Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 56337: 1996-040-00 EXP COHO RESTORATION MID-COLUMBIA
Project Number:
Title:
Upper Columbia Production
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Methow 40.00%
Wenatchee 60.00%
Contract Number:
56337
Contract Title:
1996-040-00 EXP COHO RESTORATION MID-COLUMBIA
Contract Continuation:
Previous: Next:
51817: 1996-040-00 EXP COHO RESTORATION MID-COLUMBIA - YN
  • 56662 REL 43: 1996-040-00 EXP COHO RESTORATION MID-COLUMBIA - O&M/M&E
Contract Status:
Closed
Contract Description:
The long term vision of this restoration project is to restore coho salmon to the Wenatchee and Methow river basins at biologically sustainable levels that will support harvest in most years. The project works toward development of locally adapted, naturally spawning coho populations in the Wenatchee and Methow subbasins by increasing the fitness of reintroduced coho salmon by reducing domestication and emphasizing local adaptation. The program will use strict broodstock collection protocols, which ultimately will place a limit on the proportion of natural origin adults in the hatchery program and place a limit on the proportion of hatchery origin adults on the spawning ground. Hatchery smolt production work is covered under BPA contracts with other agencies.  The U.S. Fish and Wildlife Service is contracted to full-term rear coho at Willard NFH and Winthrop NFH while also providing spawning, incubation and acclimation space at Leavenworth NFH and Winthrop NFH.  Willard NFH is partially funded through Mitchell Act while all of the rearing costs associated with Cascade FH are Mitchell Act.  Winthrop fall activities and subsequent full-term rearing of these juveniles is funded through BOR.  This will be the 3rd and possibly 4th (dependant on outcome of small scale facility) seasons that Leavenworth NFH will be utilized as the primary adult holding/spawning location for the Wenatchee program.  Leavenworth NFH will be contracted directly through BPA to provide adult holding and spawning space for the Wenatchee coho program.  Transportation of smolts from lower river facilities to acclimation ponds in the Wenatchee and Methow rivers is done through a direct contract between Oregon Department of Fish and Wildlife and BPA as well as utilizing Yakama Nation drivers to supplement ODFW transports.  

This SOW includes includes work elements for tasks that will be completed prior to January 31st, 2014.  This 24-month contract is being put in place through Accord funding that will include fall activities for the 2012/2013 CYs and extend through the early winter 2014CY.  Cost-share funding through Chelan County PUD and Grant County PUD play a critical role in assisting with meeting project costs/goals.  For example, Chelan PUD funds will pay entirely for dredging and expansion of Rohlfing's Pond, which are NOT part of this contract.  CWT'ing will be paid through a subcontract between USFWS and YN (BPA funding) for marking of the 2011 and 2012BYs.  O&M and M&E activities; to include broodstock collection, spawning, egg incubation and transportation to the lower Columbia River rearing facilities, spawning ground surveys, and subsequent data collection and CWT extraction for both the Wenatchee and Methow basins will be approximately 50% covered by the cost-sharing through the PUD's.  Concurrent project management, data analysis, and database management will also be approximately 50% covered by the PUD cost-share.   BPA will be responsible for partial funding of all O&M and M&E activities in the winter, spring, and summer, and fall for the 2012 and 2013 calendar years as well as the winter 2014.  These activities include overwinter acclimation, spring acclimation and all related data collection and analysis, and a repeat of the above listed fall activities.  Reporting period extends into the next years contract and will be addressed in the SOW.  The program will also take this opportunity to develop a comprehensive brood report to try and identify trends and standards established within the program recent successes.
