| Province | Subbasin | % |
|---|---|---|
| Columbia Plateau | Yakima | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Full Name | Organization | Write Permission | Contact Role | Work Phone | |
|---|---|---|---|---|---|
| James Greene | US Bureau of Reclamation (BOR) | No | Administrative Contact | jgreene@pn.usbr.gov | (208) 378-5071 |
| R. Dennis Hudson | US Bureau of Reclamation (BOR) | Yes | Contract Manager | rhudson@pn.usbr.gov | (208) 378-5250 |
| Paul Krueger | Bonneville Power Administration | Yes | F&W Approver | pqkrueger@bpa.gov | (503) 230-5723 |
| Jonathan McCloud | Bonneville Power Administration | Yes | COR | jmmccloud@bpa.gov | (503) 230-3110 |
| Khanida Mote | Bonneville Power Administration | Yes | Contracting Officer | kpmote@bpa.gov | (503) 230-4599 |
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Deliverable complete | A: 165. NEPA Compliance on Fogarty Ditch Fish Passage Improvements | 09/09/2005 | ||
| Deliverable complete | B: 6. Obtain Easements for Fogarty Fish Screen and Access Road | |||
| Deliverable complete | C: 119. Manage Project Locations and Final Plans | 09/09/2005 | ||
| Deliverable complete | D: 118. Meet With Landowners to Inform and Obtain Input to Project | 09/09/2005 | ||
| Deliverable complete | E: 118. Develop O&M Agreements with Landowners | |||
| Deliverable complete | F: 174. Fogarty Fish Screen Implementation Plan | 09/09/2005 | ||
| Deliverable complete | G: 119. Develop Fogarty Fish Screen Bid Package | 09/09/2005 | ||
| Deliverable complete | H: 174. Prepare Designer's Operation Criteria (DOC)/Facility Operation Manual | |||
| Deliverable complete | I: 119. Construction Management | 09/09/2005 | ||
| Deliverable complete | J: 119. Management and Coordination Activities | 09/09/2005 | ||
| Deliverable complete | K: 119. Manage and Administer Project | 09/26/2005 | ||
| Deliverable complete | L: 132. 2005 Annual Report | 09/26/2005 | ||
| Deliverable complete | M: 132. Yakima Fish Passage - Phase II Completion Report | 09/26/2005 |
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | NEPA Compliance on Fogarty Ditch Fish Passage Improvements | |||||||
| B | 6 | Obtain Easements for Fogarty Fish Screen and Access Road | |||||||
| C | 119 | Manage Project Locations and Final Plans | |||||||
| D | 118 | Meet With Landowners to Inform and Obtain Input to Project | |||||||
| E | 118 | Develop O&M Agreements with Landowners | |||||||
| F | 174 | Fogarty Fish Screen Implementation Plan | |||||||
| G | 119 | Develop Fogarty Fish Screen Bid Package | |||||||
| H | 174 | Prepare Designer's Operation Criteria (DOC)/Facility Operation Manual | |||||||
| I | 119 | Construction Management | |||||||
| J | 119 | Management and Coordination Activities | |||||||
| K | 119 | Manage and Administer Project | |||||||
| L | 132 | 2005 Annual Report | |||||||
| M | 132 | Yakima Fish Passage - Phase II Completion Report | |||||||
| N | 185 | Status Report |