SOW Report
Contract 84064 REL 4: 2019-001-00 EXP SEKOKINI SPRINGS HATCHERY
Project Number:
Title:
Sekokini Springs Hatchery
Stage:
Implementation
Area:
None
Contract Number:
84064 REL 4
Contract Title:
2019-001-00 EXP SEKOKINI SPRINGS HATCHERY
Contract Continuation:
Previous: Next:
76916 REL 24: 2019-001-00 EXP SEKOKINI SPRINGS HATCHERY
  • CR-369597: 201900100 SEKOKINI SPRINGS HATCHERY
Contract Status:
Issued
Contract Description:
Project 1991-001-000 background and context for the Sekokini Research Facility:

In 1991, Montana Fish Wildlife & Parks (MFWP) and the Confederated Salish and Kootenai Tribes (CSKT) published the Fisheries Mitigation Plan for Losses Attributable to the Construction and Operation of Hungry Horse Dam (MFWP and CSKT 1991).  This Mitigation Plan presented fisheries losses, mitigation options, and recommendations to protect, mitigate, and enhance resident fish and aquatic habitat harmed by the construction and operation of Hungry Horse Dam. The Northwest Power and Conservation Council (Council; formerly the Northwest Power Planning Council) approved the loss statement that included annual losses of juvenile bull trout (Salvelinus confluentus) and juvenile westslope cutthroat trout (WCT; Oncorhynchus clarkii lewisi), as well as the inundation loss of 124 km of critical, low gradient spawning and rearing habitat drowned when Hungry Horse Reservoir was filled. The Council next directed MFWP and CSKT to develop an Implementation Plan, subsequently also adopted for Hungry Horse Dam (MFWP and CSKT 1993). On-the-ground mitigation activities began in 1992. This project is one of a few federally-funded Columbia River mitigation projects carrying out a plan to offset a Council-adopted loss statement. Fisheries losses were to be offset by modifying dam operations, restoring or reconnecting habitat, reducing negative non-native species interactions, and implementing hatchery (native fish conservation) technology and offsite mitigation. Sekokini Springs ultimately developed from this last mitigation strategy.

In 2004, the Council adopted the Flathead Subbasin Plan in 2004 (CSKT and MFWP 2004) that further refined and codified previous approaches to fisheries loss mitigation. The federal action agency's 4-H plan is designed to recover Columbia River fish species listed as threatened or endangered under the Endangered Species Act (Federal Caucus 2000).  Our mitigation program is directed by a similar scientific framework to offset fisheries losses at various spatial scales, descending from basin-wide mitigation requirements to site-specific actions. Mitigation activities are selected and prioritized based on decision pathways described in the Flathead Subbasin Plan (2004), Among those activities is development and implementation of facilities like Sekokini Springs. In 2011, following in the wake of the Council's 3-step process of review, NPCC approved a 17-year experiment to use the capabilities provided by Sekokini Springs to help offset fisheries losses associated with Hungry Horse Dam.

The challenge and response:

The Sekokini Springs Research Facility is designed as a tool to help conserve the remaining genetic diversity of westslope cutthroat trout in the Upper Columbia River Basin. Sekokini provides a place and opportunity to systematically replicate populations that differ from the state’s M012 broodstock and to create additional sources of WCT for future restoration actions and similar hatchery applications.  Sekokini can provide unique WCT stocks for restocking lakes treated to remove genetically introgressed WCT populations.  

Restoring westslope cutthroat trout (WCT) throughout their historic range requires developing new methods and facilities.  In northwestern Montana, about half of the remaining wild, genetically pure populations inhabit the South Fork Flathead River, upstream of Hungry Horse Dam.  Surveys throughout northwestern Montana demonstrated that each stream population is genetically distinct, even in adjacent streams, and most differ from Montana’s single captive brood stock held at the Washoe Park State Fish hatchery in Anaconda, MT (called M012).  To protect the remaining genetic diversity in the Flathead Subbasin, We designed an experimental culture facility at Sekokini Springs, located about a mile downstream of Blankenship Bridge at the confluence of the North and Middle Forks of the Flathead River.  Unlike other Montana state hatcheries, wild WCT can be transported to Sekokini Springs and held in isolation until they are certified genetically pure and free of all reportable pathogens.  After certification, juvenile WCT from unique donor populations are reared to maturity and spawned to replicate progeny for WCT restoration. The isolation facility at Sekokini was designed to rear up to four unique strains of WCT simultaneously.  This is not a traditional captive broodstock hatchery. Instead, wild donor WCT will be held only as long as necessary to re-establish self-reproducing populations in restored waters throughout the Flathead Subbasin.  As of 2023, sourcestocks have been replicated from the Danaher River, Young’s, Quintonkon, Sullivan, and Emery Creeks, all from the South Fork Flathead Drainage.  These have been used to produce progeny for stocking Lick, Lena, Necklace Lakes (3), Koessler, Handkerchief, and Sunburst Lakes.  In 2019, the program expanded to include donor sources from the North Fork Flathead (Starvation Creek 2019, and Hay Creek 2019-present).  These produce progeny for stocking Glacier National Parks Lakes Evangeline and Camas in the North Fork subbasin.  In 2021 and 2022, fish were collected from Stahl Creek, a tributary of the Tobacco River in the Kootenai River.  These will produce progeny for genetic swamping of Weasel Lake starting in 2023 and restocking Rainbow Lake in 2024.  Both Lakes are in the Kootenai River Subbasin.  

