RSS Feed for updates to Project 2017-004-00 - Northern Pike Suppression and Monitoring Follow this via RSS feed. Help setting up RSS feeds?

Project Summary

Project 2017-004-00 - Northern Pike Suppression and Monitoring
Project Number:
2017-004-00
Title:
Northern Pike Suppression and Monitoring
Summary:
Northern Pike Esox lucius are a highly invasive fish species that can significantly reduce fish densities and cause large-scale changes in fish communities. Northern Pike pose significant threats to the Columbia River ecosystem as a result of predation and competition for food resources. In addition, they may pose an extinction risk for sensitive species. The increasing observations of Northern Pike in Lake Roosevelt prompted the Lake Roosevelt co-managers (Colville Confederated Tribes, Spokane Tribe of Indians, and Washington Department of Fish and Wildlife) to implement surveys to investigate abundance, diet, growth, origin, spawning locations, and movement patterns. Aggressive removal plans have been designed and are being implemented in the upper reaches of Lake Roosevelt and Kettle River.
The goal of the project is to suppress Northern Pike in Lake Roosevelt watershed and to prevent them from spreading further downstream in the Columbia River system. The co-managers will use a multi-teared approach that includes mechanical removal techniques, angler incentives, and limited monitoring and research.
Proposer:
Proponent Orgs:
Colville Confederated Tribes (Tribe)
Spokane Tribe (Tribe)
Starting FY:
2017
Ending FY:
2044
BPA PM:
Stage:
Implementation - Project Status Report
Area:
Province Subbasin %
Intermountain Columbia Upper 100.00%
Purpose:
Predation
Emphasis:
Predator Removal
Focal Species:
Burbot
Kokanee
Sturgeon, White - All Populations except Kootenai R. DPS
Trout, Bull
Trout, Interior Redband
Trout, Rainbow
Whitefish, Mountain
Species Benefit:
Anadromous: 0.0%   Resident: 100.0%   Wildlife: 0.0%
Special:
None
BiOp Association:
None

Contract(s):

73548 REL 133

Location: 48.717708° N, -118.120041° E

Dimensions: 4032 x 3024


Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

To see more detailed project budget information, please visit the "Project Budget" page

Decided Budget Transfers  (FY2023 - FY2025)

Acct FY Acct Type Amount Fund Budget Decision Date
FY2023 Expense $318,823 From: General FY23 SOY Budget Upload 06/01/2022
FY2023 Expense $308,263 From: Fish Accord - Colville Colville Tribe (CCT) 2023-2025 Accord Extension 09/30/2022
FY2023 Expense $87,794 From: Fish Accord - Colville Accord Transfers (CCT) 10/19/2022 10/19/2022
FY2023 Expense $172,714 From: General STOI FY23 03/23/2023
FY2023 Expense $43,791 To: Fish Accord - Colville Accord Transfers (CCT) 4/24/24 04/25/2024
FY2024 Expense $315,970 From: Fish Accord - Colville Colville Tribe (CCT) 2023-2025 Accord Extension 09/30/2022
FY2024 Expense $342,836 From: General FY24 SOY Budget Upload 06/01/2023
FY2024 Expense $30,737 From: Fish Accord - Colville Accord Transfers (CCT, Willamette) 10/20/2023 10/20/2023
FY2024 Expense $130,252 From: General Budget Transfers (Spokane) 11/2/2023 11/02/2023
FY2025 Expense $323,869 From: Fish Accord - Colville Colville Tribe (CCT) 2023-2025 Accord Extension 09/30/2022
FY2025 Expense $43,791 From: Fish Accord - Colville Accord Transfers (CCT) 4/24/24 04/25/2024

Pending Budget Decision?  No


Actual Project Cost Share

Current Fiscal Year — 2024   DRAFT
Cost Share Partner Total Proposed Contribution Total Confirmed Contribution
There are no project cost share contributions to show.
Previous Fiscal Years
Fiscal Year Total Contributions % of Budget
2023 $790,548 48%
2022 $607,649 43%
2021 $433,530 42%
2020 $648,079 53%
2019 $425,455 35%