Account Type(s):
Expense
Contract Start Date:
02/01/2012
Contract End Date:
04/30/2014
Current Contract Value:
$3,079,253
Expenditures:
$3,079,253

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Debbie Azure Yakama Confederated Tribes Yes Administrative Contact azud@yakamafish-nsn.gov (509) 865-5121x6334
Roy Beaty Bonneville Power Administration Yes COR rebeaty@bpa.gov (503) 230-5213
Michelle Guay Bonneville Power Administration Yes Env. Compliance Lead mxguay@bpa.gov (503) 230-3459
Tana Hoptowit Yakama Confederated Tribes Yes Administrative Contact hopt@yakamafish-nsn.gov (509) 865-5121x6318
Cory Kamphaus Yakama Confederated Tribes Yes Technical Contact kamc@yakamafish-nsn.gov (509) 548-9413x102
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Keely Murdoch Yakama Confederated Tribes Yes Technical Contact murk@yakamafish-nsn.gov (509) 548-2206
Thomas Scribner Yakama Confederated Tribes Yes Contract Manager scrt@yakamafish-nsn.gov (503) 331-9850
Paul Ward Yakama Confederated Tribes No Supervisor warp@yakamafish-nsn.gov (509) 949-4129


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Obtain environmental compliance B: 165. Produce Environmental Compliance Documentation for all applicable work on Coho Reintroduction 01/31/2014 01/31/2014
Continue to develop operation plans and protocols C: 174. Hatchery Operations and Facility Plans 01/31/2014 01/31/2014
Conduct and document maintenance and repair activities D: 61. Subcontract O&M for maintenance of facilities 01/31/2014 01/31/2014
Manage and administer project, February 1, 2012 through January 31, 2014 E: 119. Manage and Administer 2012-2014 Project for Mid Columbia Coho Restoration 01/31/2014 01/31/2014
Acclimated smolts released F: 176. Acclimation/Release: Wenatchee: Coulter Creek pond (BY 2010) 06/10/2012 06/10/2012
Acclimated smolts released G: 176. Acclimation/Release: Wenatchee: Coulter Creek pond (BY 2011) 06/10/2013 06/12/2013
Acclimated smolts released H: 176. Acclimation/Release: Wenatchee: Beaver Creek pond (BY 2010) 06/10/2012 06/10/2012
Acclimated smolts released I: 176. Acclimation/Release: Wenatchee: Beaver Creek pond (BY 2011) 06/10/2013 06/12/2013
Acclimated smolts released J: 176. Acclimation/Release: Wenatchee: Rohlfing's pond (BY 2010) 06/09/2012 06/09/2012
Acclimated smolts released K: 176. Acclimation/Release: Wenatchee: Rohlfing's pond (BY 2011) 06/09/2013 06/12/2013
Acclimated smolts released L: 176. Acclimation/Release: Wenatchee: Nason Creek wetlands (BY 2010) 05/08/2012 05/08/2012
Acclimated smolts released M: 176. Acclimation/Release: Wenatchee: Butcher Creek Pond (BY 2010) 06/11/2012 06/11/2012
Acclimated smolts released N: 176. Acclimation/Release: Wenatchee: Butcher Creek Pond (BY 2011) 06/11/2013
Acclimated smolts released O: 176. Acclimation/Release: Wenatchee: Leavenworth NFH (BY 2010) 04/15/2012 04/15/2012
Acclimated smolts released P: 176. Acclimation/Release: Wenatchee: Leavenworth NFH (BY 2011) 04/15/2013 04/24/2013
Acclimated smolts released Q: 176. Acclimation/Release: Winthrop NFH back channel rearing (BY 2010) 06/01/2012 06/01/2012
Acclimated smolts released R: 176. Acclimation/Release: Winthrop NFH back channel rearing (BY 2011) 06/01/2013 06/04/2013
Acclimated smolts released S: 176. Acclimation/Release: Methow: Twisp Ponds (BY 2010) 06/07/2012 06/07/2012
Acclimated smolts released T: 176. Acclimation/Release: Methow: Twisp Ponds (BY 2011) 06/07/2013 05/22/2013
CWT tag fish BY2011 U: 158. Mark/Tag Animals - Subcontract CWT of approximately 1,500,000 BY11 coho pre-smolts 10/30/2012 10/30/2012
