| Province | Subbasin | % |
|---|---|---|
| Middle Snake | Owyhee | 100.00% |
| Previous: | Next: |
|---|---|
| 84050 REL 9: 1995-057-03 EXP SOUTHERN IDAHO WILDLIFE MITIGATION - POLE CREEK |
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Full Name | Organization | Write Permission | Contact Role | Work Phone | |
|---|---|---|---|---|---|
| Daniel Affonso | Bonneville Power Administration | Yes | Contracting Officer | dxaffonso@bpa.gov | (503) 230-5918 |
| Christopher Cleveland | Shoshone-Paiute Tribes | Yes | Interested Party | cleveland.chris@shopai.org | (208) 759-3246 |
| Buster Gibson | Shoshone-Paiute Tribes | Yes | Supervisor | gibson.busterl@shopai.org | (208) 759-3246 |
| Heidi Haak | Bonneville Power Administration | No | Interested Party | hlhaak@bpa.gov | (541) 922-6856 |
| David Kaplowe | Bonneville Power Administration | Yes | F&W Approver | djkaplowe@bpa.gov | (503) 230-5365 |
| Carol Perugini | Shoshone-Paiute Tribes | Yes | Contract Manager | perugini.carol@shopai.org | (775) 763-6015 |
| Jennifer Plemons | Bonneville Power Administration | Yes | COR | jeplemons@bpa.gov | (503) 230-3837 |
| JESSICA POWER | Bonneville Power Administration | No | CO Assistant | jdpower@bpa.gov | (503) 230-4023 |
| John Vlastelicia | Bonneville Power Administration | No | Env. Compliance Lead | jmvlastelicia@bpa.gov | (503) 230-5986 |
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Effective implementation management and timely contract administration | A: 119. Project administration | 09/30/2026 | ||
| Complete environmental compliance activities | B: 165. Satisfy environmental compliance requirements | 09/30/2026 | ||
| List of parcels for consideration for acquisition under the SIWM Program | C: 115. SIWM Parcel Identification | 09/30/2026 | ||
| Complete Pre-acquisition activities on wildlife mitigation parcel | D: 172. Conduct pre-acquisitional tasks | 09/30/2026 | ||
| Projects prioritized based on the most current data | E: 114. SIWM Coordination | 09/30/2026 | ||
| Complete O&M on Pole Creek Property | F: 186. Fence maintenance, maintain infrastructure at Pole Creek Ranch | 09/30/2026 | ||
| Columbia spotted frog survey data | G: 115. Conduct Columbia spotted frog surveys on Pole Creek Ranch | 09/30/2026 | ||
| Trespass incidents documented as needed | H: 26. Investigate trespass on Pole Creek Ranch | 09/30/2026 | ||
| Weed Treatment Records | I: 199. Conduct weed treatment activities | 09/30/2026 | ||
| Grazing treatment completed 2026 | J: 199. Prescribed grazing treatment on main parcel of ranch | 09/30/2026 | ||
| Documentation of junipers cut down in 2026 | K: 198. Cut and lay down 2000 stage one juniper trees from Pole Creek main parcel | 09/30/2026 | ||
| Pond D planted with native wetland species | L: 198. Plant bare root seedlings on Pond D to complement pond bank seeding that occurred in 2023 | 09/30/2026 | ||
| Completed Progress (Annual) Report | M: 132. Submit Progress Report for the period (1/1/25 to 12/31/25) | 04/30/2026 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Trout, Interior Redband (O. mykiss gairdnerii) |
|
| Wildlife |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 119 | Project administration | |||||||
| B | 165 | Satisfy environmental compliance requirements | |||||||
| C | 115 | SIWM Parcel Identification | 10/07/2025 | ||||||
| D | 172 | Conduct pre-acquisitional tasks | |||||||
| E | 114 | SIWM Coordination | |||||||
| F | 186 | Fence maintenance, maintain infrastructure at Pole Creek Ranch | 10/07/2025 | ||||||
| G | 115 | Conduct Columbia spotted frog surveys on Pole Creek Ranch | 10/07/2025 | ||||||
| H | 26 | Investigate trespass on Pole Creek Ranch | |||||||
| I | 199 | Conduct weed treatment activities | 10/07/2025 | ||||||
| J | 199 | Prescribed grazing treatment on main parcel of ranch | 10/07/2025 | ||||||
| K | 198 | Cut and lay down 2000 stage one juniper trees from Pole Creek main parcel | 10/07/2025 | ||||||
| L | 198 | Plant bare root seedlings on Pond D to complement pond bank seeding that occurred in 2023 | |||||||
| M | 132 | Submit Progress Report for the period (1/1/25 to 12/31/25) | |||||||
| N | 185 | Periodic Status Reports for BPA |