Contracts

The table below contains contracts with the following statuses: Active, Closed, Complete, History, Issued.
* "Total Contracted Amount" column includes contracted amount from both capital and expense components of the contract.
Expense Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
73548 REL 49 SOW Colville Confederated Tribes 2017-004-00 EXP NORTHERN PIKE SUPPRESSION AND Closed $368,109 2/1/2019 - 1/31/2020
82671 SOW Spokane Tribe 2017-004-00 EXP STOI NORTHERN PIKE SUPPRESSION AND Closed $428,756 8/1/2019 - 9/30/2020
73548 REL 77 SOW Colville Confederated Tribes 2017-004-00 EXP NORTHERN PIKE SUPPRESSION AND MONITORING Closed $329,920 2/1/2020 - 1/31/2021
85528 SOW Spokane Tribe 2017-004-00 EXP STOI NORTHERN PIKE SUPPRESSION AND Closed $246,495 8/1/2020 - 7/31/2021
73548 REL 102 SOW Colville Confederated Tribes 2017-004-00 EXP NORTHERN PIKE SUPPRESSION AND MONITORING Closed $303,771 2/1/2021 - 1/31/2022
88384 SOW Spokane Tribe 2017-004-00 EXP STOI NORTHERN PIKE SUPPRESSION AND Closed $277,671 8/1/2021 - 7/31/2022
73548 REL 133 SOW Colville Confederated Tribes 2017-004-00 EXP NORTHERN PIKE SUPPRESSION AND MONITORING Closed $324,661 2/1/2022 - 1/31/2023
90671 SOW Spokane Tribe 2017-004-00 EXP STOI NORTHERN PIKE SUPPRESSION AND Issued $491,537 8/1/2022 - 7/31/2023
91803 SOW Colville Confederated Tribes 2017-004-00 EXP NORTHERN PIKE SUPPRESSION AND MONITORING Issued $396,057 2/1/2023 - 1/31/2024
92897 SOW Spokane Tribe 2017-004-00 EXP STOI NORTHERN PIKE SUPPRESSION AND Issued $491,537 8/1/2023 - 7/31/2024
84051 REL 10 SOW Colville Confederated Tribes 2017-004-00 EXP NORTHERN PIKE SUPPRESSION AND MONITORING Issued $346,707 2/1/2024 - 1/31/2025
CR-368335 SOW Spokane Tribe 2017-004-00 EXP STOI NORTHERN PIKE SUPPRESSION AND Pending $503,825 8/1/2024 - 7/31/2025



Annual Progress Reports
Expected (since FY2004):9
Completed:9
On time:9
Status Reports
Completed:45
On time:23
Avg Days Early:1

                Count of Contract Deliverables
Earliest Contract Subsequent Contracts Title Contractor Earliest Start Latest End Latest Status Accepted Reports Complete Green Yellow Red Total % Green and Complete Canceled
82671 85528, 88384, 90671, 92897, CR-368335 2017-004-00 EXP STOI NORTHERN PIKE SUPPRESSION AND Spokane Tribe 08/01/2019 07/31/2025 Pending 23 26 7 0 0 33 100.00% 0
Project Totals 23 26 7 0 0 33 100.00% 0


The table content is updated frequently and thus contains more recent information than what was in the original proposal reviewed by ISRP and Council.

Review: 2020 Resident Fish and Sturgeon Project Review

Council Recommendation

Assessment Number: 2017-004-00-NPCC-20210317
Project: 2017-004-00 - Northern Pike Suppression and Monitoring
Review: 2020 Resident Fish and Sturgeon Project Review
Approved Date: 10/27/2020
Recommendation: Implement
Comments: Bonneville to fund the implementation of Project #2017-004-00, Northern Pike Suppression and Monitoring as reviewed and recommended by the Council on June 13, 2018, and as updated for budget and scope of work through this review, while continuing to work with the relevant state agencies and tribes on a strategy to solicit and obtain contributions to this effort from other affected entities.
Part 3, Project-Specific Recommendation: Bonneville to fund the implementation of Project #2017-004-00, Northern Pike Suppression and Monitoring as reviewed and recommended by the Council on June 13, 2018, and as updated for budget and scope of work through this review, while continuing to work with the relevant state agencies and tribes on a strategy to solicit and obtain contributions to this effort from other affected entities.

[Background: See https:/www.nwcouncil.org/fw/reviews/2019RFS]

Independent Scientific Review Panel Assessment

Assessment Number: 2017-004-00-ISRP-20210319
Project: 2017-004-00 - Northern Pike Suppression and Monitoring
Review: 2020 Resident Fish and Sturgeon Project Review
Completed Date: None
Documentation Links:

Project Relationships: None

Name Role Organization
Edward Gresh Env. Compliance Lead Bonneville Power Administration
Holly McLellan Project Lead Colville Confederated Tribes
Carlos Matthew Interested Party Bonneville Power Administration
Brent Nichols Project Lead Spokane Tribe
Peter Lofy Supervisor Bonneville Power Administration
Joshua Ashline Interested Party Bonneville Power Administration
Joshua Ashline Project Manager Bonneville Power Administration