CWT tag fish BY2012 V: 158. Mark/Tag Animals - Subcontract CWT of approximately 1,750,000 BY12 coho pre-smolts 10/30/2013 10/30/2013
Collection of 2012 Coho Broodstock: Wenatchee and Methow programs W: 66. Trap 2012 broodstock at Dryden, Tumwater, Wells, LTP, Methow FH, Winthrop NFH, and LNFH 12/08/2012 12/08/2012
Collection of 2013 Coho Broodstock: Wenatchee and Methow programs X: 66. Trap 2013 broodstock at Dryden, Tumwater, Wells, LTP, Methow FH, Winthrop NFH, and LNFH 12/08/2013 12/08/2013
Spawn 2012 brood coho at Leavenworth NFH Y: 176. Spawn 2012 brood coho at Leavenworth NFH 11/28/2012 11/28/2012
Spawn 2013 brood coho at Leavenworth NFH Z: 176. Spawn 2013 brood coho at Leavenworth NFH 11/28/2013 11/28/2013
Spawn 2012 coho broodstock at Winthrop NFH AA: 176. Spawn 2012 brood coho at Winthrop NFH 11/26/2012 11/26/2012
Spawn 2013 coho broodstock at Winthrop NFH AB: 176. Spawn 2013 brood coho at Winthrop NFH 11/26/2013 11/26/2013
Carcass distribution for BY2013 broodstock AD: 44. Carcass dispersal of a portion of 2013 broodstock in the Wenatchee and 100% Methow River programs 01/31/2014 01/31/2014
Transport 2012 BY eyed coho eggs to rearing facilities AE: 66. Transport 2012 brood eyed-eggs from incubation facilities to rearing facilities 01/16/2013 01/16/2013
Transport 2013 BY eyed coho eggs to rearing facilities AF: 66. Transport 2013 brood eyed-eggs from incubation facilities to rearing facilities 01/16/2014 01/16/2014
Coho redd counts and spawning composition for the 2012 BY AG: 157. Conduct spawning ground surveys for the 2012 brood in the Wenatchee Basin 01/31/2013 01/31/2013
Coho redd counts and spawning composition for the 2013 BY AH: 157. Conduct spawning ground surveys for the 2013 brood in the Wenatchee Basin 01/31/2014 01/31/2014
2012 BY coho redd counts and spawning composition AI: 157. Conduct spawning ground surveys for the 2012 brood in the Methow Basin 12/31/2012 12/31/2012
2013 BY coho redd counts and spawning composition AJ: 157. Conduct spawning ground surveys for the 2013 brood in the Methow Basin 12/31/2013 12/31/2013
Completed database AK: 157. Collect biological data from 2012 coho brood at spawning 01/31/2013 01/31/2013
Completed database AL: 157. Collect biological data from 2013 coho brood at spawning 01/31/2014 01/31/2014
CWT recovery data from the 2012 BY AM: 157. Extract CWT from 2012 brood coho snouts collected at spawning and on spawning ground surveys 01/31/2013 01/31/2013
CWT recovery data from the 2013 BY AN: 157. Extract CWT from 2013 brood coho snouts collected at spawning and on spawning ground surveys 01/31/2014 01/31/2014
Out-plant a portion of 2013 coho returns: LNFH ladder to Nason Creek AP: 66. Outplant a portion of the 2013 returns collected at LNFH to the upper Wenatchee Basin 12/01/2013 12/01/2013
Juvenile fish transfer of the 2011 BY for overwintering at Leavenworth NFH AQ: 66. Transport BY11 coho from LCR facilities to LNFH for overwinter acclimation 12/15/2012 12/15/2012
Juvenile fish transfer of the 2011 BY for overwintering at Leavenworth NFH AR: 66. Transport BY12 coho from LCR facilities to LNFH for overwinter acclimation 12/15/2013 12/15/2013
PIT tag fish 2011 BY AS: 158. Mark/Tag Animals - PIT-tag 52,000 BY11 coho pre-smolts 01/31/2013 01/31/2013
PIT tag fish 2012 BY AT: 158. Mark/Tag Animals - PIT-tag 52,000 BY12 coho pre-smolts 01/31/2014 01/31/2014
Analyze data from 2011 BY AU: 162. Analyze and interpret M&E data from 2011 brood 01/31/2013 01/31/2013