Collecting wild WCT from remote wilderness streams requires coolers with ice and oxygen for transport by pack stock to the wilderness boundary, and then road or air transport to Sekokini Springs, with very little mortality.  Wild WCT from each source are collected over a minimum of three years, and we later examine progeny, to assure their genetics resemble the original donor population.  Adapting the wild juveniles to captivity, while preserving wild behavioral traits and avoiding domestication, is another challenge.  Roughly half of the wild WCT have had difficulty transitioning to pelletized hatchery food.  To prevent starvation, we supplement feedings with amphipods collected from Sekokini Springs and live mealworms until the juvenile fish can switch to pellet feed.  
The Sekokini Springs master Plan contains a research component. The Isolation Facility produces WCT and conducts research for the South Fork Flathead Drainage WCT Conservation Project that is removing sources of nonnative trout and re-establishing native WCT in the most intact metapopulation of WCT in Montana.  Restored lakes offer living laboratories to empirically link genetic differences to measures of fish performance (e.g. survival, growth, fecundity, local adaptations).  We are developing nonlethal sampling methods to reduce impacts on sensitive species.  Previous research began to assess the influence of enriched hatchery environments on survival, growth and physical parameters.  Current and future experiments will expand on this work to determine if and how hatchery experimental rearing conditions affect gene expression.  

The current contract:

Starting in STATE fiscal year 2024, this project will continue to produce WCT fry for restocking high mountain lakes in the Bob Marshall Wilderness.  Specific activities are explained within this SOW.  Funding for ongoing and continuing efforts beyond state fiscal year 2024 will be arranged on an annual basis during implementation of this existing contract, and in subsequent years thereafter.
Account Type(s):
Expense
Contract Start Date:
07/01/2023
Contract End Date:
06/30/2024
Current Contract Value:
$324,416
Expenditures:
$199,493

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Matt Boyer Montana Fish, Wildlife and Parks (MFWP) Yes Contract Manager mboyer@mt.gov (406) 751-4570
Jay Chong Bonneville Power Administration Yes Contracting Officer jxchong@bpa.gov (503) 230-4007
Mike Hensler Montana Fish, Wildlife and Parks (MFWP) No Supervisor mhensler@mt.gov (406) 751-4550
Charli Just Montana Fish, Wildlife and Parks (MFWP) No Administrative Contact cjust@mt.gov (406) 444-7063
David Kaplowe Bonneville Power Administration Yes F&W Approver djkaplowe@bpa.gov (503) 230-5365
Jessica Power Bonneville Power Administration Yes CO Assistant jdpower@bpa.gov (503) 230-4023
Scott Relyea Montana Fish, Wildlife and Parks (MFWP) Yes Technical Contact srelyea@mt.gov (406) 387-4621
Jannice Richardson Montana Fish, Wildlife and Parks (MFWP) No Administrative Contact jarichardson@mt.gov (406) 444-7319
Elizabeth Santana Bonneville Power Administration Yes COR easantana@bpa.gov (503) 230-3560


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Effective implementation management and timely contract administration A: 119. Project M&A 06/30/2024
Produce Environmental Compliance Documentation B: 165. EC compliance 06/30/2024
Weed Control C: 199. Weed control 06/30/2024
Produce annual operation plan D: 174. Produce an Annual Operation Plan 06/30/2024
Produce genetically pure WCT fry for lake stocking E: 176. Sustain exisiting fish culture operations and activities 06/30/2024
Stock Sunburst Lake F: 187. Stock Sunburst Lake 06/30/2024
Maintain Artificial Production Facility G: 61. Daily hatchery O&M and water quality monitoring of discharge 06/30/2024
Stock Evangeline Lake H: 187. Stock Evangeline Lake 06/30/2024
Stock Camas Lake I: 187. Stock Camas Lake 06/30/2024
Stock Weasel Lake J: 187. Stock Weasel Lake 06/30/2024
Completed Annual Report K: 132. Submit Annual Report for the period January 2023 to December 2023 04/29/2024

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Cutthroat Trout, Westslope (O. c. lewisi)
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 176 Produce Hatchery Fish
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 4 instances of WE 187 Put and Take Fisheries
  • 1 instance of WE 174 Produce Plan
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 199 Remove Vegetation

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Project M&A
B 165 EC compliance
C 199 Weed control 07/01/2023
D 174 Produce an Annual Operation Plan 07/01/2023
E 176 Sustain exisiting fish culture operations and activities 07/01/2023
F 187 Stock Sunburst Lake 07/01/2023
G 61 Daily hatchery O&M and water quality monitoring of discharge 07/01/2023
H 187 Stock Evangeline Lake 07/01/2023
I 187 Stock Camas Lake 07/01/2023
J 187 Stock Weasel Lake 07/01/2023
K 132 Submit Annual Report for the period January 2023 to December 2023
L 185 Periodic Status Reports for BPA