinney (Related to WE J on Contract 89876) 04/01/2023
K 47 Naches River- Plant Vegetation- Edgar Phase 2 (New) 07/18/2023
L 40 Naches River- Install Fence- Edgar Phase 2 (New) 07/18/2023
M 175 Wenas Creek- Purdin Ditch Fish Screening & Passage- Produce Design (Continued from WE M on Contract 89876) 03/26/2024
N 208 Wenas Creek- Purdin Ditch Fish Screening & Passage- Remove Diversion (New) 03/26/2024
O 47 Wenas Creek- Purdin Ditch Fish Screening & Passage- Plant Vegetation (New) 03/26/2024
P 175 Wenas Creek- Fish Passage and Screening Project- Produce Design (Continued from WE N on Contract 89876) 03/26/2024
Q 175 Coleman Creek 4.6 - Raap (continued from WE Q in 2022 Contract 89876)
R 175 Cascade at Coleman Intersection (continued from WE R in 2022 Contract 89876) 12/14/2023
S 175 Naneum 2.9 and 3.2 - Screening and Passage (continued from WE T on the 2022 Contract 89876)
T 175 Naneum Creek - Ellensburg Water Company Intersection (continued from WE T in 2022 Contract 89876) 12/14/2023
U 175 Big Creek No. 2 - Ensign Ranch (new) 12/14/2023
V 175 Whiskey Creek Barriers RM 1.5-1.7 (new) 12/14/2023
W 198 Coleman 3.4 Olmstead Park (continued from WE V in 2022 Contract 89876) 04/01/2023
X 198 Parke Creek 1.01 (connected to WE AC in 2021 contract 87467) 04/01/2023
Y 47 Coleman Creek 2.5 (connected to WE AC in 2022 Contract 89876) 04/01/2023
Z 208 Coleman Creek 4.4 -Schomer/Beard (Continued from WE S on the FY 2020 Contract 84929) 12/19/2023
AA 208 Big Creek No. 2 Ensign Ranch (new)
AB 208 Naneum 2.9 and 3.2 Screening and Passage (new)
AC 85 Naneum Creek - Ellensburg Water Company Intersection (new)
AD 85 CCR- 48725 Coleman 2.5 Valley Land Co 12/11/2023
AE 186 CCR- 48725 Manastash Creek Diversions Operation & Maintenance 05/30/2023
AF 175 CCR 48725 - Cooke Creek 3.86 and 4.25 12/14/2023