Analyze data from 2012 BY AV: 162. Analyze and interpret M&E data from 2012 brood 01/31/2014 01/31/2014
Enter data AW: 160. Enter data into and maintain local databases 09/30/2013 09/30/2013
Collect data from 2010 and 2011BY AX: 157. Collect/Generate Field and Lab Data to determine 2012 emergence timing, growth and distribution 10/15/2012 10/15/2012
Collect data from 2011 and 2012BY AY: 157. Collect/Generate Field and Lab Data to determine 2013 emergence timing, growth and distribution 10/15/2013 10/15/2013
Finalize FY 11 progress report uploaded/attached in Pisces AZ: 132. Submit Annual Report for the FY11 period (10/1/10 to 1/31/12) 02/01/2013 12/31/2013
Finalize FY 12 progress report uploaded/attached in Pisces BA: 132. Submit Annual Report for the FY12 period (2/1/12 to 1/31/13) 01/31/2014
Tissue analysis by CRITFC for genetic monitoring BB: 157. Analyze genetic tissue samples for determination of potential divergence from founding LCR pop. 09/28/2012 09/28/2012
Finalize a comprehensive monitoring report uploaded/attached in Pisces BC: 132. Submit Comprehensive Report from feasibility to current BDP II 01/31/2014
Subcontract work for water availability and water tests BD: 175. * Water Evaluations and cost reimbursement permit tracking for MET/WEN sites 01/31/2014 01/31/2014
oversee and subcontract Butcher Creek dredging operation BE: 61. * % Subcontract work for Butcher Creek dredging project 04/01/2014 03/31/2014
Submit drawings and/or specifications to BPA BF: 175. * % Project management and permitting preparation for various MET/WEN sites 04/01/2014 11/04/2013

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Coho (O. kisutch) - Unspecified Population
  • 2 instances of WE 44 Enhance Nutrients in Water Bodies
  • 19 instances of WE 176 Produce Hatchery Fish
  • 8 instances of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 2 instances of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 174 Produce Plan
  • 2 instances of WE 175 Produce Design
  • 11 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 4 instances of WE 158 Mark/Tag Animals
  • 2 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/01/2012
B 165 Produce Environmental Compliance Documentation for all applicable work on Coho Reintroduction 02/01/2012
C 174 Hatchery Operations and Facility Plans 02/01/2012
D 61 Subcontract O&M for maintenance of facilities 02/01/2012
E 119 Manage and Administer 2012-2014 Project for Mid Columbia Coho Restoration 02/01/2012
F 176 Acclimation/Release: Wenatchee: Coulter Creek pond (BY 2010) 02/01/2012
G 176 Acclimation/Release: Wenatchee: Coulter Creek pond (BY 2011) 02/01/2012
H 176 Acclimation/Release: Wenatchee: Beaver Creek pond (BY 2010) 02/01/2012
I 176 Acclimation/Release: Wenatchee: Beaver Creek pond (BY 2011) 02/01/2012
J 176 Acclimation/Release: Wenatchee: Rohlfing's pond (BY 2010) 02/01/2012
K 176 Acclimation/Release: Wenatchee: Rohlfing's pond (BY 2011) 02/01/2012
L 176 Acclimation/Release: Wenatchee: Nason Creek wetlands (BY 2010) 02/01/2012
M 176 Acclimation/Release: Wenatchee: Butcher Creek Pond (BY 2010) 02/01/2012
N 176 Acclimation/Release: Wenatchee: Butcher Creek Pond (BY 2011) 02/01/2012
O 176 Acclimation/Release: Wenatchee: Leavenworth NFH (BY 2010) 02/01/2012
P 176 Acclimation/Release: Wenatchee: Leavenworth NFH (BY 2011) 02/01/2012
Q 176 Acclimation/Release: Winthrop NFH back channel rearing (BY 2010) 02/01/2012
R 176 Acclimation/Release: Winthrop NFH back channel rearing (BY 2011) 02/01/2012
