Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
RSS Feed for updates to Project 1991-075-00 - Yakima Fish Screens Cons Bor Follow this via RSS feed. Help setting up RSS feeds?

Project Summary

Project 1991-075-00 - Yakima Fish Screens Cons Bor
Project Number:
1991-075-00
Title:
Yakima Fish Screens Cons Bor
Summary:
The Yakima Phase II Screens Construction program is an extension of the Phase I program that corrected fish passage conditions at about 16 major diversions in the Yakima River Basin. The Northwest Power Planning Council (now the Northwest Power and Conservation Council) authorized Bonneville Power Administration (BPA) to provide funding for Phase II screens through the Fish and Wildlife Program. BPA asked the Bureau of Reclamation (BOR) to plan, design, and supervise construction of the Phase II projects.
Proposer:
None
Proponent Orgs:
US Bureau of Reclamation (BOR) (Govt - Federal)
Starting FY:
1992
Ending FY:
2006
Stage:
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Purpose:
Habitat
Emphasis:
Restoration/Protection
Focal Species:
Chinook - Upper Columbia River Spring ESU
Coho - Unspecified Population
Lamprey, Pacific
Lamprey, Western Brook
Steelhead - Upper Columbia River DPS
Trout, Bull
Trout, Rainbow
Whitefish, Mountain
Species Benefit:
Anadromous: 100.0%   Resident: 0.0%   Wildlife: 0.0%
Tags:
None
Special:
None
BiOp Association:
None

No photos have been uploaded yet for this Project.

Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

To see more detailed project budget information, please visit the "Project Budget" page

No Decided Budget Transfers

Pending Budget Decision?  No


Actual Project Cost Share

Current Fiscal Year — 2024
Cost Share Partner Total Proposed Contribution Total Confirmed Contribution
There are no project cost share contributions to show.
Previous Fiscal Years
Fiscal Year Total Contributions % of Budget
There are no cost share summaries to display from previous years.

Contracts

The table below contains contracts with the following statuses: Active, Closed, Complete, History, Issued.
* "Total Contracted Amount" column includes contracted amount from both capital and expense components of the contract.
Capital Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
65 REL 2 SOW Geomax 1991-075-00 YAKIMA PHASE II FISH SCREENS CONSTRUCTION Terminated $9,659 8/1/2000 - 2/1/2001
311 REL 2 SOW US Bureau of Reclamation (BOR) 1991-075-00 YAKIM PHASE II FISH SCREENS CONSTRUCTION Terminated $1,406,377 10/1/2000 - 9/30/2001
4685 SOW Geomax 1991-075-00 - O & M OF YAKIMA PHASE II FISH SCREENS History $0 2/1/2001 - 7/1/2001
4655 SOW US Bureau of Reclamation (BOR) 1991-075-00 YAKIMA FISH SCREENS Closed $1,312,652 4/30/2001 - 9/30/2004
20034 SOW US Bureau of Reclamation (BOR) PI 199107500 YAKIMA FISH PASSAGE PHASE II CONSTRUCTION Closed $182,436 10/1/2004 - 9/30/2005
592 REL 19 SOW Eastern Washington University FOGERTY FISH SCREEN CR History $4,699 4/18/2005 - 5/27/2005
24728 SOW US Bureau of Reclamation (BOR) 1991-075-00 CAP YAKIMA FISH SCREEN CONSTRUCTION Closed $655,399 10/1/2005 - 12/31/2007
Expense Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
95 REL 1 SOW Selah Moxee Irrigation District 1991-075-00 YAKIMA PHASE II SCREENS - CONSTRUCTIONS History $3,203 2/28/2000 - 2/27/2001



Annual Progress Reports
Expected (since FY2004):3
Completed:3
On time:3
Status Reports
Completed:18
On time:11
Avg Days Late:0

                Count of Contract Deliverables
Earliest Contract Subsequent Contracts Title Contractor Earliest Start Latest End Latest Status Accepted Reports Complete Green Yellow Red Total % Green and Complete Canceled
4655 20034, 24728 1991-075-00 CAP YAKIMA FISH SCREEN CONSTRUCTION US Bureau of Reclamation (BOR) 04/30/2001 12/31/2007 Closed 18 19 0 0 3 22 86.36% 0
Project Totals 18 19 0 0 3 22 86.36% 0


The table content is updated frequently and thus contains more recent information than what was in the original proposal reviewed by ISRP and Council.

No assessments are available for this project.
Project Relationships: None

Name Role Organization
R. Dennis Hudson (Inactive) Project Lead US Bureau of Reclamation (BOR)
Jonathan McCloud Project Manager Bonneville Power Administration
David Byrnes (Inactive) Supervisor Bonneville Power Administration