Contract 20563: 2003-011-00 IMPLEMENT HABITAT RESTORATION FOR COLUMBIA R. ESTUARY
Project Number:
Title:
Columbia River Estuary Habitat Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia River Estuary Columbia Estuary 50.00%
Lower Columbia Columbia Lower 50.00%
Contract Number:
20563
Contract Title:
2003-011-00 IMPLEMENT HABITAT RESTORATION FOR COLUMBIA R. ESTUARY
Contract Continuation:
Previous: Next:
15125: 2003-011-00 IMPLEMENT HABITAT RESTORATION PROGRAM FOR COL R/EST
  • 25875: 2003-011-00 EXP IMPLEMENT HABITAT RESTORATION FOR COL. R/EST 06
Contract Status:
History
Contract Description:
Account Type(s):
Expense
Contract Start Date:
11/01/2004
Contract End Date:
10/31/2005
Current Contract Value:
$679,321
Expenditures:
$679,321

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Type:
Contract
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Matt Burlin Lower Columbia Estuary Partnership Yes Contract Manager burlin@lcrep.org (503) 226-1565x230
Matt Deniston Bonneville Power Administration Yes Interested Party fmdeniston@bpa.gov (503) 808-1204
Jill Leary Lower Columbia Estuary Partnership Yes leary@lcrep.org (503) 226-1565x235
Elida Monroe Bonneville Power Administration Yes Contracting Officer emonroe@bpa.gov (503) 230-3821
John Skidmore Bonneville Power Administration Yes F&W Approver jtskidmore@bpa.gov (503) 230-5494
Nancy Weintraub Bonneville Power Administration No Env. Compliance Lead nhweintraub@bpa.gov (503) 230-5373
Benjamin Zelinsky Bonneville Power Administration Yes COR bdzelinsky@bpa.gov (503) 230-4737


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Project partner list A: 114. Identify potential projects for 2006 funding cycle 08/01/2005 09/07/2005
Deliverable complete B: 119. Manage Projects, Estuary Partnership and BPA Admin Requirements 12/01/2006
Annual Report C: 132. Produce Annual Report 11/30/2005
Fort Columbia - NEPA Review D: 165. NEPA coverage for FY05 work 10/31/2005
Deliverable complete E: 175. Skam Ck - Develop construction and engineering plans for tidegate structures on Skamakowa Creek 08/31/2005 09/29/2005
Deliverable complete F: 157. Skam Ck - Establish baseline conditions for Skamakowa Creek 10/31/2005 09/09/2005
45,000 Plants G: 47. Sandy Riv - Plant native trees and shrubs in floodplain 09/09/2005 09/09/2005
Deliverable complete H: 47. Sandy Riv - Establish native grass seed cover 10/31/2005 10/31/2005
Deliverable complete I: 157. Sandy Riv - Conduct vegetation monitoring on Sandy River Delta 11/30/2005 10/31/2005
Deliverable complete J: 99. Sandy Riv - Create a Sandy River Delta restoration informational pamphlet 04/01/2005 09/09/2005
Deliverable complete K: 175. L+C - Conduct planning, engineering, and design of Lewis and Clark dike breach 06/30/2005 09/29/2005
Deliverable complete L: 180. L+C - Remove material for dike breaches 09/29/2005
Deliverable complete M: 30. L+C - Create tidal channels 10/31/2005 10/03/2005
Deliverable complete N: 47. L+C - Plant native trees and shrubs along channels and breaches 10/31/2005
Deliverable complete O: 157. L+C - Report of baseline habitat conditions 10/31/2005 10/31/2005
Deliverable complete P: 175. Fort Col - Develop construction plan for wetland restoration 10/31/2005 10/31/2005
Deliverable complete R: 174. Battelle - Develop strategic habitat restoration prioritization plan 11/30/2005 10/31/2005
Deliverable complete S: 184. Malarkey Ranch - Install bridge at Scappoose Barrier #294 on Honeyman Creek 09/30/2005 09/07/2005
Harborton - Pre-existing conditions monitoring T: 157. Harborton - Pre-existing conditions monitoring 08/31/2005

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
All Anadromous Salmonids
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 174 Produce Plan
  • 2 instances of WE 175 Produce Design
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Cutthroat Trout, Coastal (Oncorhynchus clarkii clarkii) - All Anadromous Populations
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (Oncorhynchus mykiss) - All Populations
  • 1 instance of WE 184 Install Fish Passage Structure

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 114 Identify potential projects for 2006 funding cycle
B 119 Manage Projects, Estuary Partnership and BPA Admin Requirements
C 132 Produce Annual Report
D 165 NEPA coverage for FY05 work
E 175 Skam Ck - Develop construction and engineering plans for tidegate structures on Skamakowa Creek
F 157 Skam Ck - Establish baseline conditions for Skamakowa Creek
G 47 Sandy Riv - Plant native trees and shrubs in floodplain
H 47 Sandy Riv - Establish native grass seed cover
I 157 Sandy Riv - Conduct vegetation monitoring on Sandy River Delta
J 99 Sandy Riv - Create a Sandy River Delta restoration informational pamphlet
K 175 L+C - Conduct planning, engineering, and design of Lewis and Clark dike breach
L 180 L+C - Remove material for dike breaches
M 30 L+C - Create tidal channels
N 47 L+C - Plant native trees and shrubs along channels and breaches
O 157 L+C - Report of baseline habitat conditions
P 175 Fort Col - Develop construction plan for wetland restoration
R 174 Battelle - Develop strategic habitat restoration prioritization plan
S 184 Malarkey Ranch - Install bridge at Scappoose Barrier #294 on Honeyman Creek
T 157 Harborton - Pre-existing conditions monitoring
U 185 Periodic Status Reports for BPA