S 176 Acclimation/Release: Methow: Twisp Ponds (BY 2010) 02/01/2012
T 176 Acclimation/Release: Methow: Twisp Ponds (BY 2011) 02/01/2012
U 158 Mark/Tag Animals - Subcontract CWT of approximately 1,500,000 BY11 coho pre-smolts 02/01/2012
V 158 Mark/Tag Animals - Subcontract CWT of approximately 1,750,000 BY12 coho pre-smolts 02/01/2012
W 66 Trap 2012 broodstock at Dryden, Tumwater, Wells, LTP, Methow FH, Winthrop NFH, and LNFH 02/01/2012
X 66 Trap 2013 broodstock at Dryden, Tumwater, Wells, LTP, Methow FH, Winthrop NFH, and LNFH 02/01/2012
Y 176 Spawn 2012 brood coho at Leavenworth NFH 02/01/2012
Z 176 Spawn 2013 brood coho at Leavenworth NFH 02/01/2012
AA 176 Spawn 2012 brood coho at Winthrop NFH 02/01/2012
AB 176 Spawn 2013 brood coho at Winthrop NFH 02/01/2012
AC 44 Carcass dispersal of a portion of 2012 broodstock in the Wenatchee and 100% Methow River programs 02/01/2012
AD 44 Carcass dispersal of a portion of 2013 broodstock in the Wenatchee and 100% Methow River programs 02/01/2012
AE 66 Transport 2012 brood eyed-eggs from incubation facilities to rearing facilities 02/01/2012
AF 66 Transport 2013 brood eyed-eggs from incubation facilities to rearing facilities 02/01/2012
AG 157 Conduct spawning ground surveys for the 2012 brood in the Wenatchee Basin 02/01/2012
AH 157 Conduct spawning ground surveys for the 2013 brood in the Wenatchee Basin 02/01/2012
AI 157 Conduct spawning ground surveys for the 2012 brood in the Methow Basin 02/01/2012
AJ 157 Conduct spawning ground surveys for the 2013 brood in the Methow Basin 02/01/2012
AK 157 Collect biological data from 2012 coho brood at spawning 02/01/2012
AL 157 Collect biological data from 2013 coho brood at spawning 02/01/2012
AM 157 Extract CWT from 2012 brood coho snouts collected at spawning and on spawning ground surveys 02/01/2012
AN 157 Extract CWT from 2013 brood coho snouts collected at spawning and on spawning ground surveys 02/01/2012
AO 66 Outplant a portion of the 2012 returns collected at LNFH to the upper Wenatchee Basin 02/01/2012
AP 66 Outplant a portion of the 2013 returns collected at LNFH to the upper Wenatchee Basin 02/01/2012
AQ 66 Transport BY11 coho from LCR facilities to LNFH for overwinter acclimation 02/01/2012
AR 66 Transport BY12 coho from LCR facilities to LNFH for overwinter acclimation 02/01/2012
AS 158 Mark/Tag Animals - PIT-tag 52,000 BY11 coho pre-smolts 02/01/2012
AT 158 Mark/Tag Animals - PIT-tag 52,000 BY12 coho pre-smolts 02/01/2012
AU 162 Analyze and interpret M&E data from 2011 brood 02/01/2012
AV 162 Analyze and interpret M&E data from 2012 brood 02/01/2012
AW 160 Enter data into and maintain local databases 02/01/2012
AX 157 Collect/Generate Field and Lab Data to determine 2012 emergence timing, growth and distribution 02/01/2012
AY 157 Collect/Generate Field and Lab Data to determine 2013 emergence timing, growth and distribution 02/01/2012
AZ 132 Submit Annual Report for the FY11 period (10/1/10 to 1/31/12) 02/01/2012
BA 132 Submit Annual Report for the FY12 period (2/1/12 to 1/31/13) 02/01/2012
BB 157 Analyze genetic tissue samples for determination of potential divergence from founding LCR pop. 02/01/2012
BC 132 Submit Comprehensive Report from feasibility to current BDP II 02/01/2012
BD 175 * Water Evaluations and cost reimbursement permit tracking for MET/WEN sites 05/07/2013
BE 61 * % Subcontract work for Butcher Creek dredging project 02/18/2014
BF 175 * % Project management and permitting preparation for various MET/WEN sites 02/01/2012